Stream Phoenix

Operating + expandingAI campusCampusMaricopa County, Arizona
60% profile completeness
42 claims from 11 sources
Current facility power
77 MW[1]
Likelyestimated
Planned capacity
267 MW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
$2.4B[1]
Likelyestimated
First operational
May 1, 2026[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H2 2028 – H2 2030
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery and government record.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Salt River Project · None (non-RTO region)
Substation: On-site substation

Power reality

Announced
267 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
190 MW[1]
Buildings 2–6 under construction (satellite-tracked phases)
Operational
77 MW[1]
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1][2]
  • Stated date: Next projected milestone: 2030-01-01 (modeled/speculative)[1]
  • Required: 267 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H2 2028 – H2 2030

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredJun 17, 2025
    Government record
    • Jun 17, 2025 · Land acquisition / deed recorded[2]
    • Jun 17, 2025 · Deed recorded for parcel 500-07-997 (owner of record: Sdc Phxa4 LLC).[2]
    • Jun 17, 2025 · Deed recorded for parcel 500-07-994 (owner of record: Sdc Phx II LLC).[2]
    • Jun 17, 2025 · Deed recorded for parcel 500-07-999 (owner of record: Sdc Phxa7 LLC).[2]
    • Sep 27, 2026 · Owner of record in county parcel data[2]
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionOct 30, 2022
    Model estimate · Satellite imagery
    • Oct 30, 2022 · Reported status: under construction[1]
    • Oct 30, 2022 · Construction start[1]
    • Oct 30, 2022 · Construction beginning, as can be seen on satellite. Major renovations on western side of the non AI building (PX1), including adding generators and cooling towers.[1]
    • May 1, 2026 · Reported status: expanding[1]
  3. EnergizationMay 1, 2026
    Satellite imagery
    • May 1, 2026 · Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the[1]
  4. OperationalMay 1, 2026
    Satellite imagery · Government record
    • May 1, 2026 · Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the[1]
    • Sep 27, 2026 · County land use: Property use code 0021[2]
    • Sep 27, 2026 · County land use: Property use code 1507[2]
    • Sep 27, 2026 · County land use: Property use code 2815[2]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.

Grid path

  1. facility
    Stream Phoenix
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    1 substation outline traced inside the campus on satellite imagery
  3. transmission
    Palo Verde - Rudd 500KV[6]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (1.28 km away). Not confirmed as the supply path.
  4. utility
    Salt River Project[3]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[5]
    Service territoryLikely
    Balancing authority: SRP
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
33.41391, -112.35968
Address
2950 S. Litchfield Road[1]Likely
County
Maricopa County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility

Most likely retail provider among 11 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Wapa-- Western Area Power Administration, Electrical Dist No8 Maricopa, Usbia-San Carlos Project, Gila River Indian Utility Authority (Gricua), Maricopa County M W C Dist #1, Buckeye Water C&D District, ….

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
77 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
64 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
267 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2030-01-01); not necessarily full build-out.

Estimated annual consumption
472 GWh/yr[4]Speculativeestimated

77 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[5]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
SRP[3]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (69 kV)[6]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.6 km[6]Likelyderived
Highest-voltage line nearby
500 kV[6]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.35¢/kWh[8]Confirmed

Arizona statewide average, July 2026.

State avg. commercial price
13.12¢/kWh[8]Confirmed

Arizona statewide average, July 2026.

Generation within 50 km
11.7 GW[9]Confirmedderived

40 EIA-reported plants within 50 km.

Generation queued in county
1.12 GW[7]Confirmedderived

5 active generation interconnection requests in Maricopa County: Solar + storage 1,100 MW, Solar 20 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
69 kV lineTransmission line0.64 km69 kV[6]
230 kV lineTransmission line0.7 km230 kV[6]
345 kV lineTransmission line0.97 km345 kV[6]
Palo Verde - Rudd 500KV · Arizona Public ServiceTransmission line1.28 km500 kV[6]
Jojoba - Kyrene 500KV · Arizona Public ServiceTransmission line1.46 km500 kV[6]
West Phoenix · Arizona Public Service CoPower plant (Natural Gas)18.9 km909 MW[9]
Agua Fria · Salt River ProjectPower plant (Natural Gas)20.7 km741 MW[9]
Ocotillo · Arizona Public Service CoPower plant (Natural Gas)41.5 km605 MW[9]
Red Hawk · Arizona Public Service CoPower plant (Natural Gas)45.5 km1 GW[9]
Palo Verde · Arizona Public Service CoPower plant (Nuclear)46.7 km3.94 GW[9]
Mesquite Generating Station Block 2 · Mesquite Power LLCPower plant (Natural Gas)47.5 km624 MW[9]
Mesquite Generating Station Block 1 · Salt River ProjectPower plant (Natural Gas)47.5 km620 MW[9]
Arlington Valley Energy Facility · Arlington Valley LLCPower plant (Natural Gas)49.9 km580 MW[9]
Unnamed substationSubstation0.61 km69 kV[6]
Unnamed substationSubstation0.95 km230 kV[6]
Largest queued generation in this countyFuelQueue statusMWSource
HARQUAHALA FLATS 2CAISO 2027Solar + storageIn study · proposed 2028-04400 MW[7]
HARQUAHALA SUNRISECAISO 1678Solar + storageIn study · proposed 2030-04300 MW[7]
VULCANCAISO 1534Solar + storageIn study · proposed 2027-12250 MW[7]
HARQUAHALA SUNRISE 2CAISO 2029Solar + storageIn study · proposed 2026-09150 MW[7]
AGUA CALIENTE SOLAR 2CAISO 1222SolarIn study · proposed 2016-1220 MW[7]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    Jun 17, 2025[2]
  3. Permitting
    —
  4. Construction start
    Oct 30, 2022[1]
  5. First operational
    May 1, 2026[1]
  6. Expected completion
    Jan 1, 2030[1]
    Projected
Planned capacity
267 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2030-01-01); not necessarily full build-out.

Buildings (planned)
2[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
1[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational77 MWMay 1, 2026[1]
Buildings 2–6under construction190 MWJan 1, 2030 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year
  • $4.2M[2]
    Full cash value · tax year 2027 · parcel 500-07-997
  • $1.7M[2]
    Limited property value (taxable basis) · tax year 2027 · parcel 500-07-997
  • $87.2M[2]
    Full cash value · tax year 2027 · parcel 500-07-994
  • $48.8M[2]
    Limited property value (taxable basis) · tax year 2027 · parcel 500-07-994
  • $68.1M[2]
    Full cash value · tax year 2027 · parcel 500-07-999
  • $38.2M[2]
    Limited property value (taxable basis) · tax year 2027 · parcel 500-07-999
Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

ParcelRecord ownerAcresZoning / useBuilding sq ftSource
500-07-997
Maricopa County, AZ
SDC PHXA4 LLC
2001 ROSS AVE STE 400 DALLAS TX USA 75201
14.71CONTACT LOCAL JURISDICTION · Property use code 0021—[2]
500-07-994
Maricopa County, AZ
SDC PHX II LLC
2001 ROSS AVE STE 400 DALLAS TX USA 75201
16.9CONTACT LOCAL JURISDICTION · Property use code 1507—[2]
500-07-999
Maricopa County, AZ
SDC PHXA7 LLC
2001 ROSS AVE STE 400 DALLAS TX USA 75201
21.51CONTACT LOCAL JURISDICTION · Property use code 2815—[2]
Site area
53.1 acres[2]Confirmed

Sum of county land area across parcels.

Land use
Property use code 0021[2]Confirmed
Capital cost / investment
$2.4B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced
Nearby comparable transactions

Size

Parcel / land records
500-07-997 (Maricopa County),500-07-994 (Maricopa County),500-07-999 (Maricopa County)[2]Confirmed
Floor area
Not yet sourced

Compute

Chip types
H100[1]Confirmed
Compute (H100-equivalents)
46,100[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Buildings operational
    0Oct 30, 2022[1]→1May 1, 2026[1]
  • Status
    Under constructionOct 30, 2022[1]→Operating + expandingMay 1, 2026[1]
  • Assessed value (official)
    $4.2M2027[10]→$163.7M2027[2]→$159.5M2027[2]

Timeline

Construction start: Oct 30, 2022[1]
First operational: May 1, 2026[1]
  1. Oct 30, 2022[1]

    Construction beginning, as can be seen on satellite. Major renovations on western side of the non AI building (PX1), including adding generators and cooling towers.

  2. Jan 31, 2026[1]

    Major construction has finished on AI building 1, and AI building 6 has been expedited, as depicted by satellite imagery.

  3. May 1, 202677 MW facility power· 1 buildings operational[1]

    Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the building will be operational.

  4. Jan 1, 2030Projected267 MW facility power· 6 buildings operational[1]

    Although official promotional sources estimate the campus to be fully operational in 10-12 years, it is likely to be finished sooner than this given the empirical durations for other data center campuses as well as because AI building 6 has been expedited. The first AI building took approximately 24 months to complete. Assuming construction for a new building starts midway for every building, then the campus will be complete in 4 years for the 5 remaining buildings, since AI buildings 2 and 6 are both underway.

  5. Jun 17, 2025[2]

    Deed recorded for parcel 500-07-997 (owner of record: Sdc Phxa4 LLC).

  6. Jun 17, 2025[2]

    Deed recorded for parcel 500-07-994 (owner of record: Sdc Phx II LLC).

  7. Jun 17, 2025[2]

    Deed recorded for parcel 500-07-999 (owner of record: Sdc Phxa7 LLC).

Buildings on this campus

1

All claims (provenance audit)

42
FieldValueSourceConfidenceAs ofStatus
NameStream Phoenix[1] Likely2026-05-01Shown
StatusUnder construction[1] derivedLikely2022-10-30Superseded / alternative
StatusUnder construction[1] derivedLikely2026-01-31Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-05-01Shown
Facility typeAI campus[1] derivedLikely2026-05-01Shown
Address2950 S. Litchfield Road[1] Likely2026-05-01Shown
Property owner of recordSdc Phxa4 LLCParcel 500-07-997: SDC PHXA4 LLC[2] Confirmed2026-09-27Shown
Property owner of recordSdc Phx II LLCParcel 500-07-994: SDC PHX II LLC[2] Confirmed2026-09-27Shown
Property owner of recordSdc Phxa7 LLCParcel 500-07-999: SDC PHXA7 LLC[2] Confirmed2026-09-27Shown
UtilitySalt River Projectterritory 16572: SALT RIVER PROJECT (POLITICAL SUBDIVISION, SALT RIVER PROJECT)[3] derivedUnverified2022Shown
Current facility power77 MW[1] estimatedLikely2026-05-01Shown
Current IT capacity64 MW[1] estimatedLikely2026-05-01Shown
Planned capacity267 MW[1] estimatedLikely2026-05-01Shown
Estimated annual consumption472 GWh/yr[4] estimatedSpeculative2026-09-29Shown
ISO / RTONone (non-RTO region)[5] derivedLikely—Shown
Balancing authoritySRP[3] derivedLikely—Shown
Nearest mapped substationUnnamed substation (69 kV)way/938592731[6] derivedLikely2026-09-28Shown
Distance to substation0.6 km[6] derivedLikely2026-09-28Shown
Highest-voltage line nearby500 kV[6] derivedLikely2026-09-28Shown
Generation queued in county1.12 GW[7] derivedConfirmed2026-09-27Shown
State avg. industrial price9.35¢/kWh[8] Confirmed2026-07Shown
State avg. commercial price13.12¢/kWh[8] Confirmed2026-07Shown
Generation within 50 km11.7 GW[9] derivedConfirmed202502Shown
Buildings (planned)2[1] derivedLikely2026-05-01Shown
Buildings operational1[1] estimatedLikely2026-05-01Shown
Buildings operational0[1] estimatedLikely2022-10-30Superseded / alternative
Buildings operational0[1] estimatedLikely2026-01-31Superseded / alternative
Site area53.1 acres[2] Confirmed2026-09-27Shown
Capital cost / investment$2.4B[1] estimatedLikely2026-05-01Shown
Parcel / land records500-07-997 (Maricopa County)[2] Confirmed2026-09-27Shown
Parcel / land records500-07-994 (Maricopa County)[2] Confirmed2026-09-27Shown
Parcel / land records500-07-999 (Maricopa County)[2] Confirmed2026-09-27Shown
Assessed value (official)$159.5M[2] Confirmed2027Shown
Land useProperty use code 0021[2] Confirmed2026-09-27Shown
Land useProperty use code 1507[2] Confirmed2026-09-27Superseded / alternative
Land useProperty use code 2815[2] Confirmed2026-09-27Superseded / alternative
Compute (H100-equivalents)46,100[1] estimatedLikely2026-05-01Shown
Chip typesH100[1] Confirmed2026-05-01Shown
Land acquiredJun 17, 2025[2] derivedConfirmed2026-09-27Shown
Construction startOct 30, 2022[1] derivedLikely2026-05-01Shown
First operationalMay 1, 2026[1] derivedLikely2026-05-01Shown
Expected completionJan 1, 2030[1] estimatedSpeculative2026-05-01Shown