Anthropic Barber Lake
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityAnthropic Barber Lake
- →substationOn-site substation[1]Satellite imageryLikely2 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityTaylor Electric Coop INC - (Tx)[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 32.39709, -100.92229
- County
- Mitchell County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Owner
- Utility
Most likely retail provider among 4 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Concho Valley Elec Coop INC, Big Country Electric Coop, INC, Oncor Electric Delivery Company LLC.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2027-04-30); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
21 EIA-reported plants within 50 km.
- Generation queued in county
15 active generation interconnection requests in Mitchell County: Storage 3,815 MW, Solar 1,686 MW, Wind 1,290 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Morgan Creek · Luminant Generation Company LLC | Power plant (Petroleum) | 6.8 km | 397 MW | [6] |
| Roscoe Wind Farm LLC · RWE Renewables Americas, LLC | Power plant (Wind) | 25.3 km | 209 MW | [6] |
| Canyon Wind Project, LLC · Canyon Wind Project, LLC | Power plant (Wind) | 27.2 km | 309 MW | [6] |
| Pyron Wind Farm LLC Hybrid · RWE Renewables Americas, LLC | Power plant (Wind) | 31.6 km | 259 MW | [6] |
| Inadale Wind Farm LLC Hybrid · RWE Renewables Americas, LLC | Power plant (Wind) | 34 km | 207 MW | [6] |
| Sweetwater Wind 4 LLC · Leeward Asset Management, LLC | Power plant (Wind) | 38 km | 241 MW | [6] |
| Panther Creek Wind Farm Three · RWE Renewables Americas, LLC | Power plant (Wind) | 48.6 km | 232 MW | [6] |
| C R Wing Cogen Plant · BHER Power Resources, Inc | Power plant (Natural Gas) | 49 km | 212 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Zeus Mitchell BESSERCOT 25INR0589 · Mitchell BESS | Storage | Under construction · proposed 2029-04 | 1.04 GW | [4] |
| Zeus Mitchell BESS IIERCOT 26INR0686 · Zeus Mitchell BESS II, LLC | Storage | In study · proposed 2027-05 | 1.04 GW | [4] |
| Zeus Spade WindERCOT 26INR0386 · Spade Wind, LLC | Wind | Under construction · proposed 2028-03 | 987 MW | [4] |
| Zeus Mitchell SolarERCOT 25INR0588 · Mitchell Solar, LLC | Solar | Under construction · proposed 2029-04 | 805 MW | [4] |
| Rosenix SolarERCOT 29INR0212 · Rosenix Solar, LLC | Solar | In study · proposed 2029-12 | 510 MW | [4] |
| Zeus Spade BESSERCOT 26INR0387 · Spade BESS | Storage | Under construction · proposed 2028-03 | 446 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startSep 18, 2025[1]
- First operationalDec 30, 2026[1]Projected
- Expected completionApr 30, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-04-30); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | under construction | 244 MW | Dec 30, 2026 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Sep 18, 2025[1]
Site grading and civil works begin.
- Nov 29, 2025[1]
Foundations of Building 1 are visible.
- Jul 30, 2026[1]
Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.
Building 1 Phase I is operational: 168 MW critical IT power (244 MW gross), running Google TPU v7 (chip type inferred, tagged likely). We estimate ~Dec 2026, about 3 months later than the disclosed target, because the site is shell-complete but not yet energized as of the Jul 2026 image. Disclosed target: Cipher 2025-09-25 PR states the 168 MW critical IT load is "expected to be delivered by September 2026."
Building 1 Phase II is operational: 207 MW total critical IT (300 MW gross). Phase II adds 39 MW critical IT (see Cipher 2025-11-20 PR). We estimate ~Apr 2027, about 3 months later than the ~Q1 2027 target, based on construction progress.
All claims (provenance audit)
23| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Anthropic Barber Lake | [1] | Likely | 2026-07-30 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-09-18 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-11-29 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-07-30 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-30 | Shown |
| Owner | Cipher MiningOwner: Cipher Mining | [1] | Confirmed | 2026-07-30 | Shown |
| End users | AnthropicUsers: Anthropic | [1] | Confirmed | 2026-07-30 | Shown |
| Utility | Taylor Electric Coop INC - (Tx)territory 27369: TAYLOR ELECTRIC COOP INC - (TX) (COOPERATIVE, TAYLOR ELECTRIC C | [2] derived | Unverified | 2022 | Shown |
| Planned capacity | 300 MW | [1] estimated | Likely | 2026-07-30 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [3] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Generation queued in county | 6.79 GW | [4] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.27 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-07-30 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-07-30 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-09-18 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-11-29 | Superseded / alternative |
| Chip types | TPU v7 | [1] | Confirmed | 2026-07-30 | Shown |
| Construction start | Sep 18, 2025 | [1] derived | Likely | 2026-07-30 | Shown |
| First operational | Dec 30, 2026 | [1] estimated | Speculative | 2026-07-30 | Shown |
| Expected completion | Apr 30, 2027 | [1] estimated | Speculative | 2026-07-30 | Shown |