Google Bristow
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationApr 29, 2024
Satellite imagery
- Apr 29, 2024 · Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.[1]
- Apr 29, 2025 · Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.[1]
- May 20, 2026 · Building 3 is operational, based off of colored motion artifacts from cooling towers.[1]
- OperationalApr 29, 2024
Satellite imagery · Government record
- Apr 29, 2024 · Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.[1]
- Apr 29, 2025 · Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.[1]
- May 20, 2026 · Building 3 is operational, based off of colored motion artifacts from cooling towers.[1]
- Sep 27, 2026 · County land use: Use code 191[2]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Bristow
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.44 km away
- →transmission535;2114 (500 kV)[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.94 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 38.77699, -77.58512
- Address
- County
- Prince William County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- End user
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Northern Virginia Elec Coop.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
286 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Virginia statewide average, July 2026.
- State avg. commercial price
Virginia statewide average, July 2026.
- Generation within 50 km
29 EIA-reported plants within 50 km.
- Generation queued in county
16 active generation interconnection requests in Prince William County: Storage 1,350 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line | Transmission line | 0.43 km | 230 kV | [6] |
| 2161 · Virginia Electric & Power Company | Transmission line | 0.47 km | 230 kV | [6] |
| 535;2114 · Virginia Electric & Power Company | Transmission line | 0.94 km | 500 kV | [6] |
| Morrisville Sub Dominion to Loudoun Sub Dominion · Dominion Energy | Transmission line | 0.97 km | 500 kV | [6] |
| Morrisville Sub DOMINION to Loudoun Sub DOMINION · Dominion Energy | Transmission line | 1.97 km | 500 kV | [6] |
| 2151;2163 | Transmission line | 1.97 km | 230 kV | [6] |
| Remington · Virginia Electric & Power Co | Power plant (Natural Gas) | 30.5 km | 604 MW | [9] |
| Covanta Fairfax Energy · Covanta Fairfax Inc | Power plant (Biomass) | 31.2 km | 98 MW | [9] |
| Potomac Energy Center, LLC · Potomac Energy Center LLC | Power plant (Natural Gas) | 31.4 km | 766 MW | [9] |
| Marsh Run Generation Facility · Old Dominion Electric Coop | Power plant (Natural Gas) | 31.9 km | 481 MW | [9] |
| Possum Point · Virginia Electric & Power Co | Power plant (Natural Gas) | 37.6 km | 645 MW | [9] |
| Covanta Alexandria/Arlington Energy · Covanta Alexandria/Arlington | Power plant (Biomass) | 39.6 km | 29 MW | [9] |
| Montgomery County Resource Recovery · Covanta Montgomery, Inc. | Power plant (Biomass) | 48.4 km | 54 MW | [9] |
| Dickerson Power · Dickerson Power, LLC | Power plant (Natural Gas) | 49.2 km | 299 MW | [9] |
| Unnamed substation | Substation | 0.44 km | 230 kV | [6] |
| Rollins Ford Substation · Virginia Electric and Power Company | Substation | 0.52 km | 230 kV | [6] |
| Linton Hall Substation · NOVEC | Substation | 0.8 km | 230 kV | [6] |
| Unnamed substation | Substation | 0.81 km | 230 kV | [6] |
| Atlantic Substation · NOVEC | Substation | 0.93 km | 230 kV | [6] |
| Gainesville Substation | Substation | 2.31 km | 230 kV | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Gainesville-Loudoun 230 kVPJM AI2-231 | Storage | In study · proposed 2023-10 | 200 MW | [7] |
| Nokesville-Vint Hill 230 kVPJM AG2-113 | Storage | In study · proposed 2022-08 | 150 MW | [7] |
| Catharpin 230 kVPJM AG2-284 | Storage | In study · proposed 2023-12 | 150 MW | [7] |
| Liberty 230 kVPJM AG2-304 | Storage | In study · proposed 2023-12 | 150 MW | [7] |
| Possum Point 230 kVPJM AG2-306 | Storage | In study · proposed 2023-12 | 150 MW | [7] |
| Possum Point 230kVPJM AH2-034 | Storage | In study · proposed 2028-12 | 100 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 7496-47-2405 Prince William County, VA | NOVA MANGO FARMS LLC C/O CORPORATION SERVICE COMPANY 251 LITTLE FALLS DR, WILMINGTON, DE | 253.92 | Use code 191 | — | [2] |
- Site area
Sum of county land area across parcels.
- Land use
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
Size
- Parcel / land records
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity
- Current facility power
- Buildings operational
- Status
Timeline
- Jul 1, 2021[1]
Land clearing begins.
Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.
Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.
Building 3 is operational, based off of colored motion artifacts from cooling towers.
- Jul 7, 2021[2]
Deed recorded for parcel 7496-47-2405 (owner of record: Nova Mango Farms LLC C/O Corporation Service Company).
Buildings on this campus
3- Google Mango Farm Building 1Operating · 290,200 sq ft footprint
- Google Mango FarmOperating · 290,000 sq ft footprint
- Google Mango Farm Building 3Operating · 290,000 sq ft footprint
All claims (provenance audit)
44| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Bristow | [1] | Likely | 2026-05-20 | Shown |
| Status | Under construction | [1] derived | Likely | 2021-07-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-04-29 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-04-29 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-05-20 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-20 | Shown |
| Address | 13001 Rollins Ford Road, Bristow, VA 20136 | [1] | Likely | 2026-05-20 | Shown |
| Property owner of record | Nova Mango Farms LLC C/O Corporation Service CompanyParcel 7496-47-2405: NOVA MANGO FARMS LLC C/O CORPORATION SERVICE COMPANY | [2] | Confirmed | 2026-09-27 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-05-20 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Confirmed | 2026-05-20 | Shown |
| Utility | Dominion Energyterritory 19876: VIRGINIA ELECTRIC & POWER CO (INVESTOR OWNED, DOMINION RESOURCE | [3] derived | Unverified | 2022 | Shown |
| Current facility power | 286 MW | [1] estimated | Likely | 2026-05-20 | Shown |
| Current facility power | 104 MW | [1] estimated | Likely | 2024-04-29 | Superseded / alternative |
| Current facility power | 208 MW | [1] estimated | Likely | 2025-04-29 | Superseded / alternative |
| Current IT capacity | 238 MW | [1] estimated | Likely | 2026-05-20 | Shown |
| Current IT capacity | 87 MW | [1] estimated | Likely | 2024-04-29 | Superseded / alternative |
| Current IT capacity | 174 MW | [1] estimated | Likely | 2025-04-29 | Superseded / alternative |
| Estimated annual consumption | 1,754 GWh/yr | [4] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [5] derived | Likely | — | Shown |
| Balancing authority | PJM | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (230 kV)way/1113210772 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 500 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.35 GW | [7] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.07¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.68¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.13 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 3 | [1] derived | Likely | 2026-05-20 | Shown |
| Buildings operational | 3 | [1] estimated | Likely | 2026-05-20 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2021-07-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-04-29 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-04-29 | Superseded / alternative |
| Site area | 253.9 acres | [2] | Confirmed | 2026-09-27 | Shown |
| Capital cost / investment | $9B | [1] estimated | Likely | 2026-05-20 | Shown |
| Parcel / land records | 7496-47-2405 (Prince William County) | [2] | Confirmed | 2026-09-27 | Shown |
| Land use | Use code 191 | [2] | Confirmed | 2026-09-27 | Shown |
| Compute (H100-equivalents) | 209,900 | [1] estimated | Likely | 2026-05-20 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-05-20 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-05-20 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-05-20 | Shown |
| Chip types | TPU v7 | [1] | Confirmed | 2026-05-20 | Shown |
| Land acquired | Jul 7, 2021 | [2] derived | Confirmed | 2026-09-27 | Shown |
| Construction start | Jul 1, 2021 | [1] derived | Likely | 2026-05-20 | Shown |
| First operational | Apr 29, 2024 | [1] derived | Likely | 2026-05-20 | Shown |