RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- Jul 23, 2026
- May 31, 2026Anthropic Lake Mariner · NY
- Buildings operational: 0 → 1
- Status: Under construction → Operating + expanding
- New capacity online: Building 1 is operational. On February 26, Terawulf stated that CB3 was expected to be energized by mid-May 2026. A drone video commissioned from RAAD shows several cooling units operating on May 8. It's therefore lik…
Source: Epoch AI - Mar 31, 2026Core42 Lake Mariner · NY
- Current IT capacity: 16 MW → 58 MW
- Current facility power: 19 MW → 58 MW
- Buildings operational: 1 → 2
- New capacity online: Building 2 is operational. On February 26, Terawulf stated that CB2A is operational, presumably making up half the final capacity. CB2B was expected in March 2026. However, it's notable that a drone video commissioned…
Source: Epoch AI - Oct 1, 2025Core42 Lake Mariner · NY
- Buildings operational: 0 → 1
- Status: Under construction → Operating + expanding
- New capacity online: Building 1 is operational. Based on Terawulf saying "As of September 30, 2025, the site has energized 245 MW of Bitcoin-mining capacity and 22.5 MW of HPC capacity." The small "Wulf Den" building was said to be 2 MW o…
Source: Epoch AI - Jun 11, 2025Anthropic Lake Mariner · NY
- Construction started: Land clearing begins for Building 1 (AKA CB3).
Source: Epoch AI - Oct 1, 2024Core42 Lake Mariner · NY
- Construction started: Land clearing begins for Building 1, also known as CB-1, the first large AI/HPC building on the site.
Source: Epoch AI - Jan 23, 2024Anthropic Lake Mariner · NY
- Permit / site plan filed: NYISO load interconnection request 1670 filed (250 MW).
Source: New York ISO - Jan 23, 2024Core42 Lake Mariner · NY
- Permit / site plan filed: NYISO load interconnection request 1670 filed (250 MW).
Source: New York ISO