Northern Indiana (New Carlisle)

Market boundary: facilities within 50 km of the metro center (editorial definition).

Facilities
5
3 campuses
Power online
1.09 GW
1 sites reporting
Under construction
0 MW
planned MW at active sites
Planned
—
0 planned sites (MW not disclosed)
AI campuses
1
1.09 GW online · 0 MW pipeline
AI compute
0.69M
H100-equivalents (est.)
Capital (reported + est.)
$11B

Totals only include facilities with a reported or estimated figure; most sites don't disclose power, so these are floors, not market size estimates. Online = operating sites; pipeline = remaining planned MW at sites under construction or planned.

Construction pipeline by expected completion

MW from phases with a projected completion date

2026
2028

Power reality

Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.

  • Announced3.04 GW
  • Interconnection requests—
  • Contracted / approved—
  • Under construction1.22 GW
  • Operational1.09 GW

838 MW announced at 2 sites has no grid, construction or operating record yet.

Pending MW by time to power

Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.

Largest gaps: announced vs documented
Verified operating: 1Announced only: 2Unverified: 2

Interconnection queues

Active requests to connect to the grid (MISO, PJM). Requests are applications, not commitments — most never get built.

Generation seeking interconnection6.36 GW · 37 requests
Solar 2.9 GWSolar + storage 1.34 GWStorage 1.33 GWGas 786 MW

Largest operators & owners

Online + pipeline MW at linked facilities

Online Under construction + planned

Largest customers & end users

Tenants and workload owners, where sourced

Online Under construction + planned

Utility exposure

Most likely retail utility by location (approximate)

Online Under construction + planned

Grid operators (ISO / RTO)

By facility location

Online Under construction + planned
  • PJM1.09 GW + 0 MW · 3 sites
  • MISO— · 2 sites

Largest facilities

By online + pipeline MW

FacilityStatusOnlinePipeline
Anthropic-Amazon New CarlisleOperating1.09 GW—

Facilities by status

  • Operating3
  • Unknown2

Campuses & sites (4)

Campus pages list their buildings