Google Michigan City
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No grid, construction or operating record yet backs the 300 MW announced.
- ⚠ No public interconnection record for this load — MISO does not publish large-load requests.
- ⚠ No recorded land acquisition found.
How the time-to-power window was estimated
- Current stage: Announced (furthest stage with documented evidence)[1]
- No public grid record: No interconnection request or utility contract found; adds uncertainty to the upper bound.
- Required: 300 MW
- From “Announced”, large loads have typically taken 2–5 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- AnnouncedSep 11, 2026
Utility filing / announcement
- Sep 11, 2026 · Planned capacity reported: 300 MW[1]
- Land acquired
- Planning / zoning
- Permitting
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under construction
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Utility filing / announcement.
Grid path
- →facilityGoogle Michigan City
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
County-level (approximate)Location is approximate (county-level (approximate)); the marker does not identify the exact site.
- Coordinates
- 41.54409, -86.73972
- County
- LaPorte County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Planned capacity
“Google / Data Center Michigan City, IN ▪ 300 MW data center project”
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Indiana statewide average, July 2026.
- State avg. commercial price
Indiana statewide average, July 2026.
- Generation within 50 km
23 EIA-reported plants within 50 km.
- Generation queued in county
11 active generation interconnection requests in LaPorte County: Solar 674 MW, Storage 635 MW, Solar + storage 535 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Michigan City · Northern Indiana Pub Serv Co | Power plant (Coal) | 24.1 km | 455 MW | [6] |
| St Joseph Energy Center · St Joseph Energy Center LLC | Power plant (Natural Gas) | 27.6 km | 715 MW | [6] |
| Arcelormittal Burns Harbor · Cleveland-Cliffs Burns Harbor LLC | Power plant (Other) | 34.7 km | 175 MW | [6] |
| Mammoth North Solar · Mammoth North, LLC | Power plant (Solar) | 39.3 km | 400 MW | [6] |
| Dunns Bridge II Solar · Dunns Bridge II Solar and Storage Generation LLC | Power plant (Solar) | 39.7 km | 491 MW | [6] |
| R M Schahfer · Northern Indiana Pub Serv Co | Power plant (Coal) | 43.6 km | 877 MW | [6] |
| Dunns Bridge I Solar · Dunns Bridge Solar Center LLC | Power plant (Solar) | 47 km | 265 MW | [6] |
| Gary Works · United States Steel-Gary | Power plant (Natural Gas) | 49.8 km | 161 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Olive-University Park 345 kVPJM AG1-447 - moved to TC1 | Storage | In study · proposed 2023-12 | 305 MW | [4] |
| Olive-University Park 345 kVPJM AG1-436 - moved to TC1 | Solar | In study · proposed 2023-12 | 250 MW | [4] |
| Reynolds - Olive 345 kVPJM AH2-419 | Solar + storage | In study · proposed 2026-12 | 210 MW | [4] |
| New Carlisle - Bosserman 138 kVPJM AI1-078 | Solar + storage | In study · proposed 2026-12 | 200 MW | [4] |
| J1355 at Stillwell 138kV SubtationMISO J1355 | Storage | IA signed · proposed 2023-05 | 160 MW | [7] |
| J1724 at LNG - STILLWELL 138kV lineMISO J1724 | Solar | IA signed · proposed 2023-09 | 150 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
- Planned capacity
“Google / Data Center Michigan City, IN ▪ 300 MW data center project”
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
9| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Operator | [1] | Confirmed | 2026-09-11 | Shown | |
| Utility | NIPSCO | [1] | Confirmed | 2026-09-11 | Shown |
| Planned capacity | 300 MW | [1] | Likely | 2026-09-11 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [2] derived | Likely | — | Shown |
| Balancing authority | MISO | [3] derived | Likely | — | Shown |
| Generation queued in county | 1.84 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.16¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.30¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.82 GW | [6] derived | Confirmed | 202502 | Shown |