Amazon Madison Mega Site
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — MISO does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationJun 23, 2025
Satellite imagery
- Jun 23, 2025 · Buildings 1-5 are operational, based on roofs being completed 5 months ago and generators being installed by 2025-04-10.[1]
- OperationalJun 23, 2025
Satellite imagery
- Jun 23, 2025 · Buildings 1-5 are operational, based on roofs being completed 5 months ago and generators being installed by 2025-04-10.[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityAmazon Madison Mega Site
- →substationOn-site substation[1]Satellite imageryLikely3 substation outlines traced inside the campus on satellite imagery
- →transmissionMcAdams Sub ENTERGY to Lakeover Sub ENTERGY 500KV[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.93 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 32.59782, -90.09122
- Address
- Amazon Data Services Inc, Madison Mega Site Nissan Parkway and Highway 22 Canton, Mississippi Madison County[1]Likely
- County
- Madison County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2028-03-15); not necessarily full build-out.
- Estimated annual consumption
341 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Mississippi statewide average, July 2026.
- State avg. commercial price
Mississippi statewide average, July 2026.
- Generation within 50 km
7 EIA-reported plants within 50 km.
- Generation queued in county
6 active generation interconnection requests in Madison County: Solar 407 MW, Storage 300 MW, Hybrid 170 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line | Transmission line | 0.65 km | 230 kV | [5] |
| McAdams Sub ENTERGY to Lakeover Sub ENTERGY 500KV · Entergy Mississippi | Transmission line | 1.93 km | 500 kV | [5] |
| Ragsdale Solar LLC · Ragsdale Solar, LLC | Power plant (Solar) | 9.2 km | 100 MW | [8] |
| Hinds Energy Facility · Entergy Mississippi LLC | Power plant (Natural Gas) | 27.2 km | 473 MW | [8] |
| Mississippi Baptist Medical Center · Mississippi Baptist Medical | Power plant (Natural Gas) | 32.7 km | 4 MW | [8] |
| Pearl River Solar Park LLC · Pearl River Solar Park, LLC | Power plant (Solar) | 34.2 km | 175 MW | [8] |
| Lineage Ms · Madison Energy Holdings LLC | Power plant (Solar) | 38.7 km | 1 MW | [8] |
| Yazoo · Public Serv Comm of Yazoo City | Power plant (Natural Gas) | 41.4 km | 33 MW | [8] |
| Cf Industries Yazoo City Complex · CF Industries Nitrogen LLC | Power plant (Natural Gas) | 43.4 km | 20 MW | [8] |
| Unnamed substation | Substation | 0.71 km | 230 kV | [5] |
| Unnamed substation | Substation | 1.03 km | 230 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J4154 at Andes SubstationMISO J4154 | Storage | In study · proposed 2028-08 | 200 MW | [6] |
| J3049 at LAKEOVER EHV - MCADAMS EHV 500.0kVMISO J3049 | Solar | In study · proposed 2024-12 | 188 MW | [6] |
| J3764 at Andes Substation 230 kVMISO J3764 | Hybrid | In study · proposed 2028-03 | 170 MW | [6] |
| J3053 at LAKEOVER EHV - MCADAMS EHV 500.0kVMISO J3053 | Solar | In study · proposed 2024-12 | 169 MW | [6] |
| J3093 at LAKEOVER EHV - MCADAMS EHV 500.0kVMISO J3093 | Storage | In study · proposed 2024-12 | 100 MW | [6] |
| J1747 at J830 POIMISO J1747 | Solar | Under construction · proposed 2022-02 | 50 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startOct 2, 2023[1]
- First operationalJun 23, 2025[1]
- Expected completionMar 15, 2028[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2028-03-15); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Sum of 5 building outlines mapped in OpenStreetMap within this campus.
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Oct 2, 2023[1]
Land clearing begins
- Mar 11, 2025[1]
Generators and chillers still being installed on buildings 1-5.
Buildings 1-5 are operational, based on roofs being completed 5 months ago and generators being installed by 2025-04-10.
Confirmation that five buildings are fully equipped with cooling and backup generators.
Buildings 6 and 7 roof completed. Building 8 roof nearly completed. Building 9 roof half way up. No new operational buildings.
Buildings 6 and 7 operational, estimated from roofs having been completed 9 months ago (similar timeline to AWS buildings at New Carlisle in 2025).
Buildings 8-12 are operational. In June of 2026 only a faint outline of buildings 10,11 and 12 is visible, estimating construction completion to be the end of 2027, alligning with expected completion by 2027. This final estimates adds three months to that for server installation.
All claims (provenance audit)
42| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Amazon Madison Mega Site | [1] | Likely | 2026-06-04 | Shown |
| Status | Under construction | [1] derived | Likely | 2023-10-02 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-03-11 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-06-23 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-04 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-06-04 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-04 | Shown |
| Project | Project Rainier | [1] | Speculative | 2026-06-04 | Shown |
| Address | Amazon Data Services Inc, Madison Mega Site Nissan Parkway and Highway 22 Canton, Mississippi Madison County | [1] | Likely | 2026-06-04 | Shown |
| Owner | Amazon Web ServicesOwner: Amazon | [1] | Confirmed | 2026-06-04 | Shown |
| End users | AnthropicUsers: Anthropic | [1] | Speculative | 2026-06-04 | Shown |
| Utility | Entergyterritory 12685: ENTERGY MISSISSIPPI LLC (INVESTOR OWNED, ENTERGY CORP) | [2] derived | Unverified | 2022 | Shown |
| Current facility power | 341 MW | [1] estimated | Likely | 2026-06-04 | Shown |
| Current facility power | 341 MW | [1] estimated | Likely | 2025-06-23 | Superseded / alternative |
| Current facility power | 341 MW | [1] estimated | Likely | 2025-10-04 | Superseded / alternative |
| Current IT capacity | 284 MW | [1] estimated | Likely | 2026-06-04 | Shown |
| Current IT capacity | 284 MW | [1] estimated | Likely | 2025-06-23 | Superseded / alternative |
| Current IT capacity | 284 MW | [1] estimated | Likely | 2025-10-04 | Superseded / alternative |
| Planned capacity | 819 MW | [1] estimated | Likely | 2026-06-04 | Shown |
| Estimated annual consumption | 2,091 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [4] derived | Likely | — | Shown |
| Balancing authority | MISO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (230 kV)way/1466908897 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.7 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 500 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 877 MW | [6] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 7.66¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.65¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 806 MW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 12 | [1] derived | Likely | 2026-06-04 | Shown |
| Buildings operational | 5 | [1] estimated | Likely | 2026-06-04 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2023-10-02 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-03-11 | Superseded / alternative |
| Buildings operational | 5 | [1] estimated | Likely | 2025-06-23 | Superseded / alternative |
| Buildings operational | 5 | [1] estimated | Likely | 2025-10-04 | Superseded / alternative |
| Building footprint | 1.07M sq ftway/1430720170 way/1430720171 way/1430720172 way/1430720173 way/1430720174 | [5] derived | Likely | 2026-09-27 | Shown |
| Capital cost / investment | $10.8B | [1] estimated | Likely | 2026-06-04 | Shown |
| Compute (H100-equivalents) | 214,300 | [1] estimated | Likely | 2026-06-04 | Shown |
| Chip types | Trainium2 | [1] | Confirmed | 2026-06-04 | Shown |
| Construction start | Oct 2, 2023 | [1] derived | Likely | 2026-06-04 | Shown |
| First operational | Jun 23, 2025 | [1] derived | Likely | 2026-06-04 | Shown |
| Expected completion | Mar 15, 2028 | [1] estimated | Speculative | 2026-06-04 | Shown |