DC
/

CoreWeave Lancaster Greenfield site

Under constructionAI campusCampusLancaster County, Pennsylvania
60% profile completeness
23 claims from 8 sources
Current facility power
Not yet sourced
Planned capacity
124 MW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
Not yet sourced
First operational
Jun 30, 2027[1]
Speculativeestimated

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2027 – H1 2028
Medium confidencewindow, not a prediction
Project verification
Under construction
Construction documented by satellite imagery.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
PPL Electric Utilities · PJM
Substation: On-site substation

Power reality

Announced
124 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
124 MW[1]
Building 1 under construction (satellite-tracked phases)
Operational
No record
  • ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Construction elapsed: Construction documented since 2025-07-15 (1.2 years).
  • Stated date: Next projected milestone: 2027-06-30 (modeled/speculative)[1]
  • Required: 124 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • Construction to first power typically takes 1.25–2.5 years.
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H1 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionJul 15, 2025
    Model estimate · Satellite imagery
    • Jul 15, 2025 · Reported status: under construction[1]
    • Jul 15, 2025 · Construction start[1]
    • Jul 15, 2025 · [Coreweave announces $6 billion investment into Lancaster data centers, at two former printing press sites.](https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announ[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    CoreWeave Lancaster Greenfield site
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    1 substation outline traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    PPL Electric Utilities[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    PJM[3]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
40.04731, -76.26045
Address
216 Greenfield Rd, Lancaster, PA[1]Likely
County
Lancaster County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    OpenAI[1]Speculative
Power supply
Capital & construction

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
CoreWeave[1]Confirmed
End user
OpenAI[1]Speculative
Utility

Location falls inside this utility's retail service territory.

Investor

Power (all fields)

Planned capacity
124 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-06-30); not necessarily full build-out.

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[3]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
11.04¢/kWh[5]Confirmed

Pennsylvania statewide average, July 2026.

State avg. commercial price
13.86¢/kWh[5]Confirmed

Pennsylvania statewide average, July 2026.

Generation within 50 km
12.09 GW[6]Confirmedderived

43 EIA-reported plants within 50 km.

Generation queued in county
40 MW[4]Confirmedderived

2 active generation interconnection requests in Lancaster County: Solar 40 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Muddy Run · Constellation Power, IncPower plant (Pumped Storage)26.9 km1.06 GW[6]
Peach Bottom · Constellation NuclearPower plant (Nuclear)32.1 km2.55 GW[6]
York Energy Center · Calpine Mid-Merit LLCPower plant (Natural Gas)34.7 km1.4 GW[6]
Ironwood LLC · Helix Ironwood LLCPower plant (Natural Gas)34.9 km760 MW[6]
Wildcat Point Generation Facility · Old Dominion Electric CoopPower plant (Natural Gas)37.4 km991 MW[6]
Brunner Island · Brunner Island LLCPower plant (Natural Gas)37.5 km1.41 GW[6]
Essential Power Rock Springs LLC · Essential Power Operating Services LLCPower plant (Natural Gas)37.5 km667 MW[6]
Crane Clean Energy Center · Constellation NuclearPower plant (Nuclear)41 km803 MW[6]
Largest queued generation in this countyFuelQueue statusMWSource
Holtwood SolarPJM AE1-226SolarSuspended · proposed 2026-0420 MW[4]
Face Rock-Kinzer #13 69 kVPJM AI2-075SolarIn study · proposed 2023-0720 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Jul 15, 2025[1]
  5. First operational
    Jun 30, 2027[1]
    Projected
  6. Expected completion
    Jun 30, 2027[1]
    Projected
Planned capacity
124 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-06-30); not necessarily full build-out.

Buildings (planned)
1[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
0[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1under construction124 MWJun 30, 2027 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
Rubin[1]Confirmed

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

Construction start: Jul 15, 2025[1]
First operational: Jun 30, 2027[1]
  1. Jul 15, 2025[1]

    Coreweave announces $6 billion investment into Lancaster data centers, at two former printing press sites.

  2. Jul 13, 2026[1]

    Cooling install continues on the roof, satellite imagery indicates that not all units have been completed. Continued presence of construction vehicles and unfinished land on the campus suggests that the building is not operational yet.

  3. Jun 30, 2027Projected124 MW facility power· 1 buildings operational[1]

    We estimate that Building 1 will be operational by Summer 2027 due to third party reporting.

All claims (provenance audit)

23
FieldValueSourceConfidenceAs ofStatus
NameCoreWeave Lancaster Greenfield site[1] Likely2026-07-13Shown
StatusUnder construction[1] derivedLikely2025-07-15Superseded / alternative
StatusUnder construction[1] derivedLikely2026-07-13Shown
Facility typeAI campus[1] derivedLikely2026-07-13Shown
Address216 Greenfield Rd, Lancaster, PA[1] Likely2026-07-13Shown
OwnerCoreWeaveOwner: CoreWeave[1] Confirmed2026-07-13Shown
End usersOpenAIUsers: OpenAI[1] Speculative2026-07-13Shown
UtilityPPL Electric Utilitiesterritory 14715: PPL ELECTRIC UTILITIES CORP (INVESTOR OWNED, PPL CORPORATION)[2] derivedLikely2022Shown
InvestorsBlue Owl CapitalInvestors: Blue Owl Capital[1] Confirmed2026-07-13Shown
Planned capacity124 MW[1] estimatedLikely2026-07-13Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[3] derivedLikely—Shown
Balancing authorityPJM[2] derivedLikely—Shown
Generation queued in county40 MW[4] derivedConfirmed2026-09-27Shown
State avg. industrial price11.04¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price13.86¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km12.09 GW[6] derivedConfirmed202502Shown
Buildings (planned)1[1] derivedLikely2026-07-13Shown
Buildings operational0[1] estimatedLikely2026-07-13Shown
Buildings operational0[1] estimatedLikely2025-07-15Superseded / alternative
Chip typesRubin[1] Confirmed2026-07-13Shown
Construction startJul 15, 2025[1] derivedLikely2026-07-13Shown
First operationalJun 30, 2027[1] estimatedSpeculative2026-07-13Shown
Expected completionJun 30, 2027[1] estimatedSpeculative2026-07-13Shown