Northern Virginia

Market boundary: facilities within 45 km of the metro center (editorial definition).

Facilities
439
3 campuses
Power online
3.4 GW
51 sites reporting
Under construction
369 MW
planned MW at active sites
Planned
—
77 planned sites (MW not disclosed)
AI campuses
3
404 MW online · 369 MW pipeline
AI compute
0.38M
H100-equivalents (est.)
Capital (reported + est.)
$15.1B
$10.1B assessed

Totals only include facilities with a reported or estimated figure; most sites don't disclose power, so these are floors, not market size estimates. Online = operating sites; pipeline = remaining planned MW at sites under construction or planned.

Construction pipeline by expected completion

MW from phases with a projected completion date

2028

Power reality

Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.

  • Announced487 MW
  • Interconnection requests—
  • Contracted / approved—
  • Under construction369 MW
  • Operational4.71 GW
Pending MW by time to power

Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.

Largest gaps: announced vs documented

No large gaps in this scope.

Verified operating: 276Under construction: 58Documented development: 88Unverified: 17

Interconnection queues

Active requests to connect to the grid (PJM). Requests are applications, not commitments — most never get built.

Generation seeking interconnection5.83 GW · 52 requests
Storage 3.97 GWGas 1.19 GWSolar 578 MWOther 98 MW

Largest operators & owners

Online + pipeline MW at linked facilities

Online Under construction + planned

Largest customers & end users

Tenants and workload owners, where sourced

Online Under construction + planned

Utility exposure

Most likely retail utility by location (approximate)

Online Under construction + planned

Grid operators (ISO / RTO)

By facility location

Online Under construction + planned
  • PJM3.39 GW + 369 MW · 439 sites

Largest facilities

By online + pipeline MW

FacilityStatusOnlinePipeline
STACK Infrastructure NVA02Operating + expanding118 MW369 MW
Google BristowOperating286 MW—
CloudHQ LC1Operating264 MW—
Digital Realty IAD39Operating192 MW—
CloudHQ LC2Operating162 MW—
Digital Realty IAD41Operating135 MW—
CloudHQ LC3Operating132 MW—
Digital Realty IAD42Operating90 MW—
Digital Realty IAD43Operating90 MW—
CyrusOne NVA1/NVA2/NVA3Operating85 MW—
QTS Ashburn 3 DC1Operating80 MW—
QTS Ashburn 3 DC2Operating80 MW—
Digital Realty ACC4Operating72 MW—
Digital Realty ACC5Operating72 MW—
Amazon IAD-162Operating65 MW—

Facilities by status

  • Operating292
  • Operating + expanding1
  • Under construction69
  • Planned77