Core42 Lake Mariner
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Feasibility study
ISO/RTO queue
- NYISO load request 1670 (250 MW): Status 6 (SRIS/SIS approved); studies available: SIS; proposed initial backfeed: 02-2027 (queue status as of 2026-09-27)[2]
- System impact study
ISO/RTO queue
- NYISO load request 1670 (250 MW): Status 6 (SRIS/SIS approved); studies available: SIS; proposed initial backfeed: 02-2027 (queue status as of 2026-09-27)[2]
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionOct 1, 2024
- EnergizationOct 1, 2025
Satellite imagery
- Oct 1, 2025 · Building 1 is operational. Based on Terawulf [saying](https://investors.terawulf.com/news-events/press-releases/detail/126/terawulf-reports-third-quarter-2025-results) "As of Septe[1]
- Mar 31, 2026 · Building 2 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025[1]
- OperationalOct 1, 2025
Satellite imagery
- Oct 1, 2025 · Building 1 is operational. Based on Terawulf [saying](https://investors.terawulf.com/news-events/press-releases/detail/126/terawulf-reports-third-quarter-2025-results) "As of Septe[1]
- Mar 31, 2026 · Building 2 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: ISO/RTO queue, Model estimate, Satellite imagery.
Grid path
- →facilityCore42 Lake Mariner
- →substationKintigh 345kV Substation[2]Queue POILikelyPoint of interconnection in NYISO load request 1670
- →transmission345 kV[2]Queue POILikelyVoltage at the requested point of interconnection (Kintigh 345kV Substation)
- →utilityNiagara Mohawk Power Corp.[3]Service territoryLikelyRetail service territory containing the site · Transmission owner (queue): NYSEG
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
NYISO 1670 Lake Mariner Data II · Lake Mariner Data LLC | This site's load request Likely Request name/customer shares “mariner” with this facility, in the same county. | System impact study Status 6 (SRIS/SIS approved); studies available: SIS; proposed initial backfeed: 02-2027 | 250 | — | Jan 23, 2024 | Feb 2027 | Kintigh 345kV Substation TO: NYSEG | [2] Sep 27, 2026 |
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 43.35707, -78.60405
- Address
- County
- Niagara County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Developer
Interconnection customer on the load request.
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: New York State Elec & Gas Corp.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
58 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Interconnection status
- Load interconnection request
NYISO load interconnection request 1670 (Data center (AI)).
- State avg. industrial price
New York statewide average, July 2026.
- State avg. commercial price
New York statewide average, July 2026.
- Generation within 50 km
47 EIA-reported plants within 50 km.
- Generation queued in county
2 active generation interconnection requests in Niagara County: Solar 225 MW. Queued projects often don't get built.
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Slayton Settlement Road Solar Csg · RPNY Solar 3, LLC | Power plant (Solar) | 17.4 km | 7 MW | [7] |
| Lockport Energy Associates LP · Lockport Energy Associates LP | Power plant (Natural Gas) | 24.5 km | 219 MW | [7] |
| Modern Innovative Energy LLC · Innovative Energy Systems Inc | Power plant (Biomass) | 34.8 km | 6 MW | [7] |
| Model City Energy Facility · Model City Energy LLC | Power plant (Biomass) | 34.8 km | 6 MW | [7] |
| World Generation X · North American Energy Services | Power plant (Natural Gas) | 39.9 km | 52 MW | [7] |
| Lewiston Niagara · New York Power Authority | Power plant (Pumped Storage) | 41.4 km | 240 MW | [7] |
| Robert Moses Niagara · New York Power Authority | Power plant (Hydroelectric) | 42.6 km | 2.44 GW | [7] |
| Reworld Niagara I · Reworld Niagara I, LLC | Power plant (Biomass) | 44.5 km | 36 MW | [7] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Somerset SolarNYISO 1079 · Somerset Solar, LLC | Solar | IA signed · proposed 2028-06 | 125 MW | [2] |
| Bear Ridge SolarNYISO 0704 · Bear Ridge Solar, LLC | Solar | IA signed · proposed 2028-04 | 100 MW | [2] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Oct 1, 2024[1]
Land clearing begins for Building 1, also known as CB-1, the first large AI/HPC building on the site.
Building 1 is operational. Based on Terawulf saying "As of September 30, 2025, the site has energized 245 MW of Bitcoin-mining capacity and 22.5 MW of HPC capacity." The small "Wulf Den" building was said to be 2 MW of IT power while CB-1 would be 16 MW. This is roughly consistent with 22.5 MW of total facility power. This building is leased to Core42, a subsidiary of UAE-based G42. It likely uses NVIDIA DGX B200 servers.
Buildings 1 and 2 both appear to have complete building and cooling equipment, based on satellite imagery. Not considering Building 2 operational yet, due to Terawulf's statement that CB2B is expected in March 2026, and is likely still in commissioning phase.
Building 2 is operational. On February 26, Terawulf stated that CB2A is operational, presumably making up half the final capacity. CB2B was expected in March 2026. However, it's notable that a drone video commissioned from RAAD showed no cooling fan movement on May 8th, suggesting it was not in use. This building is leased to Core42, a subsidiary of UAE-based G42. It likely uses NVIDIA DGX B200 servers.
Both buildings still operational according to satellite imagery.
- Jan 23, 2024[2]
NYISO load interconnection request 1670 filed (250 MW).
Proposed initial backfeed / in-service for NYISO load request 1670.
All claims (provenance audit)
41| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Core42 Lake Mariner | [1] | Likely | 2026-07-23 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-10-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-02 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-31 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-07-23 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-23 | Shown |
| Address | 7725 Lake Rd, Barker, NY 14012 | [1] | Likely | 2026-07-23 | Shown |
| Owner | Core42Owner: Core42 | [1] | Confirmed | 2026-07-23 | Shown |
| Developer | Lake Mariner Data LLC | [2] | Likely | 2026-09-27 | Shown |
| End users | G42Users: G42 | [1] | Likely | 2026-07-23 | Shown |
| Utility | Niagara Mohawk Power Corp.territory 13573: NIAGARA MOHAWK POWER CORP. (INVESTOR OWNED, NATIONAL GRID GROUP | [3] derived | Unverified | 2022 | Shown |
| Investors | GoogleInvestors: Google | [1] | Confirmed | 2026-07-23 | Shown |
| Current facility power | 58 MW | [1] estimated | Likely | 2026-07-23 | Shown |
| Current facility power | 19 MW | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Current facility power | 19 MW | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Current facility power | 58 MW | [1] estimated | Likely | 2026-03-31 | Superseded / alternative |
| Current IT capacity | 58 MW | [1] estimated | Likely | 2026-07-23 | Shown |
| Current IT capacity | 16 MW | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Current IT capacity | 16 MW | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Current IT capacity | 58 MW | [1] estimated | Likely | 2026-03-31 | Superseded / alternative |
| Estimated annual consumption | 356 GWh/yr | [4] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | NYISONEW YORK INDEPENDENT SYSTEM OPERATOR | [5] derived | Likely | — | Shown |
| Balancing authority | NYIS | [3] derived | Likely | — | Shown |
| Interconnection status | NYISO load request 1670: 250 MW, in study at Kintigh 345kV SubstationStatus 6 (SRIS/SIS approved); studies available: SIS; proposed initial backfeed: | [2] | Confirmed | 2026-09-27 | Shown |
| Load interconnection request | 250 MW | [2] | Confirmed | 2026-09-27 | Shown |
| Generation queued in county | 225 MW | [2] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.81¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 24.18¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.16 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-07-23 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-07-23 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-10-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2026-03-31 | Superseded / alternative |
| Capital cost / investment | $2.2B | [1] estimated | Likely | 2026-07-23 | Shown |
| Compute (H100-equivalents) | 71,800 | [1] estimated | Likely | 2026-07-23 | Shown |
| Chip types | B200 | [1] | Confirmed | 2026-07-23 | Shown |
| Construction start | Oct 1, 2024 | [1] derived | Likely | 2026-07-23 | Shown |
| First operational | Oct 1, 2025 | [1] derived | Likely | 2026-07-23 | Shown |