DC
/

CoreWeave Marble NC

OperatingAI campusCampusMarble, Cherokee County, North Carolina
70% profile completeness
32 claims from 10 sources
Current facility power
91 MW[1]
Likelyestimated
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
$2.5B[1]
Likelyestimated
First operational
Mar 13, 2026[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Duke Energy · None (non-RTO region)
Substation: On-site substation

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
91 MW[1]
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionJun 25, 2024
    Model estimate · Satellite imagery
    • Jun 25, 2024 · Reported status: under construction[1]
    • Jun 25, 2024 · Construction start[1]
    • Jun 25, 2024 · Core Scientific announced that CoreWeave would receive about 70 MW of HPC infrastructure from 100 MW of owned infrastructure. Site modifications were expected to begin in H2 2024.[1]
    • Mar 13, 2026 · Reported status: expanding[1]
  3. EnergizationMar 13, 2026
    Satellite imagery
    • Mar 13, 2026 · The site has been energized. Two of three data halls had been delivered at [37 billable MW](https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm), s[1]
  4. OperationalMar 13, 2026
    Satellite imagery
    • Mar 13, 2026 · The site has been energized. Two of three data halls had been delivered at [37 billable MW](https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm), s[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    CoreWeave Marble NC
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    1 substation outline traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Duke Energy[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[4]
    Service territoryLikely
    Balancing authority: DUK
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
35.18605, -83.91562
Address
155 Palmer Ln, Marble, NC 28905[1]Likely
County
Cherokee County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    OpenAI[1]Speculative
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
CoreWeave[1]Confirmed
End user
OpenAI[1]Speculative
Utility

Location falls inside this utility's retail service territory.

Power (all fields)

Current facility power
91 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
65 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
558 GWh/yr[3]Speculativeestimated

91 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[4]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
DUK[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
8.37¢/kWh[5]Confirmed

North Carolina statewide average, July 2026.

State avg. commercial price
10.73¢/kWh[5]Confirmed

North Carolina statewide average, July 2026.

Generation within 50 km
1.05 GW[6]Confirmedderived

17 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Nantahala · Duke Energy Carolinas, LLCPower plant (Hydroelectric)23.7 km45 MW[6]
Hiwassee Dam · Tennessee Valley AuthorityPower plant (Pumped Storage)24.1 km174 MW[6]
Cheoah · Brookfield Smoky Mountain Hydropower LPPower plant (Hydroelectric)29.2 km143 MW[6]
Santeetlah · Brookfield Smoky Mountain Hydropower LPPower plant (Hydroelectric)29.4 km40 MW[6]
Fontana Dam · Tennessee Valley AuthorityPower plant (Hydroelectric)31.1 km304 MW[6]
Calderwood · Brookfield Smoky Mountain Hydropower LPPower plant (Hydroelectric)34.6 km156 MW[6]
Apalachia · Tennessee Valley AuthorityPower plant (Hydroelectric)34.6 km82 MW[6]
Chilhowee · Brookfield Smoky Mountain Hydropower LPPower plant (Hydroelectric)41.8 km51 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Jun 25, 2024[1]
  5. First operational
    Mar 13, 2026[1]
  6. Expected completion
    —
Buildings (planned)
1[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
1[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational50 MWMar 13, 2026[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$2.5B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
B200[1]Confirmed
Compute (H100-equivalents)
78,800[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    36 MWMar 13, 2026[1]→65 MWMay 6, 2026[1]
  • Current facility power
    50 MWMar 13, 2026[1]→91 MWMay 6, 2026[1]
  • Buildings operational
    0Jun 25, 2024[1]→1Mar 13, 2026[1]
  • Status
    Under constructionJun 25, 2024[1]→Operating + expandingMar 13, 2026[1]→OperatingMay 6, 2026[1]

Timeline

Construction start: Jun 25, 2024[1]
First operational: Mar 13, 2026[1]
  1. Jun 25, 2024[1]

    Core Scientific announced that CoreWeave would receive about 70 MW of HPC infrastructure from 100 MW of owned infrastructure. Site modifications were expected to begin in H2 2024.

  2. Mar 13, 202650 MW facility power· 1 buildings operational[1]

    The site has been energized. Two of three data halls had been delivered at 37 billable MW, supporting about 15000 Grace Blackwell GPUs. The third hall was still in commissioning.

  3. Apr 17, 202650 MW facility power· 1 buildings operational[1]

    Satellite imagery shows the main data hall and southern utility yard substantially complete. No new public MW disclosure, so this keeps the March 2026 public 36 MW state.

  4. May 6, 202691 MW facility power· 1 buildings operational[1]

    Core Scientific said Marble was fully handed over to CoreWeave with about 65 MW of billable customer power online.

All claims (provenance audit)

32
FieldValueSourceConfidenceAs ofStatus
NameCoreWeave Marble NC[1] Likely2026-05-06Shown
StatusUnder construction[1] derivedLikely2024-06-25Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-03-13Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-04-17Superseded / alternative
StatusOperating[1] derivedLikely2026-05-06Shown
Facility typeAI campus[1] derivedLikely2026-05-06Shown
Address155 Palmer Ln, Marble, NC 28905[1] Likely2026-05-06Shown
OwnerCoreWeaveOwner: CoreWeave[1] Confirmed2026-05-06Shown
End usersOpenAIUsers: OpenAI[1] Speculative2026-05-06Shown
UtilityDuke Energyterritory 5416: DUKE ENERGY CAROLINAS, LLC (INVESTOR OWNED, DUKE ENERGY CORP)[2] derivedLikely2022Shown
Current facility power91 MW[1] estimatedLikely2026-05-06Shown
Current facility power50 MW[1] estimatedLikely2026-03-13Superseded / alternative
Current facility power50 MW[1] estimatedLikely2026-04-17Superseded / alternative
Current IT capacity65 MW[1] estimatedLikely2026-05-06Shown
Current IT capacity36 MW[1] estimatedLikely2026-03-13Superseded / alternative
Current IT capacity36 MW[1] estimatedLikely2026-04-17Superseded / alternative
Estimated annual consumption558 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTONone (non-RTO region)[4] derivedLikely—Shown
Balancing authorityDUK[2] derivedLikely—Shown
State avg. industrial price8.37¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price10.73¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km1.05 GW[6] derivedConfirmed202502Shown
Buildings (planned)1[1] derivedLikely2026-05-06Shown
Buildings operational1[1] estimatedLikely2026-05-06Shown
Buildings operational0[1] estimatedLikely2024-06-25Superseded / alternative
Buildings operational1[1] estimatedLikely2026-03-13Superseded / alternative
Buildings operational1[1] estimatedLikely2026-04-17Superseded / alternative
Capital cost / investment$2.5B[1] estimatedLikely2026-05-06Shown
Compute (H100-equivalents)78,800[1] estimatedLikely2026-05-06Shown
Chip typesB200[1] Confirmed2026-05-06Shown
Construction startJun 25, 2024[1] derivedLikely2026-05-06Shown
First operationalMar 13, 2026[1] derivedLikely2026-05-06Shown