CoreWeave Marble NC
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionJun 25, 2024
Model estimate · Satellite imagery
- Jun 25, 2024 · Reported status: under construction[1]
- Jun 25, 2024 · Construction start[1]
- Jun 25, 2024 · Core Scientific announced that CoreWeave would receive about 70 MW of HPC infrastructure from 100 MW of owned infrastructure. Site modifications were expected to begin in H2 2024.[1]
- Mar 13, 2026 · Reported status: expanding[1]
- EnergizationMar 13, 2026
Satellite imagery
- Mar 13, 2026 · The site has been energized. Two of three data halls had been delivered at [37 billable MW](https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm), s[1]
- OperationalMar 13, 2026
Satellite imagery
- Mar 13, 2026 · The site has been energized. Two of three data halls had been delivered at [37 billable MW](https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm), s[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityCoreWeave Marble NC
- →substationOn-site substation[1]Satellite imageryLikely1 substation outline traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 35.18605, -83.91562
- Address
- County
- Cherokee County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
91 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
North Carolina statewide average, July 2026.
- State avg. commercial price
North Carolina statewide average, July 2026.
- Generation within 50 km
17 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Nantahala · Duke Energy Carolinas, LLC | Power plant (Hydroelectric) | 23.7 km | 45 MW | [6] |
| Hiwassee Dam · Tennessee Valley Authority | Power plant (Pumped Storage) | 24.1 km | 174 MW | [6] |
| Cheoah · Brookfield Smoky Mountain Hydropower LP | Power plant (Hydroelectric) | 29.2 km | 143 MW | [6] |
| Santeetlah · Brookfield Smoky Mountain Hydropower LP | Power plant (Hydroelectric) | 29.4 km | 40 MW | [6] |
| Fontana Dam · Tennessee Valley Authority | Power plant (Hydroelectric) | 31.1 km | 304 MW | [6] |
| Calderwood · Brookfield Smoky Mountain Hydropower LP | Power plant (Hydroelectric) | 34.6 km | 156 MW | [6] |
| Apalachia · Tennessee Valley Authority | Power plant (Hydroelectric) | 34.6 km | 82 MW | [6] |
| Chilhowee · Brookfield Smoky Mountain Hydropower LP | Power plant (Hydroelectric) | 41.8 km | 51 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startJun 25, 2024[1]
- First operationalMar 13, 2026[1]
- Expected completion—
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | operational | 50 MW | Mar 13, 2026 | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Jun 25, 2024[1]
Core Scientific announced that CoreWeave would receive about 70 MW of HPC infrastructure from 100 MW of owned infrastructure. Site modifications were expected to begin in H2 2024.
The site has been energized. Two of three data halls had been delivered at 37 billable MW, supporting about 15000 Grace Blackwell GPUs. The third hall was still in commissioning.
Satellite imagery shows the main data hall and southern utility yard substantially complete. No new public MW disclosure, so this keeps the March 2026 public 36 MW state.
Core Scientific said Marble was fully handed over to CoreWeave with about 65 MW of billable customer power online.
All claims (provenance audit)
32| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | CoreWeave Marble NC | [1] | Likely | 2026-05-06 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-06-25 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-13 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-04-17 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-05-06 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-06 | Shown |
| Address | 155 Palmer Ln, Marble, NC 28905 | [1] | Likely | 2026-05-06 | Shown |
| Owner | CoreWeaveOwner: CoreWeave | [1] | Confirmed | 2026-05-06 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Speculative | 2026-05-06 | Shown |
| Utility | Duke Energyterritory 5416: DUKE ENERGY CAROLINAS, LLC (INVESTOR OWNED, DUKE ENERGY CORP) | [2] derived | Likely | 2022 | Shown |
| Current facility power | 91 MW | [1] estimated | Likely | 2026-05-06 | Shown |
| Current facility power | 50 MW | [1] estimated | Likely | 2026-03-13 | Superseded / alternative |
| Current facility power | 50 MW | [1] estimated | Likely | 2026-04-17 | Superseded / alternative |
| Current IT capacity | 65 MW | [1] estimated | Likely | 2026-05-06 | Shown |
| Current IT capacity | 36 MW | [1] estimated | Likely | 2026-03-13 | Superseded / alternative |
| Current IT capacity | 36 MW | [1] estimated | Likely | 2026-04-17 | Superseded / alternative |
| Estimated annual consumption | 558 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | DUK | [2] derived | Likely | — | Shown |
| State avg. industrial price | 8.37¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.73¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.05 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-05-06 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-05-06 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-06-25 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-03-13 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-04-17 | Superseded / alternative |
| Capital cost / investment | $2.5B | [1] estimated | Likely | 2026-05-06 | Shown |
| Compute (H100-equivalents) | 78,800 | [1] estimated | Likely | 2026-05-06 | Shown |
| Chip types | B200 | [1] | Confirmed | 2026-05-06 | Shown |
| Construction start | Jun 25, 2024 | [1] derived | Likely | 2026-05-06 | Shown |
| First operational | Mar 13, 2026 | [1] derived | Likely | 2026-05-06 | Shown |