DC
/

CloudHQ LC12

Under constructionColocationBuildingAshburn, Loudoun County, Virginia

Part of CloudHQ — Ashburn, VA campus

30% profile completeness
23 claims from 8 sources
Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Building footprint
141,600 sq ft[1]
Likelyderived
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
Medium confidence
Project verification
Documented development
Permitting documented by permit / site plan.
Current stage
Energization
Furthest stage with documented evidence
Utility · ISO
Dominion Energy · PJM
Substation: Greenway Substation (230 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
108 MW[1]
Reported
  • ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningSep 27, 2026
    Permit / site plan
    • Sep 27, 2026 · Permit / case ZMAP-1998-0003[8]
  4. Permitting2023
    Permit / site plan
    • 2023 · Permit date[8]
    • 2023 · Loudoun County site plan STPL-2023-0001 — Approved, 481,622 sq ft proposed.[8]
    • Sep 27, 2026 · Site plan STPL-2023-0001: Approved[8]
    • Sep 27, 2026 · Permit / case STPL-2023-0001[8]
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionSep 27, 2026
    Community map
    • Sep 27, 2026 · Reported status: under construction[1]
  3. EnergizationSep 27, 2026
    Community map
    • Sep 27, 2026 · Power in use reported: 108 MW[1]
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Permit / site plan, Community map.

Grid path

  1. facility
    CloudHQ LC12
  2. substation
    Greenway Substation (230 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 0.16 km away. Proximity does not establish that it serves the site.
  3. transmission
    2031;2188 (230 kV)[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.09 km away). Not confirmed as the supply path.
  4. utility
    Dominion Energy[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    PJM[4]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
39.00525, -77.47866
Address
22225 Loudoun County Parkway, Ashburn, VA 20147[1]Likely
County
Loudoun County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Operator
Utility

Location falls inside this utility's retail service territory.

No tenants or end users identified in our sources yet.

Power (all fields)

Current IT capacity
108 MW[1]Likely
Estimated annual consumption
861 GWh/yr[3]Speculativeestimated

140 MW (IT 108 MW × 1.3) × 8,760 h × 70% utilization.

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[4]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Greenway Substation (230 kV)[1]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.2 km[1]Likelyderived
Highest-voltage line nearby
230 kV[1]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.07¢/kWh[6]Confirmed

Virginia statewide average, July 2026.

State avg. commercial price
11.68¢/kWh[6]Confirmed

Virginia statewide average, July 2026.

Generation within 50 km
1.63 GW[7]Confirmedderived

59 EIA-reported plants within 50 km.

Generation queued in county
1.04 GW[5]Confirmedderived

11 active generation interconnection requests in Loudoun County: Storage 940 MW, Solar 100 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
2031;2188 · Dominion EnergyTransmission line0.09 km230 kV[1]
2188 · Virginia Electric & Power CompanyTransmission line0.1 km230 kV[1]
2031 · Virginia Electric & Power CompanyTransmission line0.1 km230 kV[1]
2186;2188 · Virginia Electric & Power CompanyTransmission line0.22 km230 kV[1]
2186 · Virginia Electric & Power CompanyTransmission line0.22 km230 kV[1]
2095;2137 · Virginia Electric & Power CompanyTransmission line0.89 km230 kV[1]
Potomac Energy Center, LLC · Potomac Energy Center LLCPower plant (Natural Gas)8.2 km766 MW[7]
Montgomery County Resource Recovery · Covanta Montgomery, Inc.Power plant (Biomass)21.8 km54 MW[7]
Dickerson Power · Dickerson Power, LLCPower plant (Natural Gas)22.8 km299 MW[7]
Nih Cogeneration Facility · National Institutes of HealthPower plant (Natural Gas)33.3 km28 MW[7]
Covanta Alexandria/Arlington Energy · Covanta Alexandria/ArlingtonPower plant (Biomass)37.8 km29 MW[7]
Covanta Fairfax Energy · Covanta Fairfax IncPower plant (Biomass)40.2 km98 MW[7]
Blake Solar Plant · Horus West Virginia 1, LLCPower plant (Solar)42 km80 MW[7]
Central Utility Plant At White Oak · GSA Metropolitan Service CenterPower plant (Natural Gas)43 km54 MW[7]
Greenway Substation · Virginia Electric & Power CompanySubstation0.16 km230 kV[1]
Enterprise SubstationSubstation0.38 km230 kV[1]
Stratus SubstationSubstation0.85 km230 kV[1]
Shellhorn Substation · Virginia Electric & Power CompanySubstation0.94 km230 kV[1]
Washington Metropolitan Area Transit Authority substation · Washington Metropolitan Area Transit AuthoritySubstation0.94 km34.5 kV[1]
Roundtable Substation · Virginia Electric & Power CompanySubstation1.02 km230 kV[1]
Largest queued generation in this countyFuelQueue statusMWSource
Loudoun 230 kVPJM AG2-285StorageIn study · proposed 2023-12150 MW[5]
Beaumeade 230 kVPJM AG2-287StorageIn study · proposed 2023-12150 MW[5]
New Road StoragePJM AE2-019StorageIA signed · proposed 2026-12120 MW[5]
Dulles SolarPJM AF1-147SolarIA signed · proposed 2023-12100 MW[5]
Roundtable 230 kVPJM AG2-307StorageIn study · proposed 2023-12100 MW[5]
Shelhorn 230 kVPJM AG2-323StorageIn study · proposed 2023-12100 MW[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    2023[8]
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —
Permitting status
Site plan STPL-2023-0001: Approved[8]Confirmed
Permit / case numbers
STPL-2023-0001, ZMAP-1998-0003[8]Confirmed
Planned floor area
481,600 sq ft[8]Confirmed

Building area proposed in the site plan.

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
141,600 sq ft[1]Likelyderived

Computed from the mapped OSM building outline.

Planned floor area
481,600 sq ft[8]Confirmed

Building area proposed in the site plan.

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

  1. 2023[8]

    Loudoun County site plan STPL-2023-0001 — Approved, 481,622 sq ft proposed.

Other buildings on this campus

8

All claims (provenance audit)

23
FieldValueSourceConfidenceAs ofStatus
NameCloudHQ LC12way/1560822519 name=CloudHQ LC12[1] Likely2026-09-27Shown
StatusUnder construction[1] derivedLikely2026-09-27Shown
Facility typeColocation[1] derivedUnverified2026-09-27Shown
Address22225 Loudoun County Parkway, Ashburn, VA 20147[1] Likely2026-09-27Shown
OperatorCloudHQoperator=CloudHQ[1] Likely2026-09-27Shown
UtilityDominion Energyterritory 19876: VIRGINIA ELECTRIC & POWER CO (INVESTOR OWNED, DOMINION RESOURCE[2] derivedLikely2022Shown
Current IT capacity108 MWit_power=108 MW[1] Likely2026-09-27Shown
Estimated annual consumption861 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[4] derivedLikely—Shown
Balancing authorityPJM[2] derivedLikely—Shown
Nearest mapped substationGreenway Substation (230 kV)way/216701980[1] derivedLikely2026-09-28Shown
Distance to substation0.2 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby230 kV[1] derivedLikely2026-09-28Shown
Generation queued in county1.04 GW[5] derivedConfirmed2026-09-27Shown
State avg. industrial price10.07¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price11.68¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km1.63 GW[7] derivedConfirmed202502Shown
Permitting statusSite plan STPL-2023-0001: ApprovedApplication STPL-2023-0001, zoning case ZMAP-1998-0003[8] Confirmed2026-09-27Shown
Permit / case numbersSTPL-2023-0001[8] Confirmed2026-09-27Shown
Permit / case numbersZMAP-1998-0003[8] Confirmed2026-09-27Shown
Building footprint141,600 sq ft[1] derivedLikely2026-09-27Shown
Planned floor area481,600 sq ft[8] Confirmed2026-09-27Shown
Permit / site plan filed2023[8] derivedConfirmed2026-09-27Shown