CoreWeave Muskogee OK
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — SPP does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionNov 18, 2024
Model estimate · Satellite imagery
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityCoreWeave Muskogee OK
- →substationOn-site substation[1]Satellite imageryLikely2 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityOklahoma Gas & Electric CO[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 35.69569, -95.38647
- Address
- County
- Muskogee County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2027-12-31); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Oklahoma statewide average, July 2026.
- State avg. commercial price
Oklahoma statewide average, July 2026.
- Generation within 50 km
7 EIA-reported plants within 50 km.
- Generation queued in county
6 active generation interconnection requests in Muskogee County: Solar 890 MW, Storage 475 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Georgia-Pacific Muskogee · Georgia-Pacific Muskogee LLC | Power plant (Natural Gas) | 9.3 km | 68 MW | [6] |
| Muskogee · Oklahoma Gas & Electric Co | Power plant (Natural Gas) | 11.5 km | 1.51 GW | [6] |
| Fort Gibson · USCE-Tulsa District | Power plant (Hydroelectric) | 24.1 km | 51 MW | [6] |
| Webbers Falls · USCE-Tulsa District | Power plant (Hydroelectric) | 25.1 km | 75 MW | [6] |
| Tenkiller Ferry · USCE-Tulsa District | Power plant (Hydroelectric) | 32.3 km | 42 MW | [6] |
| Eufaula Dam · USCE-Tulsa District | Power plant (Hydroelectric) | 43.3 km | 95 MW | [6] |
| Oneta Energy Center · Oneta Power LLC | Power plant (Natural Gas) | 44.9 km | 1.09 GW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| GEN-2024-268 at Keefton 345 kV SubstationSPP GEN-2024-268 | Solar | In study · proposed 2030-12 | 390 MW | [4] |
| GEN-2026-SR27 at Pecan Creek 345kV SubstationSPP GEN-2026-SR27 | Storage | In study · proposed 2028-06 | 300 MW | [4] |
| GEN-2021-053 at Pecan Creek 345 kV SubstationSPP GEN-2021-053 | Solar | IA signed · proposed 2031-06 | 300 MW | [4] |
| GEN-2017-092 at Canadian River-Muskogee and Muskogee-Seminole 345kVSPP GEN-2017-092 | Solar | IA signed · proposed 2026-12 | 200 MW | [4] |
| GEN-2018-024 at Canadian River-Muskogee and Muskogee-Seminole 345kVSPP GEN-2018-024 | Storage | IA signed · proposed 2028-12 | 100 MW | [4] |
| GEN-2021-052 at Pecan Creek 345kV substationSPP GEN-2021-052 | Storage | IA signed · proposed 2031-06 | 75 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startNov 18, 2024[1]
- First operationalDec 31, 2026[1]Projected
- Expected completionDec 31, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-12-31); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Nov 18, 2024[1]
Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center. Core Scientific says the site will provide about 70 MW of critical IT load for CoreWeave's NVIDIA GPUs.
- Apr 9, 2026[1]
Based on satellite imagery, Building 1 looks mostly complete, but the site still appears to be in construction or commissioning. Not much progress has happened in the past 4 months, and a Q2 2026 finish seems unlikely.
- Jun 13, 2026[1]
Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard work directly surrounding it, and the lack of a parking lot. Building 2 (The one not leased to CoreWeave) is still in land clearing phase.
Estimating building 1 is operational by the end of the year, judging from the building currently completed, the completed power substation to the southwest. The surrounding yard work/construction will likely still take several months, judging from the slow pace.
Core Scientific expects initial delivery of the second, unleased 82.5 MW Muskogee building in Q4 2027. Not signed to have CoreWeave GPUs as of yet, but may change in the future. Source: https://www.sec.gov/Archives/edgar/data/1839341/000162828026030918/exhibit991polarispressre.htm
All claims (provenance audit)
24| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | CoreWeave Muskogee OK | [1] | Likely | 2026-06-13 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-11-18 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-04-09 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-06-13 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-13 | Shown |
| Address | 1525 W 43rd St S, Muskogee, OK 74401, USA | [1] | Likely | 2026-06-13 | Shown |
| Owner | CoreWeaveOwner: CoreWeave | [1] | Confirmed | 2026-06-13 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Speculative | 2026-06-13 | Shown |
| Utility | Oklahoma Gas & Electric COterritory 14063: OKLAHOMA GAS & ELECTRIC CO (INVESTOR OWNED, OG&E ENERGY) | [2] derived | Unverified | 2022 | Shown |
| Planned capacity | 181 MW | [1] estimated | Likely | 2026-06-13 | Shown |
| ISO / RTO | SPPSOUTHWEST POWER POOL | [3] derived | Likely | — | Shown |
| Balancing authority | SWPP | [2] derived | Likely | — | Shown |
| Generation queued in county | 1.37 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 8.16¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.32¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.93 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-06-13 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-06-13 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-11-18 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-04-09 | Superseded / alternative |
| Chip types | B300 | [1] | Confirmed | 2026-06-13 | Shown |
| Construction start | Nov 18, 2024 | [1] derived | Likely | 2026-06-13 | Shown |
| First operational | Dec 31, 2026 | [1] estimated | Speculative | 2026-06-13 | Shown |
| Expected completion | Dec 31, 2027 | [1] estimated | Speculative | 2026-06-13 | Shown |