Google Columbus

Operating + expandingAI campusCampusColumbus, Franklin County, Ohio
90% profile completeness
62 claims from 11 sources
Current facility power
364 MW[1]
Likelyestimated
Planned capacity
464 MW[1]
Likelyestimated
Floor area
1.17M sq ft[2]
Confirmed
Buildings (planned)
Likelyderived
Capital cost / investment
$11.5B[1]
Likelyestimated
First operational
Apr 1, 2024[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H1 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery and government record.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
American Electric Power · PJM
Substation: On-site substation

Power reality

Announced
464 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
100 MW[1]
Building 5 under construction (satellite-tracked phases)
Operational
364 MW[1]
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1]
  • Stated date: Next projected milestone: 2027-07-01 (modeled/speculative)[1]
  • Required: 464 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredJun 8, 2022
    Government record
    • Jun 8, 2022 · Land acquisition / deed recorded[2]
    • Jun 8, 2022 · Deed/transfer recorded for parcel 510-180711 (no sale price disclosed).[2]
    • Sep 27, 2026 · Owner of record in county parcel data[2]
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionOct 1, 2021
    Model estimate · Satellite imagery
    • Oct 1, 2021 · Reported status: under construction[1]
    • Oct 1, 2021 · Construction start[1]
    • Oct 1, 2021 · Land clearing begins on the eastern half of the site, for Buildings 1-2[1]
    • Apr 1, 2024 · Reported status: expanding[1]
  3. EnergizationApr 1, 2024
    Satellite imagery
    • Apr 1, 2024 · Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building [1]
    • Mar 1, 2025 · Building 2 operational. Parking complete, no more visible construction.[1]
    • Oct 1, 2025 · Building 3 operational. Surrounding roads finished, no more visible construction.[1]
    • May 1, 2026 · Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost co[1]
  4. OperationalApr 1, 2024
    Satellite imagery · Government record
    • Apr 1, 2024 · Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building [1]
    • Mar 1, 2025 · Building 2 operational. Parking complete, no more visible construction.[1]
    • Oct 1, 2025 · Building 3 operational. Surrounding roads finished, no more visible construction.[1]
    • May 1, 2026 · Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost co[1]
    • Sep 27, 2026 · County land use: data center[2]
    • Sep 27, 2026 · County records a 1,172,656 sq ft building[2]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.

Grid path

  1. facility
    Google Columbus
  2. substation
    On-site substation[1][6]
    Satellite imageryLikely
    5 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.34 km away
  3. transmission
    345 kV line[6]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (1.62 km away). Not confirmed as the supply path.
  4. utility
    American Electric Power[3]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    PJM[5]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
39.84940, -82.99757
Address
5076 S High St, Columbus, OH 43207[1]Likely
County
Franklin County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Property owner of record
Owner
Google[1]Confirmed
End user
Utility

Location falls inside this utility's retail service territory.

Power (all fields)

Current facility power
364 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
303 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
464 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.

Estimated annual consumption
2,232 GWh/yr[4]Speculativeestimated

364 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[5]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[3]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (138 kV)[6]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.3 km[6]Likelyderived
Highest-voltage line nearby
345 kV[6]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.95¢/kWh[8]Confirmed

Ohio statewide average, July 2026.

State avg. commercial price
14.06¢/kWh[8]Confirmed

Ohio statewide average, July 2026.

Generation within 50 km
1.98 GW[9]Confirmedderived

15 EIA-reported plants within 50 km.

Generation queued in county
1.66 GW[7]Confirmedderived

8 active generation interconnection requests in Franklin County: Solar 845 MW, Storage 810 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
138 kV lineTransmission line0.52 km138 kV[6]
Cyprus 138kV Extension · American Electric PowerTransmission line0.9 km138 kV[6]
345 kV line · American Electric PowerTransmission line1.62 km345 kV[6]
Darby Power, LLC · Darby Power, LLCPower plant (Natural Gas)21.5 km480 MW[9]
Big Plain Solar, LLC · Leeward Asset Management, LLCPower plant (Solar)28.3 km196 MW[9]
Fox Squirrel Solar · EDF Renewable Asset Holdings, Inc.Power plant (Solar)32.6 km577 MW[9]
O'Shaughnessy Hydro · City of Columbus - (OH)Power plant (Hydroelectric)35.5 km5 MW[9]
Atlanta Farms Solar · Dominion Renewable EnergyPower plant (Solar)35.6 km200 MW[9]
Yellowbud Solar, LLC · Yellowbud Solar LLCPower plant (Solar)39 km274 MW[9]
Salt City Solar Project - Hybrid · Salt City Solar LLCPower plant (Solar)48.4 km50 MW[9]
Madison Fields Solar Project, LLC · Madison Fields Solar Project, LLCPower plant (Solar)48.7 km180 MW[9]
Unnamed substationSubstation0.34 km138 kV[6]
Unnamed substationSubstation0.52 km138 kV[6]
Unnamed substationSubstation0.55 km138 kV[6]
Cyprus Switching Station · AEP OhioSubstation0.91 km138 kV[6]
Parsons Substation · AEP OhioSubstation1.24 km138 kV[6]
Unnamed substationSubstation2.64 km69 kV[6]
Largest queued generation in this countyFuelQueue statusMWSource
Beatty 345 kVPJM AG2-376StorageIn study · proposed 2024-11400 MW[7]
Cole 345 kVPJM AH1-318StorageIn study · proposed 2025-12310 MW[7]
Cole Road 345 kVPJM AI2-171SolarIn study · proposed 2023-12310 MW[7]
Cole 345 kVPJM AF1-275SolarIn study · proposed 2022-12250 MW[7]
Pleasant Prairie SolarPJM AE2-214SolarIA signed · proposed 2026-12200 MW[7]
Hayden 345 kVPJM AH1-270SolarIn study · proposed 2023-1285 MW[7]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    Jun 8, 2022[2]
  3. Permitting
    —
  4. Construction start
    Oct 1, 2021[1]
  5. First operational
    Apr 1, 2024[1]
  6. Expected completion
    Jul 1, 2027[1]
    Projected
Planned capacity
464 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.

Buildings (planned)
5[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
4[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational78 MWApr 1, 2024[1]
Building 2operational78 MWMar 1, 2025[1]
Building 3operational104 MWOct 1, 2025[1]
Building 4operational104 MWMay 1, 2026[1]
Building 5under construction100 MWJul 1, 2027 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year
  • $242.1M[2]
    Auditor value · tax year current (2026) · parcel 510-180711
  • $33.6M[2]
    Auditor value — land · tax year current (2026) · parcel 510-180711
  • $208.4M[2]
    Auditor value — improvements · tax year current (2026) · parcel 510-180711
Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

ParcelRecord ownerAcresZoning / useBuilding sq ftSource
510-180711
Franklin County, OH
MAGELLAN ENTERPRISES LLC
Tax bills to: GOOGLE LLC
PO BOX 28190 SCOTTSDALE AZ 85255-0153
480.39data center1,172,656[2]
Site area
480.4 acres[2]Confirmed

Sum of county land area across parcels.

Land use
data center[2]Confirmed
Capital cost / investment
$11.5B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced
Nearby comparable transactions

Size

Floor area
1.17M sq ft[2]Confirmed

Building area in county assessment records.

Parcel / land records
510-180711 (Franklin County)[2]Confirmed

Compute

Chip types
TPU v5e, TPU v5p, TPU v6e, TPU v7[1]Confirmed
Compute (H100-equivalents)
332,000[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    65 MWApr 1, 2024[1]→130 MWMar 1, 2025[1]→216 MWOct 1, 2025[1]→303 MWMay 1, 2026[1]
  • Current facility power
    78 MWApr 1, 2024[1]→156 MWMar 1, 2025[1]→260 MWOct 1, 2025[1]→364 MWMay 1, 2026[1]
  • Buildings operational
    0Oct 1, 2021[1]→1Apr 1, 2024[1]→2Mar 1, 2025[1]→3Oct 1, 2025[1]→4May 1, 2026[1]
  • Status
    Under constructionOct 1, 2021[1]→Operating + expandingApr 1, 2024[1]

Timeline

Construction start: Oct 1, 2021[1]
First operational: Apr 1, 2024[1]
  1. Oct 1, 2021[1]

    Land clearing begins on the eastern half of the site, for Buildings 1-2

  2. Jul 1, 2023[1]

    Building 2 foundation work begins. Building 1 generators seem complete, cooling towers still under construction.

  3. Apr 1, 202478 MW facility power· 1 buildings operational[1]

    Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.

  4. Mar 1, 2025156 MW facility power· 2 buildings operational[1]

    Building 2 operational. Parking complete, no more visible construction.

  5. Oct 1, 2025260 MW facility power· 3 buildings operational[1]

    Building 3 operational. Surrounding roads finished, no more visible construction.

  6. Feb 21, 2026260 MW facility power· 3 buildings operational[1]

    Buildings 1-3 are visibly operational, with steam coming out of the cooling towers. Meanwhile Building 4 is extremely close to completion, with all backup generators complete with only 3 cooling towers missing their fans. ~1/2 the generators are installed for Building 5, and the roof is mostly complete (starting to install the final white layer, with the actual roof structure already complete).

  7. May 1, 2026364 MW facility power· 4 buildings operational[1]

    Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.

  8. Aug 5, 2026364 MW facility power· 4 buildings operational[1]

    Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.

  9. Jul 1, 2027Projected464 MW facility power· 5 buildings operational[1]

    Building 5 operational. The transmission line construction notice that expands site by 100 MW is assumed to be entirely for Building 5, and has an in-service date of July 1, 2027 (page 3). Estimate taken on the safe side based on completion times for Building 3-4 from when roof was complete.

  10. Jun 8, 2022[2]

    Deed/transfer recorded for parcel 510-180711 (no sale price disclosed).

Buildings on this campus

2

All claims (provenance audit)

62
FieldValueSourceConfidenceAs ofStatus
NameGoogle Columbus[1] Likely2026-08-05Shown
StatusUnder construction[1] derivedLikely2021-10-01Superseded / alternative
StatusUnder construction[1] derivedLikely2023-07-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2024-04-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-03-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-10-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-02-21Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-05-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-08-05Shown
Facility typeAI campus[1] derivedLikely2026-08-05Shown
Address5076 S High St, Columbus, OH 43207[1] Likely2026-08-05Shown
Property owner of recordMagellan Enterprises LLCParcel 510-180711: MAGELLAN ENTERPRISES LLC (tax mailing name: GOOGLE LLC)[2] Confirmed2026-09-27Shown
OwnerGoogleOwner: Google[1] Confirmed2026-08-05Shown
End usersGoogle DeepMindUsers: Google DeepMind[1] Speculative2026-08-05Shown
UtilityAmerican Electric Powerterritory 14006: OHIO POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POWER CO)[3] derivedLikely2022Shown
Current facility power364 MW[1] estimatedLikely2026-08-05Shown
Current facility power78 MW[1] estimatedLikely2024-04-01Superseded / alternative
Current facility power156 MW[1] estimatedLikely2025-03-01Superseded / alternative
Current facility power260 MW[1] estimatedLikely2025-10-01Superseded / alternative
Current facility power260 MW[1] estimatedLikely2026-02-21Superseded / alternative
Current facility power364 MW[1] estimatedLikely2026-05-01Superseded / alternative
Current IT capacity303 MW[1] estimatedLikely2026-08-05Shown
Current IT capacity65 MW[1] estimatedLikely2024-04-01Superseded / alternative
Current IT capacity130 MW[1] estimatedLikely2025-03-01Superseded / alternative
Current IT capacity216 MW[1] estimatedLikely2025-10-01Superseded / alternative
Current IT capacity216 MW[1] estimatedLikely2026-02-21Superseded / alternative
Current IT capacity303 MW[1] estimatedLikely2026-05-01Superseded / alternative
Planned capacity464 MW[1] estimatedLikely2026-08-05Shown
Estimated annual consumption2,232 GWh/yr[4] estimatedSpeculative2026-09-29Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[5] derivedLikely—Shown
Balancing authorityPJM[3] derivedLikely—Shown
Nearest mapped substationUnnamed substation (138 kV)way/1525005865[6] derivedLikely2026-09-28Shown
Distance to substation0.3 km[6] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[6] derivedLikely2026-09-28Shown
Generation queued in county1.66 GW[7] derivedConfirmed2026-09-27Shown
State avg. industrial price10.95¢/kWh[8] Confirmed2026-07Shown
State avg. commercial price14.06¢/kWh[8] Confirmed2026-07Shown
Generation within 50 km1.98 GW[9] derivedConfirmed202502Shown
Buildings (planned)5[1] derivedLikely2026-08-05Shown
Buildings operational4[1] estimatedLikely2026-08-05Shown
Buildings operational0[1] estimatedLikely2021-10-01Superseded / alternative
Buildings operational0[1] estimatedLikely2023-07-01Superseded / alternative
Buildings operational1[1] estimatedLikely2024-04-01Superseded / alternative
Buildings operational2[1] estimatedLikely2025-03-01Superseded / alternative
Buildings operational3[1] estimatedLikely2025-10-01Superseded / alternative
Buildings operational3[1] estimatedLikely2026-02-21Superseded / alternative
Buildings operational4[1] estimatedLikely2026-05-01Superseded / alternative
Floor area1.17M sq ft[2] Confirmed2026-09-27Shown
Site area480.4 acres[2] Confirmed2026-09-27Shown
Capital cost / investment$11.5B[1] estimatedLikely2026-08-05Shown
Parcel / land records510-180711 (Franklin County)[2] Confirmed2026-09-27Shown
Assessed value (official)$242.1M[2] Confirmed2026Shown
Land usedata center[2] Confirmed2026-09-27Shown
Compute (H100-equivalents)332,000[1] estimatedLikely2026-08-05Shown
Chip typesTPU v5e[1] Confirmed2026-08-05Shown
Chip typesTPU v5p[1] Confirmed2026-08-05Shown
Chip typesTPU v6e[1] Confirmed2026-08-05Shown
Chip typesTPU v7[1] Confirmed2026-08-05Shown
Land acquiredJun 8, 2022[2] derivedConfirmed2026-09-27Shown
Construction startOct 1, 2021[1] derivedLikely2026-08-05Shown
First operationalApr 1, 2024[1] derivedLikely2026-08-05Shown
Expected completionJul 1, 2027[1] estimatedSpeculative2026-08-05Shown