Google Council Bluffs (East)
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationNov 19, 2024
Satellite imagery
- Nov 19, 2024 · Building 1 is operational. Google Earth shows Building 1 had all backup generators and cooling towers installed by the end of August, but construction work was ongoing and there we[1]
- Jun 15, 2025 · Building 2 is operational. Assuming it takes 3 months after generators and cooling towers are finished, similar to Building 1.[1]
- Jul 7, 2026 · Building 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Cooling towers models vary slightly between bu[1]
- OperationalNov 19, 2024
Satellite imagery
- Nov 19, 2024 · Building 1 is operational. Google Earth shows Building 1 had all backup generators and cooling towers installed by the end of August, but construction work was ongoing and there we[1]
- Jun 15, 2025 · Building 2 is operational. Assuming it takes 3 months after generators and cooling towers are finished, similar to Building 1.[1]
- Jul 7, 2026 · Building 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Cooling towers models vary slightly between bu[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Council Bluffs (East)
- →substationSatellite imageryLikely4 substation outlines traced inside the campus on satellite imagery; OSM maps Southland Substation 0.37 km away
- →transmission345 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.01 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.17163, -95.79595
- Address
- County
- Pottawattamie County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- End user
- Utility
Location falls inside this utility's retail service territory.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
284 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside overlapping MISO and SPP footprints; chosen by the balancing areas of the overlapping utilities.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Iowa statewide average, July 2026.
- State avg. commercial price
Iowa statewide average, July 2026.
- Generation within 50 km
11 EIA-reported plants within 50 km.
- Generation queued in county
1 active generation interconnection requests in Pottawattamie County: Wind 200 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 345 kV line | Transmission line | 0.01 km | 345 kV | [5] |
| 69 kV line · MidAmerican Energy | Transmission line | 0.41 km | 69 kV | [5] |
| 161 kV line · MidAmerican Energy | Transmission line | 0.47 km | 161 kV | [5] |
| Walter Scott Jr Energy Center · MidAmerican Energy Co | Power plant (Coal) | 3.9 km | 1.51 GW | [8] |
| Jones Street · Omaha Public Power District | Power plant (Petroleum) | 13.8 km | 124 MW | [8] |
| Sarpy County · Omaha Public Power District | Power plant (Natural Gas) | 14.6 km | 316 MW | [8] |
| North Omaha · Omaha Public Power District | Power plant (Coal) | 21.5 km | 564 MW | [8] |
| Cass County · Omaha Public Power District | Power plant (Natural Gas) | 28.6 km | 324 MW | [8] |
| Fort Calhoun Community Solar · DG Southwest Solar Portfolio 2019, LLC | Power plant (Solar) | 36.2 km | 5 MW | [8] |
| Elk City Station · Omaha Public Power District | Power plant (Biomass) | 45 km | 6 MW | [8] |
| Platteview Solar LLC · AES Distributed Energy | Power plant (Solar) | 48.9 km | 81 MW | [8] |
| Southland Substation · MidAmerican Energy | Substation | 0.37 km | 345 kV | [5] |
| Unnamed substation | Substation | 0.37 km | 345 kV | [5] |
| Unnamed substation | Substation | 0.51 km | 345 kV | [5] |
| MidAmerican Energy substation · MidAmerican Energy | Substation | 0.64 km | 345 kV | [5] |
| Unnamed substation | Substation | 0.71 km | 345 kV | [5] |
| Bunge Substation · MidAmerican Energy | Substation | 1.84 km | 161 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J2990 at Overland - J1859 POI 345kV Line TapMISO J2990 | Wind | In study · proposed 2025-06 | 200 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity
- Current facility power
- Buildings operational
- Status
Timeline
- Sep 6, 2022[1]
Land clearing begins for east buildings
Building 1 is operational. Google Earth shows Building 1 had all backup generators and cooling towers installed by the end of August, but construction work was ongoing and there were almost no cars parked. By February 2025, Google Earth shows no construction work and many cars. So our best guess is in the middle, in November 2024. Building 3 roof is complete.
Building 2 is operational. Assuming it takes 3 months after generators and cooling towers are finished, similar to Building 1.
Land clearing begins in the southwest, suggesting more buildings are planned.
Building 3 has all 34 backup generators installed and 4 cooling towers installed, with 3 more cooling towers under construction. There are gaps between cooling towers suggesting that more could be added. Buildings 1 and 2 are running close to full capacity, given that water vapor is coming out of 5 of 7 cooling towers for each building. The land cleared in the southwest appears to be shaped for two more similar buildings, with notches for substations.
Building 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Cooling towers models vary slightly between buildings. Ground clearing to the southwest seems to be setting up for two more buildings.
Buildings on this campus
16- GoogleOperating · 76,100 sq ft footprint
- GoogleOperating · 319,200 sq ft footprint
- GoogleOperating · 258,500 sq ft footprint
- GoogleOperating · 211,700 sq ft footprint
- GoogleOperating · 131,600 sq ft footprint
- GoogleOperating · 129,900 sq ft footprint
- GoogleOperating · 132,200 sq ft footprint
- GoogleOperating · 132,400 sq ft footprint
- GoogleOperating · 130,900 sq ft footprint
- GoogleOperating · 129,700 sq ft footprint
- GoogleOperating · 134,600 sq ft footprint
- GoogleOperating · 174,400 sq ft footprint
- GoogleOperating · 174,700 sq ft footprint
- GoogleOperating · 158,400 sq ft footprint
- GoogleOperating · 295,000 sq ft footprint
- GoogleOperating · 297,100 sq ft footprint
All claims (provenance audit)
47| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Council Bluffs (East) | [1] | Likely | 2026-07-07 | Shown |
| Status | Under construction | [1] derived | Likely | 2022-09-06 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-11-19 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-06-15 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-07-19 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-01-11 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-07-07 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-07 | Shown |
| Address | 10410 Bunge Ave, Council Bluffs, IA 51503 | [1] | Likely | 2026-07-07 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-07-07 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Speculative | 2026-07-07 | Shown |
| Utility | MidAmerican Energyterritory 12341: MIDAMERICAN ENERGY CO (INVESTOR OWNED, BERKSHIRE HATHAWAY ENERG | [2] derived | Likely | 2022 | Shown |
| Current facility power | 284 MW | [1] estimated | Likely | 2026-07-07 | Shown |
| Current facility power | 95 MW | [1] estimated | Likely | 2024-11-19 | Superseded / alternative |
| Current facility power | 190 MW | [1] estimated | Likely | 2025-06-15 | Superseded / alternative |
| Current facility power | 190 MW | [1] estimated | Likely | 2025-07-19 | Superseded / alternative |
| Current facility power | 190 MW | [1] estimated | Likely | 2026-01-11 | Superseded / alternative |
| Current IT capacity | 237 MW | [1] estimated | Likely | 2026-07-07 | Shown |
| Current IT capacity | 79 MW | [1] estimated | Likely | 2024-11-19 | Superseded / alternative |
| Current IT capacity | 158 MW | [1] estimated | Likely | 2025-06-15 | Superseded / alternative |
| Current IT capacity | 158 MW | [1] estimated | Likely | 2025-07-19 | Superseded / alternative |
| Current IT capacity | 158 MW | [1] estimated | Likely | 2026-01-11 | Superseded / alternative |
| Estimated annual consumption | 1,741 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | SOUTHWEST POWER P | [4] derived | Likely | — | Shown |
| Balancing authority | MISO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Southland Substation (345 kV)way/545122717 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 200 MW | [6] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.99¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.27¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.94 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 5 | [1] derived | Likely | 2026-07-07 | Shown |
| Buildings operational | 3 | [1] estimated | Likely | 2026-07-07 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2022-09-06 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-11-19 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-06-15 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-07-19 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2026-01-11 | Superseded / alternative |
| Capital cost / investment | $9B | [1] estimated | Likely | 2026-07-07 | Shown |
| Compute (H100-equivalents) | 255,700 | [1] estimated | Likely | 2026-07-07 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-07-07 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-07-07 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-07-07 | Shown |
| Chip types | TPU v7 | [1] | Confirmed | 2026-07-07 | Shown |
| Construction start | Sep 6, 2022 | [1] derived | Likely | 2026-07-07 | Shown |
| First operational | Nov 19, 2024 | [1] derived | Likely | 2026-07-07 | Shown |