Anthropic Barber Lake

Under constructionAI campusCampusMitchell County, Texas
50% profile completeness
23 claims from 13 sources
Current facility power
Not yet sourced
Planned capacity
300 MW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
Not yet sourced
First operational
Dec 30, 2026[1]
Speculativeestimated

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2027 – H1 2028
Medium confidencewindow, not a prediction
Project verification
Under construction
Construction documented by satellite imagery.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
Taylor Electric Coop INC - (Tx) · ERCOT
Substation: On-site substation

Power reality

Announced
300 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
244 MW[1]
Building 1 under construction (satellite-tracked phases)
Operational
No record
  • ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Construction elapsed: Construction documented since 2025-09-18 (1.0 years).
  • Stated date: Next projected milestone: 2026-12-30 (modeled/speculative)[1]
  • Required: 300 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • Construction to first power typically takes 1.25–2.5 years.
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H1 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionSep 18, 2025
    Model estimate · Satellite imagery
    • Sep 18, 2025 · Reported status: under construction[1]
    • Sep 18, 2025 · Construction start[1]
    • Sep 18, 2025 · Site grading and civil works begin.[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Anthropic Barber Lake
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    2 substation outlines traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Taylor Electric Coop INC - (Tx)[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    ERCOT[3]
    Service territoryLikely
    Balancing authority: ERCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
32.39709, -100.92229
County
Mitchell County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
End user
Anthropic[1]Confirmed
Utility

Most likely retail provider among 4 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Concho Valley Elec Coop INC, Big Country Electric Coop, INC, Oncor Electric Delivery Company LLC.

Power (all fields)

Planned capacity
300 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-04-30); not necessarily full build-out.

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
ERCOT[3]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
ERCO[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
7.07¢/kWh[5]Confirmed

Texas statewide average, July 2026.

State avg. commercial price
8.47¢/kWh[5]Confirmed

Texas statewide average, July 2026.

Generation within 50 km
3.27 GW[6]Confirmedderived

21 EIA-reported plants within 50 km.

Generation queued in county
6.79 GW[4]Confirmedderived

15 active generation interconnection requests in Mitchell County: Storage 3,815 MW, Solar 1,686 MW, Wind 1,290 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Morgan Creek · Luminant Generation Company LLCPower plant (Petroleum)6.8 km397 MW[6]
Roscoe Wind Farm LLC · RWE Renewables Americas, LLCPower plant (Wind)25.3 km209 MW[6]
Canyon Wind Project, LLC · Canyon Wind Project, LLCPower plant (Wind)27.2 km309 MW[6]
Pyron Wind Farm LLC Hybrid · RWE Renewables Americas, LLCPower plant (Wind)31.6 km259 MW[6]
Inadale Wind Farm LLC Hybrid · RWE Renewables Americas, LLCPower plant (Wind)34 km207 MW[6]
Sweetwater Wind 4 LLC · Leeward Asset Management, LLCPower plant (Wind)38 km241 MW[6]
Panther Creek Wind Farm Three · RWE Renewables Americas, LLCPower plant (Wind)48.6 km232 MW[6]
C R Wing Cogen Plant · BHER Power Resources, IncPower plant (Natural Gas)49 km212 MW[6]
Largest queued generation in this countyFuelQueue statusMWSource
Zeus Mitchell BESSERCOT 25INR0589 · Mitchell BESSStorageUnder construction · proposed 2029-041.04 GW[4]
Zeus Mitchell BESS IIERCOT 26INR0686 · Zeus Mitchell BESS II, LLCStorageIn study · proposed 2027-051.04 GW[4]
Zeus Spade WindERCOT 26INR0386 · Spade Wind, LLCWindUnder construction · proposed 2028-03987 MW[4]
Zeus Mitchell SolarERCOT 25INR0588 · Mitchell Solar, LLCSolarUnder construction · proposed 2029-04805 MW[4]
Rosenix SolarERCOT 29INR0212 · Rosenix Solar, LLCSolarIn study · proposed 2029-12510 MW[4]
Zeus Spade BESSERCOT 26INR0387 · Spade BESSStorageUnder construction · proposed 2028-03446 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Sep 18, 2025[1]
  5. First operational
    Dec 30, 2026[1]
    Projected
  6. Expected completion
    Apr 30, 2027[1]
    Projected
Planned capacity
300 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-04-30); not necessarily full build-out.

Buildings (planned)
1[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
0[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1under construction244 MWDec 30, 2026 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
TPU v7[1]Confirmed

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

Construction start: Sep 18, 2025[1]
First operational: Dec 30, 2026[1]
  1. Sep 18, 2025[1]

    Site grading and civil works begin.

  2. Nov 29, 2025[1]

    Foundations of Building 1 are visible.

  3. Jul 30, 2026[1]

    Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.

  4. Dec 30, 2026Projected244 MW facility power· 1 buildings operational[1]

    Building 1 Phase I is operational: 168 MW critical IT power (244 MW gross), running Google TPU v7 (chip type inferred, tagged likely). We estimate ~Dec 2026, about 3 months later than the disclosed target, because the site is shell-complete but not yet energized as of the Jul 2026 image. Disclosed target: Cipher 2025-09-25 PR states the 168 MW critical IT load is "expected to be delivered by September 2026."

  5. Apr 30, 2027Projected300 MW facility power· 1 buildings operational[1]

    Building 1 Phase II is operational: 207 MW total critical IT (300 MW gross). Phase II adds 39 MW critical IT (see Cipher 2025-11-20 PR). We estimate ~Apr 2027, about 3 months later than the ~Q1 2027 target, based on construction progress.

All claims (provenance audit)

23
FieldValueSourceConfidenceAs ofStatus
NameAnthropic Barber Lake[1] Likely2026-07-30Shown
StatusUnder construction[1] derivedLikely2025-09-18Superseded / alternative
StatusUnder construction[1] derivedLikely2025-11-29Superseded / alternative
StatusUnder construction[1] derivedLikely2026-07-30Shown
Facility typeAI campus[1] derivedLikely2026-07-30Shown
OwnerCipher MiningOwner: Cipher Mining[1] Confirmed2026-07-30Shown
End usersAnthropicUsers: Anthropic[1] Confirmed2026-07-30Shown
UtilityTaylor Electric Coop INC - (Tx)territory 27369: TAYLOR ELECTRIC COOP INC - (TX) (COOPERATIVE, TAYLOR ELECTRIC C[2] derivedUnverified2022Shown
Planned capacity300 MW[1] estimatedLikely2026-07-30Shown
ISO / RTOERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.[3] derivedLikely—Shown
Balancing authorityERCO[2] derivedLikely—Shown
Generation queued in county6.79 GW[4] derivedConfirmed2026-09-01Shown
State avg. industrial price7.07¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price8.47¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km3.27 GW[6] derivedConfirmed202502Shown
Buildings (planned)1[1] derivedLikely2026-07-30Shown
Buildings operational0[1] estimatedLikely2026-07-30Shown
Buildings operational0[1] estimatedLikely2025-09-18Superseded / alternative
Buildings operational0[1] estimatedLikely2025-11-29Superseded / alternative
Chip typesTPU v7[1] Confirmed2026-07-30Shown
Construction startSep 18, 2025[1] derivedLikely2026-07-30Shown
First operationalDec 30, 2026[1] estimatedSpeculative2026-07-30Shown
Expected completionApr 30, 2027[1] estimatedSpeculative2026-07-30Shown