Stream Phoenix
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredJun 17, 2025
Government record
- Jun 17, 2025 · Land acquisition / deed recorded[2]
- Jun 17, 2025 · Deed recorded for parcel 500-07-997 (owner of record: Sdc Phxa4 LLC).[2]
- Jun 17, 2025 · Deed recorded for parcel 500-07-994 (owner of record: Sdc Phx II LLC).[2]
- Jun 17, 2025 · Deed recorded for parcel 500-07-999 (owner of record: Sdc Phxa7 LLC).[2]
- Sep 27, 2026 · Owner of record in county parcel data[2]
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionOct 30, 2022
Model estimate · Satellite imagery
- Oct 30, 2022 · Reported status: under construction[1]
- Oct 30, 2022 · Construction start[1]
- Oct 30, 2022 · Construction beginning, as can be seen on satellite. Major renovations on western side of the non AI building (PX1), including adding generators and cooling towers.[1]
- May 1, 2026 · Reported status: expanding[1]
- EnergizationMay 1, 2026
Satellite imagery
- May 1, 2026 · Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the[1]
- OperationalMay 1, 2026
Satellite imagery · Government record
- May 1, 2026 · Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the[1]
- Sep 27, 2026 · County land use: Property use code 0021[2]
- Sep 27, 2026 · County land use: Property use code 1507[2]
- Sep 27, 2026 · County land use: Property use code 2815[2]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.
Grid path
- →facilityStream Phoenix
- →substationOn-site substation[1]Satellite imageryLikely1 substation outline traced inside the campus on satellite imagery
- →transmissionPalo Verde - Rudd 500KV[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.28 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 33.41391, -112.35968
- Address
- County
- Maricopa County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- Utility
Most likely retail provider among 11 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Wapa-- Western Area Power Administration, Electrical Dist No8 Maricopa, Usbia-San Carlos Project, Gila River Indian Utility Authority (Gricua), Maricopa County M W C Dist #1, Buckeye Water C&D District, ….
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2030-01-01); not necessarily full build-out.
- Estimated annual consumption
77 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Arizona statewide average, July 2026.
- State avg. commercial price
Arizona statewide average, July 2026.
- Generation within 50 km
40 EIA-reported plants within 50 km.
- Generation queued in county
5 active generation interconnection requests in Maricopa County: Solar + storage 1,100 MW, Solar 20 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 69 kV line | Transmission line | 0.64 km | 69 kV | [6] |
| 230 kV line | Transmission line | 0.7 km | 230 kV | [6] |
| 345 kV line | Transmission line | 0.97 km | 345 kV | [6] |
| Palo Verde - Rudd 500KV · Arizona Public Service | Transmission line | 1.28 km | 500 kV | [6] |
| Jojoba - Kyrene 500KV · Arizona Public Service | Transmission line | 1.46 km | 500 kV | [6] |
| West Phoenix · Arizona Public Service Co | Power plant (Natural Gas) | 18.9 km | 909 MW | [9] |
| Agua Fria · Salt River Project | Power plant (Natural Gas) | 20.7 km | 741 MW | [9] |
| Ocotillo · Arizona Public Service Co | Power plant (Natural Gas) | 41.5 km | 605 MW | [9] |
| Red Hawk · Arizona Public Service Co | Power plant (Natural Gas) | 45.5 km | 1 GW | [9] |
| Palo Verde · Arizona Public Service Co | Power plant (Nuclear) | 46.7 km | 3.94 GW | [9] |
| Mesquite Generating Station Block 2 · Mesquite Power LLC | Power plant (Natural Gas) | 47.5 km | 624 MW | [9] |
| Mesquite Generating Station Block 1 · Salt River Project | Power plant (Natural Gas) | 47.5 km | 620 MW | [9] |
| Arlington Valley Energy Facility · Arlington Valley LLC | Power plant (Natural Gas) | 49.9 km | 580 MW | [9] |
| Unnamed substation | Substation | 0.61 km | 69 kV | [6] |
| Unnamed substation | Substation | 0.95 km | 230 kV | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| HARQUAHALA FLATS 2CAISO 2027 | Solar + storage | In study · proposed 2028-04 | 400 MW | [7] |
| HARQUAHALA SUNRISECAISO 1678 | Solar + storage | In study · proposed 2030-04 | 300 MW | [7] |
| VULCANCAISO 1534 | Solar + storage | In study · proposed 2027-12 | 250 MW | [7] |
| HARQUAHALA SUNRISE 2CAISO 2029 | Solar + storage | In study · proposed 2026-09 | 150 MW | [7] |
| AGUA CALIENTE SOLAR 2CAISO 1222 | Solar | In study · proposed 2016-12 | 20 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquiredJun 17, 2025[2]
- Permitting—
- Construction startOct 30, 2022[1]
- First operationalMay 1, 2026[1]
- Expected completionJan 1, 2030[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2030-01-01); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
- $4.2M[2]Full cash value · tax year 2027 · parcel 500-07-997
- $1.7M[2]Limited property value (taxable basis) · tax year 2027 · parcel 500-07-997
- $87.2M[2]Full cash value · tax year 2027 · parcel 500-07-994
- $48.8M[2]Limited property value (taxable basis) · tax year 2027 · parcel 500-07-994
- $68.1M[2]Full cash value · tax year 2027 · parcel 500-07-999
- $38.2M[2]Limited property value (taxable basis) · tax year 2027 · parcel 500-07-999
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 500-07-997 Maricopa County, AZ | SDC PHXA4 LLC 2001 ROSS AVE STE 400 DALLAS TX USA 75201 | 14.71 | CONTACT LOCAL JURISDICTION · Property use code 0021 | — | [2] |
| 500-07-994 Maricopa County, AZ | SDC PHX II LLC 2001 ROSS AVE STE 400 DALLAS TX USA 75201 | 16.9 | CONTACT LOCAL JURISDICTION · Property use code 1507 | — | [2] |
| 500-07-999 Maricopa County, AZ | SDC PHXA7 LLC 2001 ROSS AVE STE 400 DALLAS TX USA 75201 | 21.51 | CONTACT LOCAL JURISDICTION · Property use code 2815 | — | [2] |
- Site area
Sum of county land area across parcels.
- Land use
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
- Cogent Data Center · 29.0 km · parcel 113-54-017A$8.3M · Jun 1, 2026 [2]
- 1GServers · 33.4 km · parcel 122-76-036$3.2M · Feb 1, 2025 [2]
- Alembic Computer Services, Inc. · 35.5 km · parcel 123-31-001E$35M · Jul 1, 2025 [2]
- Iron Mountain AZP-2 · 35.7 km · parcel 125-08-002C$8.6M · Sep 1, 2015 [2]
- Iron Mountain AZP-1 · 35.9 km · parcel 125-08-007A$106.9M · Jan 1, 2018 [2]
- J-Curve Technologies · 36.1 km · parcel 124-58-126$11.7M · Dec 1, 2025 [2]
Size
- Parcel / land records
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Oct 30, 2022[1]
Construction beginning, as can be seen on satellite. Major renovations on western side of the non AI building (PX1), including adding generators and cooling towers.
- Jan 31, 2026[1]
Major construction has finished on AI building 1, and AI building 6 has been expedited, as depicted by satellite imagery.
Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the building will be operational.
Although official promotional sources estimate the campus to be fully operational in 10-12 years, it is likely to be finished sooner than this given the empirical durations for other data center campuses as well as because AI building 6 has been expedited. The first AI building took approximately 24 months to complete. Assuming construction for a new building starts midway for every building, then the campus will be complete in 4 years for the 5 remaining buildings, since AI buildings 2 and 6 are both underway.
- Jun 17, 2025[2]
Deed recorded for parcel 500-07-997 (owner of record: Sdc Phxa4 LLC).
- Jun 17, 2025[2]
Deed recorded for parcel 500-07-994 (owner of record: Sdc Phx II LLC).
- Jun 17, 2025[2]
Deed recorded for parcel 500-07-999 (owner of record: Sdc Phxa7 LLC).
Buildings on this campus
1- Stream Data Centers PHX-1Operating · 414,300 sq ft footprint
All claims (provenance audit)
42| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Stream Phoenix | [1] | Likely | 2026-05-01 | Shown |
| Status | Under construction | [1] derived | Likely | 2022-10-30 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-01-31 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-01 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-01 | Shown |
| Address | 2950 S. Litchfield Road | [1] | Likely | 2026-05-01 | Shown |
| Property owner of record | Sdc Phxa4 LLCParcel 500-07-997: SDC PHXA4 LLC | [2] | Confirmed | 2026-09-27 | Shown |
| Property owner of record | Sdc Phx II LLCParcel 500-07-994: SDC PHX II LLC | [2] | Confirmed | 2026-09-27 | Shown |
| Property owner of record | Sdc Phxa7 LLCParcel 500-07-999: SDC PHXA7 LLC | [2] | Confirmed | 2026-09-27 | Shown |
| Utility | Salt River Projectterritory 16572: SALT RIVER PROJECT (POLITICAL SUBDIVISION, SALT RIVER PROJECT) | [3] derived | Unverified | 2022 | Shown |
| Current facility power | 77 MW | [1] estimated | Likely | 2026-05-01 | Shown |
| Current IT capacity | 64 MW | [1] estimated | Likely | 2026-05-01 | Shown |
| Planned capacity | 267 MW | [1] estimated | Likely | 2026-05-01 | Shown |
| Estimated annual consumption | 472 GWh/yr | [4] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [5] derived | Likely | — | Shown |
| Balancing authority | SRP | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (69 kV)way/938592731 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.6 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 500 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.12 GW | [7] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.35¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.12¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 11.7 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-05-01 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-05-01 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2022-10-30 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-01-31 | Superseded / alternative |
| Site area | 53.1 acres | [2] | Confirmed | 2026-09-27 | Shown |
| Capital cost / investment | $2.4B | [1] estimated | Likely | 2026-05-01 | Shown |
| Parcel / land records | 500-07-997 (Maricopa County) | [2] | Confirmed | 2026-09-27 | Shown |
| Parcel / land records | 500-07-994 (Maricopa County) | [2] | Confirmed | 2026-09-27 | Shown |
| Parcel / land records | 500-07-999 (Maricopa County) | [2] | Confirmed | 2026-09-27 | Shown |
| Assessed value (official) | $159.5M | [2] | Confirmed | 2027 | Shown |
| Land use | Property use code 0021 | [2] | Confirmed | 2026-09-27 | Shown |
| Land use | Property use code 1507 | [2] | Confirmed | 2026-09-27 | Superseded / alternative |
| Land use | Property use code 2815 | [2] | Confirmed | 2026-09-27 | Superseded / alternative |
| Compute (H100-equivalents) | 46,100 | [1] estimated | Likely | 2026-05-01 | Shown |
| Chip types | H100 | [1] | Confirmed | 2026-05-01 | Shown |
| Land acquired | Jun 17, 2025 | [2] derived | Confirmed | 2026-09-27 | Shown |
| Construction start | Oct 30, 2022 | [1] derived | Likely | 2026-05-01 | Shown |
| First operational | May 1, 2026 | [1] derived | Likely | 2026-05-01 | Shown |
| Expected completion | Jan 1, 2030 | [1] estimated | Speculative | 2026-05-01 | Shown |