Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. May 2, 2026
    Meta Eagle Mountain · UT
    • Status: Operating + expanding → Operating
    Source: Epoch AI
  2. Dec 7, 2025
    Meta Eagle Mountain · UT
    • Buildings operational: 0 → 2
    • Status: Under construction → Operating + expanding
    • New capacity online: Buildings 1 and 2 both estimated to be operational 90 days after testing was underway in September.
    Source: Epoch AI
  3. Oct 1, 2023
    Meta Eagle Mountain · UT
    • Construction started: Land clearing begins.
    Source: Epoch AI
  4. Oct 1, 2023
    QTS Eagle Mountain · UT
    • Construction started: First signs of site preparation show up on satellite imagery.
    Source: Epoch AI