Colossus 1
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionApr 24, 2024
- EnergizationAug 11, 2024
Satellite imagery
- Aug 11, 2024 · First [significant/useful training workload](https://x.ai/colossus) on 25k H100s.[1]
- OperationalAug 11, 2024
Satellite imagery
- Aug 11, 2024 · First [significant/useful training workload](https://x.ai/colossus) on 25k H100s.[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityColossus 1
- →substationSatellite imageryLikely3 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.37 km away
- →transmissionWest Memphis - Freeport 500kV[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.61 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- 2 on-site power generator outlines traced on satellite imagery[1]Epoch AI satellite annotations (fuel type and capacity not identified)Unknown typeBehind-the-meterLikely
Location & imagery
Mapped outline- Coordinates
- 35.05974, -90.15609
- Address
- County
- Shelby County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Owner
- Utility
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2025-07-22); not necessarily full build-out.
- Estimated annual consumption
425 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Tennessee statewide average, July 2026.
- State avg. commercial price
Tennessee statewide average, July 2026.
- Generation within 50 km
9 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 161 kV line | Transmission line | 0.34 km | 161 kV | [5] |
| Allen - Freeport 161kV · Memphis Light, Gas and Water | Transmission line | 0.5 km | 161 kV | [5] |
| West Memphis - Freeport 500kV · Tennessee Valley Authority | Transmission line | 0.61 km | 500 kV | [5] |
| Allen - Southgate 161kV · Memphis Light, Gas and Water | Transmission line | 1.41 km | 161 kV | [5] |
| Allen - Southgate #2 161kV · Memphis Light, Gas and Water | Transmission line | 1.54 km | 161 kV | [5] |
| Allen · Tennessee Valley Authority | Power plant (Natural Gas) | 1.7 km | 1.48 GW | [7] |
| Wildflower Solar, LLC (Ms) · Duke Energy Renewables Services | Power plant (Solar) | 11.2 km | 100 MW | [7] |
| TVA Southaven Combined Cycle · Tennessee Valley Authority | Power plant (Natural Gas) | 13 km | 780 MW | [7] |
| West Memphis Solar Station · Entergy Arkansas LLC | Power plant (Solar) | 17.7 km | 180 MW | [7] |
| Sr Innovation - Nike PV · SR Innovation, LLC | Power plant (Solar) | 32 km | 2 MW | [7] |
| Big Cypress Solar, LLC · Big Cypress Solar, LLC | Power plant (Solar) | 34.5 km | 180 MW | [7] |
| Millington Solar Farm · SR Millington, LLC | Power plant (Solar) | 42.5 km | 53 MW | [7] |
| Sr Byhalia, LLC · SR Byhalia, LLC | Power plant (Solar) | 49.8 km | 5 MW | [7] |
| Unnamed substation | Substation | 0.37 km | 161 kV | [5] |
| Unnamed substation | Substation | 0.39 km | 22.9 kV | [5] |
| Memphis Light, Gas and Water substation · Memphis Light, Gas and Water | Substation | 0.39 km | — | [5] |
| Unnamed substation | Substation | 0.43 km | 161 kV | [5] |
| Unnamed substation | Substation | 1.01 km | 500 kV | [5] |
| Memphis Light, Gas and Water substation · Memphis Light, Gas and Water | Substation | 1.12 km | 161 kV | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startApr 24, 2024[1]
- First operationalAug 11, 2024[1]
- Expected completion—
- Planned capacity
Projected facility power at the last tracked milestone (2025-07-22); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | operational | 45 MW | Aug 11, 2024 | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity
- Current facility power
- Buildings operational
- Status
Timeline
- Apr 24, 2024[1]
Construction starts with a road added on site, retrofitting a former Electrolux building.
First significant/useful training workload on 25k H100s.
150k H100s and 50k H200s online. This is roughly when Musk said, plus on this date they reported "running jobs with 150K+ GPUs".
Second substation almost connected (red cables)
30k B200s added (in GB200 configuration).
Third substation looks completed, but it doesn't appear to be connected to the building yet. Some air-cooled chillers removed, while large cooling towers are added.
There is still construction visible in the third substation yard and next to the new cooling towers.
Third substation was expected to power the building in Fall.
All air-cooled chillers have been disconnected and/or removed from the site, leaving only the cooling towers for cooling. The third substation looks complete, with red cables connected to the building.
Anthropic announces their agreement with SpaceX to use all of the compute capacity at Colossus 1. They state that this corresponds to more than 300 MW (presumably IT power) and over 220,000 GPUs. This is slightly different to previous reports adding up to 230,000 GPUs, but still roughly consistent with our estimates.
We assume that Anthropic has started using Colossus 1 now, since the announcement said they would get access to 300 MW "within the month" of May.
No major changes to the data center since February. Solar panels have been placed next to the facility.
Buildings on this campus
1- xAI ColossusOperating · 778,800 sq ft footprint
All claims (provenance audit)
74| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Colossus 1 | [1] | Likely | 2026-06-15 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-04-24 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-08-11 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-09-02 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-02-17 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-03-06 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-07-22 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-09-17 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-19 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-11-07 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-11 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-06 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-06-01 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-06-15 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-15 | Shown |
| Address | 3231 Riverport Rd, Memphis, TN 38109 | [1] | Likely | 2026-06-15 | Shown |
| Owner | SpaceXAI (xAI)Owner: SpaceXAI | [1] | Confirmed | 2026-06-15 | Shown |
| End users | AnthropicUsers: Anthropic | [1] | Confirmed | 2026-06-15 | Shown |
| Utility | Memphis Light, Gas and WaterEnergy companies: MLGW | [1] | Confirmed | 2026-06-15 | Shown |
| Current facility power | 425 MW | [1] estimated | Likely | 2026-06-15 | Shown |
| Current facility power | 45 MW | [1] estimated | Likely | 2024-08-11 | Superseded / alternative |
| Current facility power | 181 MW | [1] estimated | Likely | 2024-09-02 | Superseded / alternative |
| Current facility power | 361 MW | [1] estimated | Likely | 2025-02-17 | Superseded / alternative |
| Current facility power | 361 MW | [1] estimated | Likely | 2025-03-06 | Superseded / alternative |
| Current facility power | 442 MW | [1] estimated | Likely | 2025-07-22 | Superseded / alternative |
| Current facility power | 348 MW | [1] estimated | Likely | 2025-09-17 | Superseded / alternative |
| Current facility power | 348 MW | [1] estimated | Likely | 2025-10-19 | Superseded / alternative |
| Current facility power | 442 MW | [1] estimated | Likely | 2025-11-07 | Superseded / alternative |
| Current facility power | 425 MW | [1] estimated | Likely | 2026-02-11 | Superseded / alternative |
| Current facility power | 425 MW | [1] estimated | Likely | 2026-05-06 | Superseded / alternative |
| Current facility power | 425 MW | [1] estimated | Likely | 2026-06-01 | Superseded / alternative |
| Current IT capacity | 340 MW | [1] estimated | Likely | 2026-06-15 | Shown |
| Current IT capacity | 35 MW | [1] estimated | Likely | 2024-08-11 | Superseded / alternative |
| Current IT capacity | 139 MW | [1] estimated | Likely | 2024-09-02 | Superseded / alternative |
| Current IT capacity | 278 MW | [1] estimated | Likely | 2025-02-17 | Superseded / alternative |
| Current IT capacity | 278 MW | [1] estimated | Likely | 2025-03-06 | Superseded / alternative |
| Current IT capacity | 340 MW | [1] estimated | Likely | 2025-07-22 | Superseded / alternative |
| Current IT capacity | 268 MW | [1] estimated | Likely | 2025-09-17 | Superseded / alternative |
| Current IT capacity | 268 MW | [1] estimated | Likely | 2025-10-19 | Superseded / alternative |
| Current IT capacity | 340 MW | [1] estimated | Likely | 2025-11-07 | Superseded / alternative |
| Current IT capacity | 340 MW | [1] estimated | Likely | 2026-02-11 | Superseded / alternative |
| Current IT capacity | 340 MW | [1] estimated | Likely | 2026-05-06 | Superseded / alternative |
| Current IT capacity | 340 MW | [1] estimated | Likely | 2026-06-01 | Superseded / alternative |
| Planned capacity | 442 MW | [1] estimated | Likely | 2026-06-15 | Shown |
| Estimated annual consumption | 2,606 GWh/yr | [2] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [3] derived | Likely | — | Shown |
| Balancing authority | TVA | [4] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (161 kV)way/1413617102 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 500 kV | [5] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 7.13¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.43¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.78 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-06-15 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-06-15 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-04-24 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-08-11 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-09-02 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-02-17 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-03-06 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-07-22 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-09-17 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-10-19 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-11-07 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-02-11 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-05-06 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-06-01 | Superseded / alternative |
| Capital cost / investment | $12.9B | [1] estimated | Likely | 2026-06-15 | Shown |
| Compute (H100-equivalents) | 275,800 | [1] estimated | Likely | 2026-06-15 | Shown |
| Chip types | H100 | [1] | Confirmed | 2026-06-15 | Shown |
| Chip types | H200 | [1] | Confirmed | 2026-06-15 | Shown |
| Chip types | B200 | [1] | Confirmed | 2026-06-15 | Shown |
| Construction start | Apr 24, 2024 | [1] derived | Likely | 2026-06-15 | Shown |
| First operational | Aug 11, 2024 | [1] derived | Likely | 2026-06-15 | Shown |