POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityGoogle
- →substationUnnamed substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.18 km away. Proximity does not establish that it serves the site.
- →transmission138 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.27 km away). Not confirmed as the supply path.
- →utilitySouth Central Power Company[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 39.72427, -82.68792
- County
- Fairfield County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
11 EIA-reported plants within 50 km.
- Generation queued in county
7 active generation interconnection requests in Fairfield County: Solar 918 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.27 km | 138 kV | [1] |
| 69 kV line | Transmission line | 1.99 km | 69 kV | [1] |
| Renick Run Pumping Station 03-04 · City of Columbus - (OH) | Power plant (Petroleum) | 35.9 km | 2 MW | [6] |
| Ps St-8 Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 40.6 km | 2 MW | [6] |
| Yellowbud Solar, LLC · Yellowbud Solar LLC | Power plant (Solar) | 40.7 km | 274 MW | [6] |
| Denison Solar Array · AEP Onsite Partners, LLC | Power plant (Solar) | 41.4 km | 2 MW | [6] |
| Salt City Solar Project - Hybrid · Salt City Solar LLC | Power plant (Solar) | 41.7 km | 50 MW | [6] |
| Darby Power, LLC · Darby Power, LLC | Power plant (Natural Gas) | 41.9 km | 480 MW | [6] |
| Suburban Landfill Gas Recovery · WM Renewable Energy LLC | Power plant (Biomass) | 43.2 km | 6 MW | [6] |
| Atlanta Farms Solar · Dominion Renewable Energy | Power plant (Solar) | 45.6 km | 200 MW | [6] |
| Unnamed substation | Substation | 0.18 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.38 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.46 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.89 km | 69 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Muskingum-W. Millersport 345 kVPJM AE2-048 | Solar | IA signed · proposed 2022-06 | 220 MW | [4] |
| Harrison-Good Hope 138 kVPJM AG1-351 | Solar | In study · proposed 2023-12 | 142 MW | [4] |
| West Millersport 138 kVPJM AH1-032 | Solar | In study · proposed 2023-12 | 138 MW | [4] |
| West Millersport 138 kVPJM AG2-003 | Solar | In study · proposed 2023-12 | 120 MW | [4] |
| Muskingum River-W. Millersport 345 kVPJM AE2-136 | Solar | In study · proposed 2022-06 | 114 MW | [4] |
| West Millersport 138 kVPJM AG1-163 | Solar | In study · proposed 2023-12 | 100 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
Other buildings on this campus
2- Google LancasterOperating
- GoogleOperating · 289,600 sq ft footprint
All claims (provenance audit)
15| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Googleway/1501120016 name=Google | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-09-27 | Shown |
| Operator | Googleoperator=Google | [1] | Likely | 2026-09-27 | Shown |
| Utility | South Central Power Companyterritory 18085: SOUTH CENTRAL POWER COMPANY (COOPERATIVE, SOUTH CENTRAL POWER C | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1245829346 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 918 MW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.02 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 292,100 sq ft | [1] derived | Likely | 2026-09-27 | Shown |