Linked facilities
19
States
13
Reported power online
3.28 GW
Reported planned capacity
14.73 GW
Power totals sum only facilities with a reported or estimated figure, across all roles (a company can be tenant at one site and owner at another).
Loading map…
US footprint by state
- Texas5 sites · 1.16 GW
- Wisconsin2 sites · 442 MW
- Georgia2 sites · 899 MW
- New Mexico1 sites
- Michigan1 sites
- Ohio1 sites
- Arizona1 sites · 263 MW
- Iowa1 sites · 228 MW
- Oklahoma1 sites
- Pennsylvania1 sites
- Virginia1 sites · 114 MW
- North Carolina1 sites · 91 MW
- North Dakota1 sites · 88 MW
Relationship graph
Derived from the ownership → operation → tenancy → workload chain at each shared facility, plus company-to-company relationships extracted from cited documents. Speculative links are excluded.
Workloads served by
- Oracle5 sites · ConfirmedOpenAI Stargate Abilene, OpenAI Stargate Michigan, OpenAI Stargate New Mexico
- Microsoft3 sites · LikelyMicrosoft Fairwater Atlanta, Microsoft Fairwater Wisconsin, Microsoft Goodyear
- SoftBank2 sites · ConfirmedOpenAI Stargate Lordstown, OpenAI Stargate Milam
- CoreWeave1 site · LikelyCoreWeave Denton TX
Invests in
- Oracle3 sites · ConfirmedOpenAI Stargate Abilene, OpenAI Stargate Shackelford, OpenAI Stargate Wisconsin
- Vantage Data Centers2 sites · LikelyOpenAI Stargate Shackelford, OpenAI Stargate Wisconsin
- Crusoe1 site · ConfirmedOpenAI Stargate Abilene
| Facility | Role | Location | Status | Power |
|---|---|---|---|---|
| OpenAI Stargate New Mexico | End user | NM | Under construction | 2.45 GW planned |
| OpenAI Stargate Shackelford | End user, Investor | Abilene, TX | Under construction | 1.96 GW planned |
| OpenAI Stargate Michigan | End user | MI | Under construction | 1.4 GW planned |
| OpenAI Stargate Wisconsin | End user, Investor | WI | Under construction | 1.3 GW planned |
| OpenAI Stargate Milam | End user | TX | Under construction | 1.2 GW planned |
| Microsoft Fairwater Atlanta | End user Likely | Fayetteville, GA | Operating | 859 MW |
| OpenAI Stargate Abilene | End user, Investor | Abilene, TX | Operating + expanding | 590 MW |
| Microsoft Fairwater Wisconsin | End user Likely | Mount Pleasant, WI | Operating + expanding | 442 MW |
| CoreWeave Denton TX | End user Likely | Denton, TX | Operating + expanding | 367 MW |
| OpenAI Stargate Lordstown | End user | Warren, OH | Under construction | 300 MW planned |
| Microsoft Goodyear | End user Likely | Goodyear, AZ | Operating | 263 MW |
| Microsoft Project Osmium | End user Speculative | Cumming, IA | Operating | 228 MW |
| Coreweave Helios | End user Speculative | Afton, TX | Operating + expanding | 200 MW |
| CoreWeave Muskogee OK | End user Speculative | Muskogee, OK | Under construction | 181 MW planned |
| CoreWeave Lancaster Greenfield site | End user Speculative | PA | Under construction | 124 MW planned |
| CoreWeave Chester VA | End user Speculative | VA | Operating + expanding | 114 MW |
| CoreWeave Marble NC | End user Speculative | Marble, NC | Operating | 91 MW |
| CoreWeave Ellendale ND | End user Speculative | Ellendale, ND | Operating + expanding | 88 MW |
| CoreWeave Dalton 1 & 2 | End user Speculative | GA | Operating | 40 MW |