Google Lincoln
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — SPP does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationMay 12, 2026
Satellite imagery
- May 12, 2026 · Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started[1]
- OperationalMay 12, 2026
Satellite imagery
- May 12, 2026 · Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Lincoln
- →substationOn-site substation[1]Satellite imageryLikely2 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityLincoln Electric System[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 40.90541, -96.65396
- Address
- County
- Lancaster County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Norris Public Power District.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-10-01); not necessarily full build-out.
- Estimated annual consumption
170 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Nebraska statewide average, July 2026.
- State avg. commercial price
Nebraska statewide average, July 2026.
- Generation within 50 km
15 EIA-reported plants within 50 km.
- Generation queued in county
17 active generation interconnection requests in Lancaster County: Gas 1,096 MW, Other 695 MW, Solar 642 MW, Wind 428 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Terry Bundy Generating Station · Lincoln Electric System | Power plant (Natural Gas) | 3.5 km | 171 MW | [7] |
| Archer Daniels Midland Lincoln · Archer Daniels Midland Co | Power plant (Natural Gas) | 5.5 km | 8 MW | [7] |
| J Street · Lincoln Electric System | Power plant (Natural Gas) | 11.8 km | 30 MW | [7] |
| Rokeby · Lincoln Electric System | Power plant (Natural Gas) | 20.5 km | 259 MW | [7] |
| Wahoo · City of Wahoo - (NE) | Power plant (Natural Gas) | 34.3 km | 14 MW | [7] |
| Platteview Solar LLC · AES Distributed Energy | Power plant (Solar) | 39.2 km | 81 MW | [7] |
| Sheldon · Nebraska Public Power District | Power plant (Coal) | 40.1 km | 216 MW | [7] |
| Hallam · Nebraska Public Power District | Power plant (Petroleum) | 40.1 km | 43 MW | [7] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| GEN-2024-021 at Olive Creek 345 kV SubstationSPP GEN-2024-021 | Gas | In study · proposed 2030-12 | 540 MW | [5] |
| GEN-2023-224 at Olive Creek 345 kV SubstationSPP GEN-2023-224 | Other | IA signed · proposed 2029-06 | 478 MW | [5] |
| GEN-2024-020 at Olive Creek 345 kV SubstationSPP GEN-2024-020 | Gas | In study · proposed 2030-12 | 390 MW | [5] |
| GEN-2017-181 at Tobias 345kV SubstationSPP GEN-2017-181 | Wind | IA signed · proposed 2028-07 | 300 MW | [5] |
| GEN-2021-043 at 8000 SW 12th (Rokeby) Station, 115kV BusSPP GEN-2021-043 | Storage | IA signed · proposed 2030-05 | 250 MW | [5] |
| GEN-2021-049 at Wagener 115kV SubstationSPP GEN-2021-049 | Solar | IA signed · proposed 2029-09 | 225 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startJul 1, 2023[1]
- First operationalMay 12, 2026[1]
- Expected completionOct 1, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-10-01); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Jul 1, 2023[1]
Land clearing begins for the site
- Oct 23, 2025[1]
Building 1 looks mostly complete: the large items like generators and substation are done. It is just missing 2 more cooling towers (4 fans). They just seem to be paving and setting up the secondary equipment so it is probably a few months away from operation. Building 2 foundation has been laid.
Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.
Building 2 operational. Estimated based on the construction timeline for Building 1, specifically the time to operational since the roof was complete and the time to operational since the foundation work began.
All claims (provenance audit)
29| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Lincoln | [1] | Likely | 2026-05-12 | Shown |
| Status | Under construction | [1] derived | Likely | 2023-07-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-10-23 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-12 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-12 | Shown |
| Address | 5475 Cloud Ct, Lincoln, NE 68514 | [1] | Likely | 2026-05-12 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-05-12 | Shown |
| Utility | Lincoln Electric Systemterritory 11018: LINCOLN ELECTRIC SYSTEM (MUNICIPAL, LINCOLN ELECTRIC SYSTEM) | [2] derived | Unverified | 2022 | Shown |
| Current facility power | 170 MW | [1] estimated | Likely | 2026-05-12 | Shown |
| Current IT capacity | 141 MW | [1] estimated | Likely | 2026-05-12 | Shown |
| Planned capacity | 339 MW | [1] estimated | Likely | 2026-05-12 | Shown |
| Estimated annual consumption | 1,042 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | SPPSOUTHWEST POWER POOL | [4] derived | Likely | — | Shown |
| Balancing authority | SWPP | [2] derived | Likely | — | Shown |
| Generation queued in county | 3.27 GW | [5] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.00¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 9.39¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 839 MW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-05-12 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-05-12 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2023-07-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-10-23 | Superseded / alternative |
| Capital cost / investment | $5.3B | [1] estimated | Likely | 2026-05-12 | Shown |
| Compute (H100-equivalents) | 197,600 | [1] estimated | Likely | 2026-05-12 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-05-12 | Shown |
| Chip types | TPU v7 | [1] | Confirmed | 2026-05-12 | Shown |
| Construction start | Jul 1, 2023 | [1] derived | Likely | 2026-05-12 | Shown |
| First operational | May 12, 2026 | [1] derived | Likely | 2026-05-12 | Shown |
| Expected completion | Oct 1, 2027 | [1] estimated | Speculative | 2026-05-12 | Shown |