Crusoe Abilene Expansion
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityCrusoe Abilene Expansion
- →substationUnnamed substation (345 kV)[4]Proximity onlyUnverifiedNearest mapped substation, 1.31 km away. Proximity does not establish that it serves the site.
- →transmission345 kV line[4]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.38 km away). Not confirmed as the supply path.
- →utilityTaylor Electric Coop INC - (Tx)[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 32.49249, -99.78262
- Address
- County
- Taylor County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: AEP Texas North Company, Coleman County Elec Coop, INC.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2027-11-11); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
13 EIA-reported plants within 50 km.
- Generation queued in county
14 active generation interconnection requests in Taylor County: Solar 2,188 MW, Storage 920 MW, Wind 377 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 69 kV line | Transmission line | 0.62 km | 69 kV | [4] |
| 138 kV line | Transmission line | 0.69 km | 138 kV | [4] |
| 345 kV line | Transmission line | 1.38 km | 345 kV | [4] |
| Post Oak Wind LLC · Mesquite Wind LLC | Power plant (Wind) | 12.1 km | 200 MW | [7] |
| Mesquite Wind Power LLC · Mesquite Wind LLC | Power plant (Wind) | 30.9 km | 200 MW | [7] |
| Buffalo Gap 3 Wind Farm · AES Distributed Energy | Power plant (Wind) | 37.5 km | 170 MW | [7] |
| Anson Solar Center, LLC · Engie North America | Power plant (Solar) | 37.6 km | 200 MW | [7] |
| Horse Hollow Wind Energy Center · FPL Energy Horse Hollow LLC | Power plant (Wind) | 40.3 km | 736 MW | [7] |
| Buffalo Gap 2 Wind Farm · AES Distributed Energy | Power plant (Wind) | 41.8 km | 233 MW | [7] |
| Trent Wind Farm · Trent Wind Farm LLC | Power plant (Wind) | 43.1 km | 152 MW | [7] |
| Hackberry Wind Farm · Hackberry Wind LLC | Power plant (Wind) | 45.6 km | 162 MW | [7] |
| Unnamed substation | Substation | 1.31 km | 345 kV | [4] |
| Abilene Northwest Substation · American Electric Power | Substation | 1.33 km | 138 kV | [4] |
| Unnamed substation | Substation | 1.38 km | 138 kV | [4] |
| Vogel Street Substation · American Electric Power | Substation | 2.7 km | 69 kV | [4] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Key City Solar SLFERCOT 26INR0701 · Key City Solar LLC | Solar | In study · proposed 2029-03 | 989 MW | [5] |
| Dog Star Solar IERCOT 27INR0503 · Dog Star Solar LLC | Solar | In study · proposed 2027-12 | 499 MW | [5] |
| Dog Star Solar IIERCOT 27INR0504 · Dog Star Solar LLC | Solar | In study · proposed 2027-12 | 499 MW | [5] |
| Forts Trail BESSERCOT 24INR0341 · JC Central Bluff, LLC | Storage | In study · proposed 2029-03 | 209 MW | [5] |
| Forts Trail BESS 2ERCOT 24INR0488 · JC Central Bluff, LLC | Storage | In study · proposed 2029-03 | 206 MW | [5] |
| Taylor County Paul StorageERCOT 26INR0618 · DM-TCP, LLC | Storage | In study · proposed 2029-12 | 205 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startNov 2, 2025[1]
- First operationalSep 17, 2027[1]Projected
- Expected completionNov 11, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-11-11); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Nov 2, 2025[1]
Land clearing begins for Buildings 1-2.
- Jan 15, 2026[1]
Land clearing continues.
Building 1 operational. Based on the completion date to "build-out an office and data hall", stated in a regulatory filing.
Building 2 operational. Based on the completion date to "build-out an office and data hall", stated in a regulatory filing.
All claims (provenance audit)
26| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Crusoe Abilene Expansion | [1] | Likely | 2026-01-15 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-11-02 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-01-15 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-01-15 | Shown |
| Address | 5502 Spinks Rd, Abilene, TX 79601 | [1] | Likely | 2026-01-15 | Shown |
| Owner | MicrosoftOwner: Microsoft | [1] | Confirmed | 2026-01-15 | Shown |
| End users | MicrosoftUsers: Microsoft | [1] | Likely | 2026-01-15 | Shown |
| Utility | Taylor Electric Coop INC - (Tx)territory 27369: TAYLOR ELECTRIC COOP INC - (TX) (COOPERATIVE, TAYLOR ELECTRIC C | [2] derived | Unverified | 2022 | Shown |
| Investors | NVIDIAInvestors: NVIDIA | [1] | Confirmed | 2026-01-15 | Shown |
| Planned capacity | 941 MW | [1] estimated | Likely | 2026-01-15 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [3] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (345 kV)way/1537802646 | [4] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 1.3 km | [4] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [4] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 3.49 GW | [5] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.39 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-01-15 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-01-15 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-11-02 | Superseded / alternative |
| Chip types | Rubin | [1] | Confirmed | 2026-01-15 | Shown |
| Construction start | Nov 2, 2025 | [1] derived | Likely | 2026-01-15 | Shown |
| First operational | Sep 17, 2027 | [1] estimated | Speculative | 2026-01-15 | Shown |
| Expected completion | Nov 11, 2027 | [1] estimated | Speculative | 2026-01-15 | Shown |