DC
/

Meta-QTS Hillsboro 2

OperatingAI campusCampusHillsboro, Washington County, Oregon
70% profile completeness
42 claims from 9 sources
Current facility power
243 MW[1]
Likelyestimated
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
$6.8B[1]
Likelyestimated
First operational
Aug 2, 2023[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Portland General Electric · None (non-RTO region)
Substation: On-site substation (likely Shute Substation)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
243 MW[1]
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionApr 1, 2021
    Model estimate · Satellite imagery
    • Apr 1, 2021 · Reported status: under construction[1]
    • Apr 1, 2021 · Construction start[1]
    • Apr 1, 2021 · First signs of site land clearing appear on satellite imagery.[1]
    • Aug 2, 2023 · Reported status: expanding[1]
  3. EnergizationAug 2, 2023
    Satellite imagery
    • Aug 2, 2023 · Satellite imagery shows Building 2 and 3 cooling nearing completion and Building 4 cooling install continues. We believe Building 1 is operational now due to the lack of constructi[1]
    • Nov 8, 2024 · We believe Buildings 2, 3, and 4 are operational due to the absence of construction vehicles and completed parking lots/concrete around the facilities. There is also a vehicle pres[1]
  4. OperationalAug 2, 2023
    Satellite imagery
    • Aug 2, 2023 · Satellite imagery shows Building 2 and 3 cooling nearing completion and Building 4 cooling install continues. We believe Building 1 is operational now due to the lack of constructi[1]
    • Nov 8, 2024 · We believe Buildings 2, 3, and 4 are operational due to the absence of construction vehicles and completed parking lots/concrete around the facilities. There is also a vehicle pres[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Meta-QTS Hillsboro 2
  2. substation
    On-site substation (likely Shute Substation)[1][5]
    Satellite imageryLikely
    2 substation outlines traced inside the campus on satellite imagery; OSM maps Shute Substation 0.45 km away
  3. transmission
    Keeler-Allston No 1 (500 kV)[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (1.33 km away). Not confirmed as the supply path.
  4. utility
    Portland General Electric[1]
    DocumentedConfirmed
    Named in a source
  5. ISO / RTO
    None (non-RTO region)[3]
    Service territoryLikely
    Balancing authority: PGE
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

  • Constable Bess (Batteries, 75 MW) is 0.9 km away[7]
    EIA plant within 1.5 km; proximity does not establish that it supplies the facility
    Battery storageCo-located75 MWUnverified

Location & imagery

Mapped outline
Coordinates
45.55894, -122.93255
Address
4755 NE Huffman St, Hillsboro, OR 97124[1]Likely
County
Washington County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Meta[1]Likely
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Meta[1]Likely
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Meta[1]Likely
End user
Meta[1]Likely
Energy partner
Avangrid[1]Confirmed

Power (all fields)

Current facility power
243 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
180 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
1,490 GWh/yr[2]Speculativeestimated

243 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[3]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
PGE[4]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Shute Substation (115 kV)[5]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.5 km[5]Likelyderived
Highest-voltage line nearby
500 kV[5]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
8.92¢/kWh[6]Confirmed

Oregon statewide average, July 2026.

State avg. commercial price
10.60¢/kWh[6]Confirmed

Oregon statewide average, July 2026.

Generation within 50 km
598 MW[7]Confirmedderived

30 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
230 kV lineTransmission line0.14 km230 kV[5]
Keeler-Forest Grove No 1 · Bonneville Power AdministrationTransmission line0.18 km115 kV[5]
Keeler-Forest Grove No 2 · Bonneville Power AdministrationTransmission line0.2 km115 kV[5]
115 kV lineTransmission line0.25 km115 kV[5]
Keeler - SunsetTransmission line1.29 km230 kV[5]
Keeler-Allston No 1 · Bonneville Power AdministrationTransmission line1.33 km500 kV[5]
Constable Bess · Portland General Electric CoPower plant (Batteries)0.9 km75 MW[7]
Milfordsolar Or · Adapture Renewables, Inc.Power plant (Solar)9.2 km3 MW[7]
River Road Gen Plant · PUD No 1 of Clark County - (WA)Power plant (Natural Gas)19 km230 MW[7]
Coffee Creek Bess · Portland General Electric CoPower plant (Batteries)26.9 km17 MW[7]
Sullivan · Portland General Electric CoPower plant (Hydroelectric)33.4 km18 MW[7]
Sundial (Troutdale) Bess · Troutdale Grid, LLCPower plant (Batteries)39.9 km200 MW[7]
Sulussolar17 · Adapture Renewables, Inc.Power plant (Solar)45.4 km3 MW[7]
Ssd Clackamas 1, LLC · Thor Solar 1 CEI, LLCPower plant (Solar)49.2 km4 MW[7]
Shute Substation · Portland General ElectricSubstation0.45 km115 kV[5]
Evergreen Substation West · Portland General ElectricSubstation0.94 km230 kV[5]
Sunset Substation · Portland General ElectricSubstation1.38 km230 kV[5]
Unnamed substationSubstation1.45 km—[5]
West Union Substation · Portland General ElectricSubstation2.96 km—[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Apr 1, 2021[1]
  5. First operational
    Aug 2, 2023[1]
  6. Expected completion
    —
Buildings (planned)
4[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
4[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational61 MWAug 2, 2023[1]
Buildings 2–4operational182 MWNov 8, 2024[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$6.8B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
H100[1]Confirmed
Compute (H100-equivalents)
123,800[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    45 MWAug 2, 2023[1]→180 MWNov 8, 2024[1]
  • Current facility power
    61 MWAug 2, 2023[1]→243 MWNov 8, 2024[1]
  • Buildings operational
    1Aug 2, 2023[1]→4Nov 8, 2024[1]
  • Status
    Operating + expandingAug 2, 2023[1]→OperatingApr 17, 2026[1]

Timeline

Construction start: Apr 1, 2021[1]
First operational: Aug 2, 2023[1]
  1. Apr 1, 2021[1]

    First signs of site land clearing appear on satellite imagery.

  2. Apr 29, 2023[1]

    Satellite imagery shows Building 3 and 4 cooling start to go on.

  3. Aug 2, 202361 MW facility power· 1 buildings operational[1]

    Satellite imagery shows Building 2 and 3 cooling nearing completion and Building 4 cooling install continues. We believe Building 1 is operational now due to the lack of construction equipment on or immediately around the building.

  4. Nov 8, 2024243 MW facility power· 4 buildings operational[1]

    We believe Buildings 2, 3, and 4 are operational due to the absence of construction vehicles and completed parking lots/concrete around the facilities. There is also a vehicle presence in the parking lot similar to the level seen during normal operation at other data center campuses. Finally, it is more than 12 months after cooling has been installed or in the final stages of install for the remaining three buildings.

  5. Apr 14, 2025243 MW facility power· 4 buildings operational[1]

    All four buildings are operational

  6. Apr 17, 2026243 MW facility power· 4 buildings operational[1]

    All four buildings are operational.

Buildings on this campus

4

All claims (provenance audit)

42
FieldValueSourceConfidenceAs ofStatus
NameMeta-QTS Hillsboro 2[1] Likely2026-04-17Shown
StatusUnder construction[1] derivedLikely2021-04-01Superseded / alternative
StatusUnder construction[1] derivedLikely2023-04-29Superseded / alternative
StatusOperating + expanding[1] derivedLikely2023-08-02Superseded / alternative
StatusOperating + expanding[1] derivedLikely2024-11-08Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-04-14Superseded / alternative
StatusOperating[1] derivedLikely2026-04-17Shown
Facility typeAI campus[1] derivedLikely2026-04-17Shown
Address4755 NE Huffman St, Hillsboro, OR 97124[1] Likely2026-04-17Shown
OwnerMetaOwner: Meta[1] Likely2026-04-17Shown
End usersMetaUsers: Meta[1] Likely2026-04-17Shown
UtilityPortland General ElectricEnergy companies: Portland General Electric[1] Confirmed2026-04-17Shown
Energy partnersAvangridEnergy companies: Avangrid[1] Confirmed2026-04-17Shown
Current facility power243 MW[1] estimatedLikely2026-04-17Shown
Current facility power61 MW[1] estimatedLikely2023-08-02Superseded / alternative
Current facility power243 MW[1] estimatedLikely2024-11-08Superseded / alternative
Current facility power243 MW[1] estimatedLikely2025-04-14Superseded / alternative
Current IT capacity180 MW[1] estimatedLikely2026-04-17Shown
Current IT capacity45 MW[1] estimatedLikely2023-08-02Superseded / alternative
Current IT capacity180 MW[1] estimatedLikely2024-11-08Superseded / alternative
Current IT capacity180 MW[1] estimatedLikely2025-04-14Superseded / alternative
Estimated annual consumption1,490 GWh/yr[2] estimatedSpeculative2026-09-29Shown
ISO / RTONone (non-RTO region)[3] derivedLikely—Shown
Balancing authorityPGE[4] derivedLikely—Shown
Nearest mapped substationShute Substation (115 kV)way/735145719[5] derivedLikely2026-09-28Shown
Distance to substation0.5 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby500 kV[5] derivedLikely2026-09-28Shown
State avg. industrial price8.92¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price10.60¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km598 MW[7] derivedConfirmed202502Shown
Buildings (planned)4[1] derivedLikely2026-04-17Shown
Buildings operational4[1] estimatedLikely2026-04-17Shown
Buildings operational0[1] estimatedLikely2021-04-01Superseded / alternative
Buildings operational0[1] estimatedLikely2023-04-29Superseded / alternative
Buildings operational1[1] estimatedLikely2023-08-02Superseded / alternative
Buildings operational4[1] estimatedLikely2024-11-08Superseded / alternative
Buildings operational4[1] estimatedLikely2025-04-14Superseded / alternative
Capital cost / investment$6.8B[1] estimatedLikely2026-04-17Shown
Compute (H100-equivalents)123,800[1] estimatedLikely2026-04-17Shown
Chip typesH100[1] Confirmed2026-04-17Shown
Construction startApr 1, 2021[1] derivedLikely2026-04-17Shown
First operationalAug 2, 2023[1] derivedLikely2026-04-17Shown