What changed — Blue Owl Capital
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- Jul 15, 2025CoreWeave Lancaster Greenfield site · PA
- Construction started: Coreweave announces $6 billion investment into Lancaster data centers, at two former printing press sites.
Source: Epoch AI