POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityGoogle NBY-6
- →substationUnnamed substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.17 km away. Proximity does not establish that it serves the site.
- →transmission138 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.18 km away). Not confirmed as the supply path.
- →utilityAmerican Electric Power[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 40.05411, -82.76797
- County
- Licking County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Licking Rural Electric INC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
9 EIA-reported plants within 50 km.
- Generation queued in county
14 active generation interconnection requests in Licking County: Solar 1,773 MW, Storage 750 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.18 km | 138 kV | [1] |
| Denison Solar Array · AEP Onsite Partners, LLC | Power plant (Solar) | 21.4 km | 2 MW | [6] |
| Dodge Park Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 23.8 km | 2 MW | [6] |
| St-1/1a Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 24.1 km | 1 MW | [6] |
| Renick Run Pumping Station 03-04 · City of Columbus - (OH) | Power plant (Petroleum) | 25 km | 2 MW | [6] |
| Ps St-8 Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 26.1 km | 2 MW | [6] |
| O'Shaughnessy Hydro · City of Columbus - (OH) | Power plant (Hydroelectric) | 32.4 km | 5 MW | [6] |
| Suburban Landfill Gas Recovery · WM Renewable Energy LLC | Power plant (Biomass) | 47.3 km | 6 MW | [6] |
| Igs Cmh4, LLC · Greenbacker Renewable Energy Corporation | Power plant (Solar) | 48.4 km | 4 MW | [6] |
| Unnamed substation | Substation | 0.17 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.29 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.29 km | 138 kV | [1] |
| Google substation · Google | Substation | 0.63 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.74 km | 138 kV | [1] |
| QTS NAL-2 Substation · Quality Technology Services | Substation | 0.99 km | 138 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Centerburg 138 kVPJM AI2-088 | Solar | In study · proposed 2025-12 | 413 MW | [4] |
| Centerburg 138 kVPJM AG1-034 | Solar | In study · proposed 2023-10 | 363 MW | [4] |
| Centerburg 138 kVPJM AH1-036 | Storage | In study · proposed 2024-07 | 278 MW | [4] |
| Centerburg 138 kVPJM AG1-024 | Solar | In study · proposed 2023-10 | 235 MW | [4] |
| Flint GridPJM AF1-062 | Storage | IA signed · proposed 2026-11 | 200 MW | [4] |
| Jug Street 138 kVPJM AI2-226 | Storage | In study · proposed 2022-08 | 200 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
- $303.5M[7]Comparable-assessment model · Sep 29, 2026$1054/sq ft × 287,919 sq ft (n=32 comps)
- Annual property tax
- Not yet sourced
- NAO 1/NAO 2 · 2.2 km · parcel 094-107100-00.001$36.4M · Aug 10, 2017 [8]
- LCO 1 · 2.5 km · parcel 094-106782-00.000$34.3M · May 23, 2019 [8]
- Amazon Web Services CMH50 · 4.7 km · parcel 095-111744-00.000$12.8M · Jul 23, 2015 [8]
Size
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
Other buildings on this campus
7- Google New AlbanyOperating · 95,300 sq ft footprint
- Google NBY-1Operating · 141,500 sq ft footprint
- Google NBY-2Operating · 142,400 sq ft footprint
- Google NBY-3Operating · 288,700 sq ft footprint
- Google NBY-4Operating · 287,100 sq ft footprint
- Google NBY-5Operating · 287,300 sq ft footprint
- Google NBY-7Operating · 270,700 sq ft footprint
All claims (provenance audit)
18| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google NBY-6way/1386016633 name=Google NBY-6 | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-09-27 | Shown |
| Operator | Googleoperator=Google | [1] | Likely | 2026-09-27 | Shown |
| Utility | American Electric Powerterritory 14006: OHIO POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POWER CO) | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1428404272 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 2.52 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 25 MW | [6] derived | Confirmed | 202502 | Shown |
| Floor area | 287,900 sq ft | [1] estimated | Unverified | 2026-09-27 | Shown |
| Building footprint | 287,900 sq ft | [1] derived | Likely | 2026-09-27 | Shown |
| Floors | 1building:levels=1 | [1] | Likely | 2026-09-27 | Shown |
| Model estimate of property value | $303.5M | [7] estimated | Speculative | 2026-09-29 | Shown |