Data centers in Franklin County, Ohio
Datacenter Source tracks 33 data centers in Franklin County, Ohio. Facilities that disclose power add up to 364 MW online and 100 MW in the pipeline — floors, since 6% report a figure.
Follow
Get changes to Franklin County, Ohio
Or subscribe in a feed reader: RSS / Atom
Facilities
- Google Columbus AI campus · ColumbusOperating + expanding364 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.+100 MW pipeline EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Amazon AWS: Hilliard Data Center HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Amazon Web Services HyperscaleOperating
- Compugen New Albany UnclassifiedOperating
- Compugen New Albany UnclassifiedOperating
- DartPoints Dublin Unclassified · 43017Operating
- Google HyperscaleOperating
- Google Lockbourne, OH HyperscaleOperating
- Google NBY-4 HyperscaleOperating
- Google NBY-5 HyperscaleOperating
- Oppidan data center UnclassifiedOperating
- STACK New Albany UnclassifiedOperating
- TJX Corporate Techno UnclassifiedOperating
- Unnamed data center UnclassifiedOperating
- Unnamed data center UnclassifiedOperating
- Unnamed data center UnclassifiedOperating
- Unnamed data center UnclassifiedOperating
Interconnection-queue requests filed here (last two years)
Requests to connect generation or large loads, as the ISO/RTO publishes them. Filing is an application, not a commitment to build.
No dated queue filings for this county in the files we ingest (some ISOs don't publish a county or filing date).
Local impact
Water, on-site generation and air permits, incentives, regulatory events and large-load tariffs, where a source documents them. Counts are of sourced records, not of the state's totals.
Evaporative (cooling towers): 1 site EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Not yet collected
- American Electric Power: AEP Ohio data center tariff ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Public Utilities Commission of Ohio · Docket 24-508-EL-ATA · Jul 9, 2025 · source
Not yet collected
Recent changes
- May 1, 2026 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current IT capacity: 216 MW → 303 MW
- May 1, 2026 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current facility power: 260 MW → 364 MW
- May 1, 2026 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 3 → 4
- May 1, 2026 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. New capacity online: Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.
- Dec 2, 2025 · STACK New Albany ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. Land acquired: Deed/transfer recorded for parcel 222-004355 (no sale price disclosed).
- Oct 1, 2025 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current IT capacity: 130 MW → 216 MW
- Oct 1, 2025 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current facility power: 156 MW → 260 MW
- Oct 1, 2025 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 2 → 3
- Oct 1, 2025 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. New capacity online: Building 3 operational. Surrounding roads finished, no more visible construction.
- Mar 1, 2025 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current IT capacity: 65 MW → 130 MW
- Mar 1, 2025 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current facility power: 78 MW → 156 MW
- Mar 1, 2025 · Google Columbus EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 1 → 2