DC
/

QTS Eagle Mountain

Under constructionAI campusCampusEagle Mountain, Utah County, Utah
50% profile completeness
25 claims from 8 sources
Current facility power
Not yet sourced
Planned capacity
411 MW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
Not yet sourced
First operational
Dec 31, 2026[1]
Speculativeestimated

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2027 – H2 2027
Medium confidencewindow, not a prediction
Project verification
Under construction
Construction documented by satellite imagery.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
PacifiCorp · None (non-RTO region)
Substation: On-site substation

Power reality

Announced
411 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
411 MW[1]
Buildings 1–2, Building 3 under construction (satellite-tracked phases)
Operational
No record
  • ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Construction elapsed: Construction documented since 2023-10-01 (3.0 years).
  • Stated date: Next projected milestone: 2026-12-31 (modeled/speculative)[1]
  • Required: 411 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • Construction to first power typically takes 1.25–2.5 years.
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2027

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionOct 1, 2023
    Model estimate · Satellite imagery
    • Oct 1, 2023 · Reported status: under construction[1]
    • Oct 1, 2023 · Construction start[1]
    • Oct 1, 2023 · First signs of site preparation show up on satellite imagery.[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    QTS Eagle Mountain
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    1 substation outline traced inside the campus on satellite imagery
  3. transmission
    345 kV line[4]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.7 km away). Not confirmed as the supply path.
  4. utility
    PacifiCorp[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[3]
    Service territoryLikely
    Balancing authority: PACW, PACE
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
40.26596, -112.03057
Address
652 E Hyperscale Way, Eagle Mountain, UT 84013[1]Likely
County
Utah County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Meta[1]Speculative
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
End user
Meta[1]Speculative
Utility

Location falls inside this utility's retail service territory.

Power (all fields)

Planned capacity
411 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[3]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
PACW, PACE[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (345 kV)[4]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.7 km[4]Likelyderived
Highest-voltage line nearby
345 kV[4]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.10¢/kWh[5]Confirmed

Utah statewide average, July 2026.

State avg. commercial price
10.85¢/kWh[5]Confirmed

Utah statewide average, July 2026.

Generation within 50 km
1.72 GW[6]Confirmedderived

21 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
345 kV lineTransmission line0.7 km345 kV[4]
Lake Side Power Plant · PacifiCorpPower plant (Natural Gas)24.6 km1.18 GW[6]
Byu Central Heating Plant · Brigham Young University (BYU)Power plant (Natural Gas)32.7 km14 MW[6]
Nebo Power Station · Utah Associated Mun Power SysPower plant (Natural Gas)34.2 km130 MW[6]
Whitehead · City of Springville - (UT)Power plant (Natural Gas)36.1 km24 MW[6]
Spanish Fork Wind Park 2 LLC · Spanish Fork Wind Park 2, LLCPower plant (Wind)43.8 km19 MW[6]
West Valley Generation Project · Utah Municipal Power AgencyPower plant (Natural Gas)44.6 km185 MW[6]
Murray Turbine · City of Murray - (UT)Power plant (Natural Gas)46.5 km36 MW[6]
Clover Creek Solar Community Solar · AES Distributed EnergyPower plant (Solar)48.8 km80 MW[6]
Unnamed substationSubstation0.72 km345 kV[4]
PacifiCorp substation · PacifiCorpSubstation1.17 km345 kV[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Oct 1, 2023[1]
  5. First operational
    Dec 31, 2026[1]
    Projected
  6. Expected completion
    Jul 1, 2027[1]
    Projected
Planned capacity
411 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.

Buildings (planned)
2[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
0[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Buildings 1–2under construction274 MWDec 31, 2026 (projected)[1]
Building 3under construction137 MWJul 1, 2027 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
B300[1]Confirmed

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

Construction start: Oct 1, 2023[1]
First operational: Dec 31, 2026[1]
  1. Oct 1, 2023[1]

    First signs of site preparation show up on satellite imagery.

  2. Sep 8, 2025[1]

    Site preparation continues. Outline of a first building that is not the data center of interest Buildings 1 or 2 is visible.

  3. May 2, 2026[1]

    Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emergency generator install continues as well.

  4. Dec 31, 2026Projected274 MW facility power· 2 buildings operational[1]

    We estimate Buildings 1 and 2 will be fully operational by the end of 2026 because there are at least seven months since cooling and emergency generators have started to be installed. This estimate is also in line with similar QTS data center campus construction timelines.

  5. Jul 1, 2027Projected411 MW facility power· 3 buildings operational[1]

    We estimate Building 3 will be fully operational by H2 2027 following a similar time line to Buildings 1 and 2 of 14 months from land clearing to operational.

All claims (provenance audit)

25
FieldValueSourceConfidenceAs ofStatus
NameQTS Eagle Mountain[1] Likely2026-05-02Shown
StatusUnder construction[1] derivedLikely2023-10-01Superseded / alternative
StatusUnder construction[1] derivedLikely2025-09-08Superseded / alternative
StatusUnder construction[1] derivedLikely2026-05-02Shown
Facility typeAI campus[1] derivedLikely2026-05-02Shown
Address652 E Hyperscale Way, Eagle Mountain, UT 84013[1] Likely2026-05-02Shown
End usersMetaUsers: Meta[1] Speculative2026-05-02Shown
UtilityPacifiCorpterritory 14354: PACIFICORP (INVESTOR OWNED, PACIFICORP)[2] derivedLikely2022Shown
Planned capacity411 MW[1] estimatedLikely2026-05-02Shown
ISO / RTONone (non-RTO region)[3] derivedLikely—Shown
Balancing authorityPACW, PACE[2] derivedLikely—Shown
Nearest mapped substationUnnamed substation (345 kV)way/1473440687[4] derivedLikely2026-09-28Shown
Distance to substation0.7 km[4] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[4] derivedLikely2026-09-28Shown
State avg. industrial price9.10¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price10.85¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km1.72 GW[6] derivedConfirmed202502Shown
Buildings (planned)2[1] derivedLikely2026-05-02Shown
Buildings operational0[1] estimatedLikely2026-05-02Shown
Buildings operational0[1] estimatedLikely2023-10-01Superseded / alternative
Buildings operational0[1] estimatedLikely2025-09-08Superseded / alternative
Chip typesB300[1] Confirmed2026-05-02Shown
Construction startOct 1, 2023[1] derivedLikely2026-05-02Shown
First operationalDec 31, 2026[1] estimatedSpeculative2026-05-02Shown
Expected completionJul 1, 2027[1] estimatedSpeculative2026-05-02Shown