What changed — Distribution Land Corp

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. May 28, 2026
    Meta Prometheus · OH
    • Land acquired: Deed/transfer recorded for parcel 095-112218-00.000 (no sale price disclosed).
  2. May 18, 2026
    Meta Prometheus · OH
    • Current IT capacity: 368 MW → 496 MW
    • Current facility power: 478 MW → 645 MW
    • Buildings operational: 6 → 11
    • New capacity online: Building 7-11 (Meta tents) are operational. In January we saw them look almost complete, with some work still ongoing for power equipment. Assuming 3 more months for commissioning, we expect operation by May. Northern…
    Source: Epoch AI
  3. Jan 18, 2026
    Meta Prometheus · OH
    • Current IT capacity: 76 MW → 368 MW
    • Current facility power: 99 MW → 478 MW
    • Buildings operational: 1 → 6
    • New capacity online: Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equipment lining their…
    Source: Epoch AI
  4. Oct 14, 2025
    Meta Prometheus · OH
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. The on-site power …
    Source: Epoch AI