Google Columbus
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationApr 1, 2024
Satellite imagery
- Apr 1, 2024 · Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building [1]
- Mar 1, 2025 · Building 2 operational. Parking complete, no more visible construction.[1]
- Oct 1, 2025 · Building 3 operational. Surrounding roads finished, no more visible construction.[1]
- May 1, 2026 · Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost co[1]
- OperationalApr 1, 2024
Satellite imagery · Government record
- Apr 1, 2024 · Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building [1]
- Mar 1, 2025 · Building 2 operational. Parking complete, no more visible construction.[1]
- Oct 1, 2025 · Building 3 operational. Surrounding roads finished, no more visible construction.[1]
- May 1, 2026 · Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost co[1]
- Sep 27, 2026 · County land use: data center[2]
- Sep 27, 2026 · County records a 1,172,656 sq ft building[2]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Columbus
- →substationSatellite imageryLikely5 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.34 km away
- →transmission345 kV line[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.62 km away). Not confirmed as the supply path.
- →utilityAmerican Electric Power[3]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 39.84940, -82.99757
- Address
- County
- Franklin County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- End user
- Utility
Location falls inside this utility's retail service territory.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.
- Estimated annual consumption
364 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
15 EIA-reported plants within 50 km.
- Generation queued in county
8 active generation interconnection requests in Franklin County: Solar 845 MW, Storage 810 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.52 km | 138 kV | [6] |
| Cyprus 138kV Extension · American Electric Power | Transmission line | 0.9 km | 138 kV | [6] |
| 345 kV line · American Electric Power | Transmission line | 1.62 km | 345 kV | [6] |
| Darby Power, LLC · Darby Power, LLC | Power plant (Natural Gas) | 21.5 km | 480 MW | [9] |
| Big Plain Solar, LLC · Leeward Asset Management, LLC | Power plant (Solar) | 28.3 km | 196 MW | [9] |
| Fox Squirrel Solar · EDF Renewable Asset Holdings, Inc. | Power plant (Solar) | 32.6 km | 577 MW | [9] |
| O'Shaughnessy Hydro · City of Columbus - (OH) | Power plant (Hydroelectric) | 35.5 km | 5 MW | [9] |
| Atlanta Farms Solar · Dominion Renewable Energy | Power plant (Solar) | 35.6 km | 200 MW | [9] |
| Yellowbud Solar, LLC · Yellowbud Solar LLC | Power plant (Solar) | 39 km | 274 MW | [9] |
| Salt City Solar Project - Hybrid · Salt City Solar LLC | Power plant (Solar) | 48.4 km | 50 MW | [9] |
| Madison Fields Solar Project, LLC · Madison Fields Solar Project, LLC | Power plant (Solar) | 48.7 km | 180 MW | [9] |
| Unnamed substation | Substation | 0.34 km | 138 kV | [6] |
| Unnamed substation | Substation | 0.52 km | 138 kV | [6] |
| Unnamed substation | Substation | 0.55 km | 138 kV | [6] |
| Cyprus Switching Station · AEP Ohio | Substation | 0.91 km | 138 kV | [6] |
| Parsons Substation · AEP Ohio | Substation | 1.24 km | 138 kV | [6] |
| Unnamed substation | Substation | 2.64 km | 69 kV | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Beatty 345 kVPJM AG2-376 | Storage | In study · proposed 2024-11 | 400 MW | [7] |
| Cole 345 kVPJM AH1-318 | Storage | In study · proposed 2025-12 | 310 MW | [7] |
| Cole Road 345 kVPJM AI2-171 | Solar | In study · proposed 2023-12 | 310 MW | [7] |
| Cole 345 kVPJM AF1-275 | Solar | In study · proposed 2022-12 | 250 MW | [7] |
| Pleasant Prairie SolarPJM AE2-214 | Solar | IA signed · proposed 2026-12 | 200 MW | [7] |
| Hayden 345 kVPJM AH1-270 | Solar | In study · proposed 2023-12 | 85 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquiredJun 8, 2022[2]
- Permitting—
- Construction startOct 1, 2021[1]
- First operationalApr 1, 2024[1]
- Expected completionJul 1, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 510-180711 Franklin County, OH | MAGELLAN ENTERPRISES LLC Tax bills to: GOOGLE LLC PO BOX 28190 SCOTTSDALE AZ 85255-0153 | 480.39 | data center | 1,172,656 | [2] |
- Site area
Sum of county land area across parcels.
- Land use
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
- Amazon Web Services · 26.9 km · parcel 050-011455$226,596 · Oct 18, 2022 [2]
- DartPoints Dublin · 29.5 km · parcel 273-001702$15.3M · Oct 29, 2020 [2]
- Google NBY-4 · 30.3 km · parcel 222-004984$27.4M · Dec 13, 2018 [2]
- TJX Corporate Techno · 32.5 km · parcel 222-004441$2.1M · Jul 23, 2010 [2]
- Compugen New Albany · 32.5 km · parcel 222-004644$2.2M · Oct 1, 2014 [2]
- Compugen New Albany · 32.8 km · parcel 222-001940$6.8M · Feb 6, 2023 [2]
Size
Compute
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity
- Current facility power
- Buildings operational
- Status
Timeline
- Oct 1, 2021[1]
Land clearing begins on the eastern half of the site, for Buildings 1-2
- Jul 1, 2023[1]
Building 2 foundation work begins. Building 1 generators seem complete, cooling towers still under construction.
Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.
Building 2 operational. Parking complete, no more visible construction.
Building 3 operational. Surrounding roads finished, no more visible construction.
Buildings 1-3 are visibly operational, with steam coming out of the cooling towers. Meanwhile Building 4 is extremely close to completion, with all backup generators complete with only 3 cooling towers missing their fans. ~1/2 the generators are installed for Building 5, and the roof is mostly complete (starting to install the final white layer, with the actual roof structure already complete).
Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.
Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.
Building 5 operational. The transmission line construction notice that expands site by 100 MW is assumed to be entirely for Building 5, and has an in-service date of July 1, 2027 (page 3). Estimate taken on the safe side based on completion times for Building 3-4 from when roof was complete.
- Jun 8, 2022[2]
Deed/transfer recorded for parcel 510-180711 (no sale price disclosed).
Buildings on this campus
2- GoogleOperating · 290,200 sq ft footprint
- Google Lockbourne, OHOperating
All claims (provenance audit)
62| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Columbus | [1] | Likely | 2026-08-05 | Shown |
| Status | Under construction | [1] derived | Likely | 2021-10-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2023-07-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-04-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-03-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-21 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-08-05 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-08-05 | Shown |
| Address | 5076 S High St, Columbus, OH 43207 | [1] | Likely | 2026-08-05 | Shown |
| Property owner of record | Magellan Enterprises LLCParcel 510-180711: MAGELLAN ENTERPRISES LLC (tax mailing name: GOOGLE LLC) | [2] | Confirmed | 2026-09-27 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-08-05 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Speculative | 2026-08-05 | Shown |
| Utility | American Electric Powerterritory 14006: OHIO POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POWER CO) | [3] derived | Likely | 2022 | Shown |
| Current facility power | 364 MW | [1] estimated | Likely | 2026-08-05 | Shown |
| Current facility power | 78 MW | [1] estimated | Likely | 2024-04-01 | Superseded / alternative |
| Current facility power | 156 MW | [1] estimated | Likely | 2025-03-01 | Superseded / alternative |
| Current facility power | 260 MW | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Current facility power | 260 MW | [1] estimated | Likely | 2026-02-21 | Superseded / alternative |
| Current facility power | 364 MW | [1] estimated | Likely | 2026-05-01 | Superseded / alternative |
| Current IT capacity | 303 MW | [1] estimated | Likely | 2026-08-05 | Shown |
| Current IT capacity | 65 MW | [1] estimated | Likely | 2024-04-01 | Superseded / alternative |
| Current IT capacity | 130 MW | [1] estimated | Likely | 2025-03-01 | Superseded / alternative |
| Current IT capacity | 216 MW | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Current IT capacity | 216 MW | [1] estimated | Likely | 2026-02-21 | Superseded / alternative |
| Current IT capacity | 303 MW | [1] estimated | Likely | 2026-05-01 | Superseded / alternative |
| Planned capacity | 464 MW | [1] estimated | Likely | 2026-08-05 | Shown |
| Estimated annual consumption | 2,232 GWh/yr | [4] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [5] derived | Likely | — | Shown |
| Balancing authority | PJM | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1525005865 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.66 GW | [7] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.98 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 5 | [1] derived | Likely | 2026-08-05 | Shown |
| Buildings operational | 4 | [1] estimated | Likely | 2026-08-05 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2021-10-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2023-07-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-04-01 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-03-01 | Superseded / alternative |
| Buildings operational | 3 | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Buildings operational | 3 | [1] estimated | Likely | 2026-02-21 | Superseded / alternative |
| Buildings operational | 4 | [1] estimated | Likely | 2026-05-01 | Superseded / alternative |
| Floor area | 1.17M sq ft | [2] | Confirmed | 2026-09-27 | Shown |
| Site area | 480.4 acres | [2] | Confirmed | 2026-09-27 | Shown |
| Capital cost / investment | $11.5B | [1] estimated | Likely | 2026-08-05 | Shown |
| Parcel / land records | 510-180711 (Franklin County) | [2] | Confirmed | 2026-09-27 | Shown |
| Assessed value (official) | $242.1M | [2] | Confirmed | 2026 | Shown |
| Land use | data center | [2] | Confirmed | 2026-09-27 | Shown |
| Compute (H100-equivalents) | 332,000 | [1] estimated | Likely | 2026-08-05 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-08-05 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-08-05 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-08-05 | Shown |
| Chip types | TPU v7 | [1] | Confirmed | 2026-08-05 | Shown |
| Land acquired | Jun 8, 2022 | [2] derived | Confirmed | 2026-09-27 | Shown |
| Construction start | Oct 1, 2021 | [1] derived | Likely | 2026-08-05 | Shown |
| First operational | Apr 1, 2024 | [1] derived | Likely | 2026-08-05 | Shown |
| Expected completion | Jul 1, 2027 | [1] estimated | Speculative | 2026-08-05 | Shown |