CoreWeave Lancaster Greenfield site
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionJul 15, 2025
Model estimate · Satellite imagery
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityCoreWeave Lancaster Greenfield site
- →substationOn-site substation[1]Satellite imageryLikely1 substation outline traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 40.04731, -76.26045
- Address
- County
- Lancaster County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
- Investor
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2027-06-30); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Pennsylvania statewide average, July 2026.
- State avg. commercial price
Pennsylvania statewide average, July 2026.
- Generation within 50 km
43 EIA-reported plants within 50 km.
- Generation queued in county
2 active generation interconnection requests in Lancaster County: Solar 40 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Muddy Run · Constellation Power, Inc | Power plant (Pumped Storage) | 26.9 km | 1.06 GW | [6] |
| Peach Bottom · Constellation Nuclear | Power plant (Nuclear) | 32.1 km | 2.55 GW | [6] |
| York Energy Center · Calpine Mid-Merit LLC | Power plant (Natural Gas) | 34.7 km | 1.4 GW | [6] |
| Ironwood LLC · Helix Ironwood LLC | Power plant (Natural Gas) | 34.9 km | 760 MW | [6] |
| Wildcat Point Generation Facility · Old Dominion Electric Coop | Power plant (Natural Gas) | 37.4 km | 991 MW | [6] |
| Brunner Island · Brunner Island LLC | Power plant (Natural Gas) | 37.5 km | 1.41 GW | [6] |
| Essential Power Rock Springs LLC · Essential Power Operating Services LLC | Power plant (Natural Gas) | 37.5 km | 667 MW | [6] |
| Crane Clean Energy Center · Constellation Nuclear | Power plant (Nuclear) | 41 km | 803 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Holtwood SolarPJM AE1-226 | Solar | Suspended · proposed 2026-04 | 20 MW | [4] |
| Face Rock-Kinzer #13 69 kVPJM AI2-075 | Solar | In study · proposed 2023-07 | 20 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startJul 15, 2025[1]
- First operationalJun 30, 2027[1]Projected
- Expected completionJun 30, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-06-30); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | under construction | 124 MW | Jun 30, 2027 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Jul 15, 2025[1]
- Jul 13, 2026[1]
Cooling install continues on the roof, satellite imagery indicates that not all units have been completed. Continued presence of construction vehicles and unfinished land on the campus suggests that the building is not operational yet.
We estimate that Building 1 will be operational by Summer 2027 due to third party reporting.
All claims (provenance audit)
23| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | CoreWeave Lancaster Greenfield site | [1] | Likely | 2026-07-13 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-07-15 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-07-13 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-13 | Shown |
| Address | 216 Greenfield Rd, Lancaster, PA | [1] | Likely | 2026-07-13 | Shown |
| Owner | CoreWeaveOwner: CoreWeave | [1] | Confirmed | 2026-07-13 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Speculative | 2026-07-13 | Shown |
| Utility | PPL Electric Utilitiesterritory 14715: PPL ELECTRIC UTILITIES CORP (INVESTOR OWNED, PPL CORPORATION) | [2] derived | Likely | 2022 | Shown |
| Investors | Blue Owl CapitalInvestors: Blue Owl Capital | [1] | Confirmed | 2026-07-13 | Shown |
| Planned capacity | 124 MW | [1] estimated | Likely | 2026-07-13 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Generation queued in county | 40 MW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 11.04¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.86¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 12.09 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-07-13 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-07-13 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-07-15 | Superseded / alternative |
| Chip types | Rubin | [1] | Confirmed | 2026-07-13 | Shown |
| Construction start | Jul 15, 2025 | [1] derived | Likely | 2026-07-13 | Shown |
| First operational | Jun 30, 2027 | [1] estimated | Speculative | 2026-07-13 | Shown |
| Expected completion | Jun 30, 2027 | [1] estimated | Speculative | 2026-07-13 | Shown |