Meta Eagle Mountain

OperatingAI campusCampusEagle Mountain, Utah County, Utah
70% profile completeness
35 claims from 9 sources
Current facility power
179 MW[1]
Likelyestimated
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
$5B[1]
Likelyestimated
First operational
Dec 7, 2025[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
PacifiCorp · None (non-RTO region)
Substation: On-site substation

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
179 MW[1]
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionOct 1, 2023
    Model estimate · Satellite imagery
    • Oct 1, 2023 · Reported status: under construction[1]
    • Oct 1, 2023 · Construction start[1]
    • Oct 1, 2023 · Land clearing begins.[1]
    • Dec 7, 2025 · Reported status: expanding[1]
  3. EnergizationDec 7, 2025
    Satellite imagery
    • Dec 7, 2025 · Buildings 1 and 2 both estimated to be operational 90 days after testing was underway in September.[1]
  4. OperationalDec 7, 2025
    Satellite imagery
    • Dec 7, 2025 · Buildings 1 and 2 both estimated to be operational 90 days after testing was underway in September.[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Meta Eagle Mountain
  2. substation
    On-site substation[1][5]
    Satellite imageryLikely
    2 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.24 km away
  3. transmission
    345 kV line[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.23 km away). Not confirmed as the supply path.
  4. utility
    PacifiCorp[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[4]
    Service territoryLikely
    Balancing authority: PACW, PACE
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
40.26781, -112.01951
Address
1275 N Community Cir, Eagle Mountain, UT 84005[1]Likely
County
Utah County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Energy partner:
Utility:
Capital & construction
Contractor:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Meta[1]Confirmed
End user
Meta[1]Confirmed
Utility

Location falls inside this utility's retail service territory.

Energy partner
Williams[1]Confirmed
Contractor
Mortenson[1]Confirmed

Power (all fields)

Current facility power
179 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
133 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
1,098 GWh/yr[3]Speculativeestimated

179 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[4]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
PACW, PACE[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (345 kV)[5]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.2 km[5]Likelyderived
Highest-voltage line nearby
345 kV[5]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.10¢/kWh[6]Confirmed

Utah statewide average, July 2026.

State avg. commercial price
10.85¢/kWh[6]Confirmed

Utah statewide average, July 2026.

Generation within 50 km
1.72 GW[7]Confirmedderived

21 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
345 kV lineTransmission line0.23 km345 kV[5]
Lake Side Power Plant · PacifiCorpPower plant (Natural Gas)23.6 km1.18 GW[7]
Byu Central Heating Plant · Brigham Young University (BYU)Power plant (Natural Gas)31.8 km14 MW[7]
Nebo Power Station · Utah Associated Mun Power SysPower plant (Natural Gas)33.7 km130 MW[7]
Whitehead · City of Springville - (UT)Power plant (Natural Gas)35.2 km24 MW[7]
Spanish Fork Wind Park 2 LLC · Spanish Fork Wind Park 2, LLCPower plant (Wind)43.1 km19 MW[7]
West Valley Generation Project · Utah Municipal Power AgencyPower plant (Natural Gas)44.4 km185 MW[7]
Murray Turbine · City of Murray - (UT)Power plant (Natural Gas)46 km36 MW[7]
Clover Creek Solar Community Solar · AES Distributed EnergyPower plant (Solar)48.8 km80 MW[7]
Unnamed substationSubstation0.24 km345 kV[5]
PacifiCorp substation · PacifiCorpSubstation0.76 km345 kV[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Oct 1, 2023[1]
  5. First operational
    Dec 7, 2025[1]
  6. Expected completion
    —
Buildings (planned)
2[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
2[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Buildings 1–2operational179 MWDec 7, 2025[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$5B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
B300[1]Confirmed
Compute (H100-equivalents)
151,400[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Buildings operational
    0Oct 1, 2023[1]→2Dec 7, 2025[1]
  • Status
    Under constructionOct 1, 2023[1]→Operating + expandingDec 7, 2025[1]→OperatingMay 2, 2026[1]

Timeline

Construction start: Oct 1, 2023[1]
First operational: Dec 7, 2025[1]
  1. Oct 1, 2023[1]

    Land clearing begins.

  2. Sep 8, 2025[1]

    We believe Buildings 1 and 2 are still undergoing testing due to construction equipment and unfinished land surrounding the data center sites, as well as color motion artifacts on a small number of the cooling fans.

  3. Dec 7, 2025179 MW facility power· 2 buildings operational[1]

    Buildings 1 and 2 both estimated to be operational 90 days after testing was underway in September.

  4. May 2, 2026179 MW facility power· 2 buildings operational[1]

    Satellite image shows strong evidence that Buildings 1 and 2 are operational: colored motion artifacts on many cooling fans, plus cars parked at the building entrances.

Buildings on this campus

5
  • MetaOperating · 345,200 sq ft footprint
  • MetaOperating · 627,100 sq ft footprint
  • MetaOperating · 628,900 sq ft footprint
  • MetaOperating · 379,200 sq ft footprint
  • MetaOperating · 310,500 sq ft footprint

All claims (provenance audit)

35
FieldValueSourceConfidenceAs ofStatus
NameMeta Eagle Mountain[1] Likely2026-05-02Shown
StatusUnder construction[1] derivedLikely2023-10-01Superseded / alternative
StatusUnder construction[1] derivedLikely2025-09-08Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-12-07Superseded / alternative
StatusOperating[1] derivedLikely2026-05-02Shown
Facility typeAI campus[1] derivedLikely2026-05-02Shown
Address1275 N Community Cir, Eagle Mountain, UT 84005[1] Likely2026-05-02Shown
OwnerMetaOwner: Meta[1] Confirmed2026-05-02Shown
End usersMetaUsers: Meta[1] Confirmed2026-05-02Shown
UtilityPacifiCorpterritory 14354: PACIFICORP (INVESTOR OWNED, PACIFICORP)[2] derivedLikely2022Shown
Energy partnersWilliamsEnergy companies: Williams[1] Confirmed2026-05-02Shown
ConstructionMortensonConstruction companies: Mortenson[1] Confirmed2026-05-02Shown
Current facility power179 MW[1] estimatedLikely2026-05-02Shown
Current facility power179 MW[1] estimatedLikely2025-12-07Superseded / alternative
Current IT capacity133 MW[1] estimatedLikely2026-05-02Shown
Current IT capacity133 MW[1] estimatedLikely2025-12-07Superseded / alternative
Estimated annual consumption1,098 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTONone (non-RTO region)[4] derivedLikely—Shown
Balancing authorityPACW, PACE[2] derivedLikely—Shown
Nearest mapped substationUnnamed substation (345 kV)way/1473440687[5] derivedLikely2026-09-28Shown
Distance to substation0.2 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[5] derivedLikely2026-09-28Shown
State avg. industrial price9.10¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price10.85¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km1.72 GW[7] derivedConfirmed202502Shown
Buildings (planned)2[1] derivedLikely2026-05-02Shown
Buildings operational2[1] estimatedLikely2026-05-02Shown
Buildings operational0[1] estimatedLikely2023-10-01Superseded / alternative
Buildings operational0[1] estimatedLikely2025-09-08Superseded / alternative
Buildings operational2[1] estimatedLikely2025-12-07Superseded / alternative
Capital cost / investment$5B[1] estimatedLikely2026-05-02Shown
Compute (H100-equivalents)151,400[1] estimatedLikely2026-05-02Shown
Chip typesB300[1] Confirmed2026-05-02Shown
Construction startOct 1, 2023[1] derivedLikely2026-05-02Shown
First operationalDec 7, 2025[1] derivedLikely2026-05-02Shown