Facebook Fort Worth Datacenter
Part of Meta — Tarrant County, TX campus
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityFacebook Fort Worth Datacenter
- →substationFacebook Data Center (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.31 km away. Proximity does not establish that it serves the site.
- →transmission345 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.87 km away). Not confirmed as the supply path.
- →utilityDenton County Elec Coop, INC[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
ERCOT 26INR0487 Anglin BESS · Fort Worth BESS LLC · Storage | Possibly related generation Speculative Generation request name/developer shares “fort” with this facility, in the same county. Not confirmed as serving it. | System impact study SS Completed, FIS Started, No IA | 206 | — | — | Sep 30, 2028 | 1883 EVRSW 138kV | [4] Sep 1, 2026 |
On-site & dedicated generation
- ERCOT 26INR0487 Anglin BESS (Storage, 206 MW requested)[4]Generation request name/developer shares “fort” with this facility, in the same county. Not confirmed as serving it.Battery storageArrangement unknown206 MWSpeculative
Location & imagery
Mapped outline- Coordinates
- 32.98377, -97.25935
- Address
- County
- Tarrant County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 4 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Tri-County Electric Coop, INC (Tx), United Electric Coop Service INC - (Tx), Oncor Electric Delivery Company LLC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
50 EIA-reported plants within 50 km.
- Generation queued in county
4 active generation interconnection requests in Tarrant County: Storage 792 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line · Oncor | Transmission line | 0.29 km | 138 kV | [1] |
| 345 kV line | Transmission line | 0.87 km | 345 kV | [1] |
| Chisholm Grid Energy Storage System · Chisholm Grid, LLC | Power plant (Batteries) | 14.8 km | 100 MW | [6] |
| Denton Energy Center · City of Denton - (TX) | Power plant (Natural Gas) | 26.1 km | 226 MW | [6] |
| Spencer · City of Garland - (TX) | Power plant (Natural Gas) | 27.7 km | 122 MW | [6] |
| Handley · Constellation Power, Inc | Power plant (Natural Gas) | 28.7 km | 1.25 GW | [6] |
| Connolly Bess · BT Connolly Storage, LLC | Power plant (Batteries) | 29.3 km | 125 MW | [6] |
| Noble Solar · BT Noble Solar, LLC | Power plant (Solar) | 30.9 km | 400 MW | [6] |
| Porter Solar, LLC (Tx) · Porter Solar, LLC | Power plant (Solar) | 37.8 km | 245 MW | [6] |
| Mountain Creek · Mountain Creek Power, LLC | Power plant (Natural Gas) | 41.9 km | 808 MW | [6] |
| Facebook Data Center · Oncor | Substation | 0.31 km | 138 kV | [1] |
| Roanoke Substation | Substation | 0.93 km | 345 kV | [1] |
| Unnamed substation | Substation | 2.17 km | 138 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Team Ranch StorageERCOT 24INR0763 · BAF Storage, LLC | Storage | In study · proposed 2027-03 | 307 MW | [4] |
| Anglin BESSERCOT 26INR0487 · Fort Worth BESS LLC | Storage | In study · proposed 2028-09 | 206 MW | [4] |
| Stockyard Grid BattERCOT 21INR0492 · Stockyard Grid, LLC | Storage | IA signed · proposed 2028-12 | 151 MW | [4] |
| Salazar BESSERCOT 28INR0116 · Salazar Energy Storage LLC | Storage | In study · proposed 2028-07 | 128 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
Other buildings on this campus
2- Facebook Fort Worth DatacenterOperating · 436,400 sq ft footprint
- Facebook Fort Worth DatacenterOperating · 755,300 sq ft footprint
All claims (provenance audit)
18| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Facebook Fort Worth Datacenterway/500820007 name=Facebook Fort Worth Datacenter | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-09-27 | Shown |
| Address | 4500 Like Way | [1] | Likely | 2026-09-27 | Shown |
| Operator | Metaoperator=Meta | [1] | Likely | 2026-09-27 | Shown |
| Utility | Denton County Elec Coop, INCterritory 5078: DENTON COUNTY ELEC COOP, INC (COOPERATIVE, DENTON COUNTY ELEC CO | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [3] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Facebook Data Center (138 kV)way/578383232 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 792 MW | [4] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.47 GW | [6] derived | Confirmed | 202502 | Shown |
| Floor area | 636,100 sq ft | [1] estimated | Unverified | 2026-09-27 | Shown |
| Building footprint | 636,100 sq ft | [1] derived | Likely | 2026-09-27 | Shown |
| Floors | 1building:levels=1 | [1] | Likely | 2026-09-27 | Shown |