What changed — Sdc Phxa4 LLC
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- May 1, 2026Stream Phoenix · AZ
- Buildings operational: 0 → 1
- Status: Under construction → Operating + expanding
- New capacity online: Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the building will be operational.
Source: Epoch AI - Jun 17, 2025Stream Phoenix · AZ
- Land acquired: Deed recorded for parcel 500-07-997 (owner of record: Sdc Phxa4 LLC).