What changed — MidAmerican Energy
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- Jul 7, 2026Google Council Bluffs (East) · IA
- Current IT capacity: 158 MW → 237 MW
- Current facility power: 190 MW → 284 MW
- Buildings operational: 2 → 3
- Status: Operating + expanding → Operating
- New capacity online: Building 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Cooling towers models vary slightly between buildings. Ground clearing to the south…
Source: Epoch AI - Jun 16, 2026
- Jun 15, 2025Google Council Bluffs (East) · IA
- Current IT capacity: 79 MW → 158 MW
- Current facility power: 95 MW → 190 MW
- Buildings operational: 1 → 2
- New capacity online: Building 2 is operational. Assuming it takes 3 months after generators and cooling towers are finished, similar to Building 1.
Source: Epoch AI - Mar 1, 2025Microsoft Project Osmium · IA
- Current IT capacity: 95 MW → 190 MW
- Current facility power: 114 MW → 228 MW
- Buildings operational: 2 → 4
- New capacity online: Building 3-4 operational, no visible construction.
Source: Epoch AI - Nov 19, 2024Google Council Bluffs (East) · IA
- Buildings operational: 0 → 1
- Status: Under construction → Operating + expanding
- New capacity online: Building 1 is operational. Google Earth shows Building 1 had all backup generators and cooling towers installed by the end of August, but construction work was ongoing and there were almost no cars parked. By February…
Source: Epoch AI - Jun 14, 2024