Data centers in Taylor County, Texas
Datacenter Source tracks 2 data centers in Taylor County, Texas. Facilities that disclose power add up to 590 MW online and 1.53 GW in the pipeline — floors, since 100% report a figure.
Follow
Get changes to Taylor County, Texas
Or subscribe in a feed reader: RSS / Atom
Facilities
- OpenAI Stargate Abilene AI campus · AbileneOperating + expanding590 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.+590 MW pipeline EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Crusoe Abilene Expansion AI campus · AbileneUnder construction+941 MW pipeline EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Interconnection-queue requests filed here (last two years)
Requests to connect generation or large loads, as the ISO/RTO publishes them. Filing is an application, not a commitment to build.
No dated queue filings for this county in the files we ingest (some ISOs don't publish a county or filing date).
Local impact
Water, on-site generation and air permits, incentives, regulatory events and large-load tariffs, where a source documents them. Counts are of sourced records, not of the state's totals.
Not yet collected
1 sites with documented on-site generation (MW not reported)
Not yet collected
Not yet collected for this state's utilities.
Not yet collected
Recent changes
- May 23, 2026 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current IT capacity: 211 MW → 421 MW
- May 23, 2026 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current facility power: 295 MW → 590 MW
- May 23, 2026 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 2 → 4
- May 23, 2026 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. New capacity online: Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 …
- Dec 24, 2025 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current IT capacity: 105 MW → 211 MW
- Dec 24, 2025 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current facility power: 147 MW → 295 MW
- Dec 24, 2025 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 1 → 2
- Dec 24, 2025 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. New capacity online: Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a TDLR filing, but this date is also cons…
- Nov 2, 2025 · Crusoe Abilene Expansion EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Construction started: Land clearing begins for Buildings 1-2.
- Sep 26, 2025 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 0 → 1
- Sep 26, 2025 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Status: Under construction → Operating + expanding
- Sep 26, 2025 · OpenAI Stargate Abilene EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. New capacity online: Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe announcement. While the first phase consists of Building 1 and 2, the language doesn't outright confirm t…