Meta Temple

Operating + expandingAI campusCampusTemple, Bell County, Texas
80% profile completeness
42 claims from 11 sources
Current facility power
198 MW[1]
Likelyestimated
Planned capacity
231 MW[1]
Likelyestimated
Building footprint
666,600 sq ft[5]
Likelyderived
Buildings (planned)
Likelyderived
Capital cost / investment
$5.8B[1]
Likelyestimated
First operational
Dec 9, 2025[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H1 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Pedernales Electric Coop, INC · ERCOT
Substation: On-site substation

Power reality

Announced
231 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
33 MW[1]
Building 3 under construction (satellite-tracked phases)
Operational
198 MW[1]
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1]
  • Stated date: Next projected milestone: 2026-09-30 (modeled/speculative)[1]
  • Required: 231 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionApr 1, 2022
    Model estimate · Satellite imagery
    • Apr 1, 2022 · Reported status: under construction[1]
    • Apr 1, 2022 · Construction start[1]
    • Apr 1, 2022 · Land clearing begins.[1]
    • Dec 9, 2025 · Reported status: expanding[1]
  3. EnergizationDec 9, 2025
    Satellite imagery
    • Dec 9, 2025 · Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best e[1]
  4. OperationalDec 9, 2025
    Satellite imagery
    • Dec 9, 2025 · Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best e[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Meta Temple
  2. substation
    On-site substation[1][5]
    Satellite imageryLikely
    4 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.35 km away
  3. transmission
    138 kV line[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.33 km away). Not confirmed as the supply path.
  4. utility
    Pedernales Electric Coop, INC[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    ERCOT[4]
    Service territoryLikely
    Balancing authority: ERCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
31.13066, -97.37037
Address
2310 Eberhardt Rd, Temple, TX 76504[1]Likely
County
Bell County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Capital & construction
Contractor:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Meta[1]Confirmed
End user
Meta[1]Confirmed
Utility

Most likely retail provider among 5 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Heart of Texas Electric Coop, Bartlett Electric Coop, INC, Oncor Electric Delivery Company LLC, City of Bartlett - (Tx).

Contractor
JE Dunn[1]Confirmed

Power (all fields)

Current facility power
198 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
152 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
231 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2026-09-30); not necessarily full build-out.

Estimated annual consumption
1,214 GWh/yr[3]Speculativeestimated

198 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
ERCOT[4]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
ERCO[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (138 kV)[5]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.4 km[5]Likelyderived
Highest-voltage line nearby
138 kV[5]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
7.07¢/kWh[7]Confirmed

Texas statewide average, July 2026.

State avg. commercial price
8.47¢/kWh[7]Confirmed

Texas statewide average, July 2026.

Generation within 50 km
3.35 GW[8]Confirmedderived

20 EIA-reported plants within 50 km.

Generation queued in county
2.34 GW[6]Confirmedderived

9 active generation interconnection requests in Bell County: Storage 1,439 MW, Gas 637 MW, Solar 264 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
138 kV lineTransmission line0.33 km138 kV[5]
Temple Power Station · Temple Generation Holdings LLCPower plant (Natural Gas)9.7 km1.58 GW[8]
Big Elm Solar · Big Elm Solar, LLCPower plant (Solar)14.6 km200 MW[8]
Five Wells Solar Center - Hybrid · Five Wells Solar Center, LLCPower plant (Solar)18.1 km579 MW[8]
Orion III Solar Project · Ben Milam Solar 3 LLCPower plant (Solar)30.1 km250 MW[8]
Bpl Crown Solar LLC · BPL Crown Solar LLCPower plant (Solar)36.4 km100 MW[8]
Bpl Sol Solar LLC · BPL Sol Solar LLCPower plant (Solar)36.4 km100 MW[8]
Orion I Solar Project · Ben Milam Solar 1 LLCPower plant (Solar)38.2 km200 MW[8]
Orion II Solar Project · Ben Milam Solar 2 LLCPower plant (Solar)43 km250 MW[8]
Unnamed substationSubstation0.35 km138 kV[5]
Unnamed substationSubstation0.41 km138 kV[5]
Unnamed substationSubstation0.77 km138 kV[5]
Unnamed substationSubstation0.93 km138 kV[5]
Largest queued generation in this countyFuelQueue statusMWSource
Riviera GasERCOT 29INR0206 · BKV-BPP Power GasIn study · proposed 2030-06637 MW[6]
Lavita BESSERCOT 26INR0465 · Lavita BESS, LLCStorageIn study · proposed 2028-07606 MW[6]
Bell County Morgan StorageERCOT 26INR0615 · DM-BCTRM, LLCStorageIn study · proposed 2029-12256 MW[6]
Bell County Leifester StorageERCOT 26INR0614 · DM-BCRCML, LLCStorageIn study · proposed 2029-09205 MW[6]
Goldeneye BESSERCOT 25INR0100 · Black Mountain Energy Storage IIStorageIA signed · proposed 2028-05202 MW[6]
Cosper SolarERCOT 25INR0281 · Gransolar Texas Twenty LLCSolarIA signed · proposed 2027-11148 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Apr 1, 2022[1]
  5. First operational
    Dec 9, 2025[1]
  6. Expected completion
    Sep 30, 2026[1]
    Projected
Planned capacity
231 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2026-09-30); not necessarily full build-out.

Buildings (planned)
3[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
2[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Buildings 1–2operational198 MWDec 9, 2025[1]
Building 3under construction33 MWSep 30, 2026 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$5.8B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
666,600 sq ft[5]Likelyderived

Sum of 2 building outlines mapped in OpenStreetMap within this campus.

Floor area
Not yet sourced

Compute

Chip types
B300[1]Confirmed
Compute (H100-equivalents)
173,200[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Buildings operational
    0Apr 1, 2022[1]→2Dec 9, 2025[1]
  • Status
    Under constructionApr 1, 2022[1]→Operating + expandingDec 9, 2025[1]

Timeline

Construction start: Apr 1, 2022[1]
First operational: Dec 9, 2025[1]
  1. Apr 1, 2022[1]

    Land clearing begins.

  2. Feb 5, 2023[1]

    A traditional H-shaped Meta data center is partially built.

  3. Apr 1, 2023[1]

    The traditional Meta data center has been demolished mid-construction, in favor of Meta's new AI-optimized design.

  4. Nov 15, 2025[1]

    Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Space is cleared for Building 3.

  5. Dec 9, 2025198 MW facility power· 2 buildings operational[1]

    Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best estimate, but note that the planned completion date in this regulatory filing is 2026-03-01.

  6. Feb 24, 2026198 MW facility power· 2 buildings operational[1]

    Building 3 is under construction. An outline is visible for the building which has similar dimensions to those deployed at the Meta Prometheus site.

  7. Sep 30, 2026Projected231 MW facility power· 3 buildings operational[1]

    Building 3 is operational. Based on the stated completion date in this regulatory filing

All claims (provenance audit)

42
FieldValueSourceConfidenceAs ofStatus
NameMeta Temple[1] Likely2026-02-24Shown
StatusUnder construction[1] derivedLikely2022-04-01Superseded / alternative
StatusUnder construction[1] derivedLikely2023-02-05Superseded / alternative
StatusUnder construction[1] derivedLikely2023-04-01Superseded / alternative
StatusUnder construction[1] derivedLikely2025-11-15Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-12-09Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-02-24Shown
Facility typeAI campus[1] derivedLikely2026-02-24Shown
Address2310 Eberhardt Rd, Temple, TX 76504[1] Likely2026-02-24Shown
OwnerMetaOwner: Meta[1] Confirmed2026-02-24Shown
End usersMetaUsers: Meta[1] Confirmed2026-02-24Shown
UtilityPedernales Electric Coop, INCterritory 14626: PEDERNALES ELECTRIC COOP, INC (COOPERATIVE, PEDERNALES ELECTRIC[2] derivedUnverified2022Shown
ConstructionJE DunnConstruction companies: JE Dunn[1] Confirmed2026-02-24Shown
Current facility power198 MW[1] estimatedLikely2026-02-24Shown
Current facility power198 MW[1] estimatedLikely2025-12-09Superseded / alternative
Current IT capacity152 MW[1] estimatedLikely2026-02-24Shown
Current IT capacity152 MW[1] estimatedLikely2025-12-09Superseded / alternative
Planned capacity231 MW[1] estimatedLikely2026-02-24Shown
Estimated annual consumption1,214 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTOERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.[4] derivedLikely—Shown
Balancing authorityERCO[2] derivedLikely—Shown
Nearest mapped substationUnnamed substation (138 kV)way/1469988913[5] derivedLikely2026-09-28Shown
Distance to substation0.4 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby138 kV[5] derivedLikely2026-09-28Shown
Generation queued in county2.34 GW[6] derivedConfirmed2026-09-01Shown
State avg. industrial price7.07¢/kWh[7] Confirmed2026-07Shown
State avg. commercial price8.47¢/kWh[7] Confirmed2026-07Shown
Generation within 50 km3.35 GW[8] derivedConfirmed202502Shown
Buildings (planned)3[1] derivedLikely2026-02-24Shown
Buildings operational2[1] estimatedLikely2026-02-24Shown
Buildings operational0[1] estimatedLikely2022-04-01Superseded / alternative
Buildings operational0[1] estimatedLikely2023-02-05Superseded / alternative
Buildings operational0[1] estimatedLikely2023-04-01Superseded / alternative
Buildings operational0[1] estimatedLikely2025-11-15Superseded / alternative
Buildings operational2[1] estimatedLikely2025-12-09Superseded / alternative
Building footprint666,600 sq ftway/1469988846 way/1469988847[5] derivedLikely2026-09-27Shown
Capital cost / investment$5.8B[1] estimatedLikely2026-02-24Shown
Compute (H100-equivalents)173,200[1] estimatedLikely2026-02-24Shown
Chip typesB300[1] Confirmed2026-02-24Shown
Construction startApr 1, 2022[1] derivedLikely2026-02-24Shown
First operationalDec 9, 2025[1] derivedLikely2026-02-24Shown
Expected completionSep 30, 2026[1] estimatedSpeculative2026-02-24Shown