Microsoft-Nebius New Jersey
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationApr 15, 2026
Satellite imagery
- Apr 15, 2026 · High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational aro[1]
- OperationalApr 15, 2026
Satellite imagery
- Apr 15, 2026 · High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational aro[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMicrosoft-Nebius New Jersey
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps Lincoln 3/Clayville Substation 0.23 km away
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityCity of Vineland - (Nj)[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- Clayville (Natural Gas, 55 MW) is 0.5 km away[8]EIA plant within 1.5 km; proximity does not establish that it supplies the facilityNatural gasCo-located55 MWUnverified
Location & imagery
Mapped outline- Coordinates
- 39.42753, -75.01651
- Address
- County
- Cumberland County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
70 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- State avg. industrial price
New Jersey statewide average, July 2026.
- State avg. commercial price
New Jersey statewide average, July 2026.
- Generation within 50 km
62 EIA-reported plants within 50 km.
- Generation queued in county
12 active generation interconnection requests in Cumberland County: Solar 324 MW, Storage 100 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Clayville · City of Vineland - (NJ) | Power plant (Natural Gas) | 0.5 km | 55 MW | [8] |
| Sherman Avenue · Calpine New Jersey Generation LLC | Power plant (Natural Gas) | 4.4 km | 87 MW | [8] |
| Howard Down · City of Vineland - (NJ) | Power plant (Natural Gas) | 7 km | 55 MW | [8] |
| Cumberland (Nj) · Calpine New Jersey Generation LLC | Power plant (Natural Gas) | 7.2 km | 187 MW | [8] |
| Pseg Salem Generating Station · PSEG Nuclear LLC | Power plant (Nuclear) | 44.8 km | 2.32 GW | [8] |
| Pseg Hope Creek Generating Station · PSEG Nuclear LLC | Power plant (Nuclear) | 45 km | 1.17 GW | [8] |
| West Deptford Energy Station · West Deptford Energy LLC | Power plant (Natural Gas) | 49.3 km | 735 MW | [8] |
| Garrison Energy Center LLC · Garrison Energy Center LLC | Power plant (Natural Gas) | 49.4 km | 309 MW | [8] |
| Lincoln 3/Clayville Substation · Vineland Municipal Electric Utility | Substation | 0.23 km | 138 kV | [5] |
| Lincoln/Clayville Substation · Vineland Municipal Electric Utility | Substation | 0.34 km | 69 kV | [5] |
| Wheaton Substation | Substation | 2.04 km | 69 kV | [5] |
| Unnamed substation | Substation | 2.2 km | 69 kV | [5] |
| Butler Substation · Vineland Municipal Electric Utility | Substation | 2.29 km | 69 kV | [5] |
| Unnamed substation | Substation | 2.58 km | 69 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Buckshutem Solar IPJM AE1-179 | Solar | IA signed · proposed 2027-01 | 60 MW | [6] |
| South Millville - Newport 69 kVPJM AI2-385 | Solar | In study · proposed 2025-03 | 60 MW | [6] |
| Sherman Ave - West Vineland 69 kVPJM AF1-238 - moved to TC1 | Storage | In study · proposed 2023-05 | 50 MW | [6] |
| Nabb Solar ProjectPJM AE1-240 | Solar | Suspended · proposed 2024-10 | 50 MW | [6] |
| Carlls Corner - Sherman Ave 69 kVPJM AI2-387 | Solar | In study · proposed 2024-12 | 50 MW | [6] |
| Roadstown 69 kVPJM AG2-241 | Solar | In study · proposed 2023-09 | 47 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startMay 31, 2024[1]
- First operationalApr 15, 2026[1]
- Expected completion—
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | operational | 70 MW | Apr 15, 2026 | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- May 31, 2024[1]
Land clearing begins for northern two buildings (Building 1-2).
- Dec 15, 2025[1]
By mid-December 2025 the building was still not complete. A satellite analysis by SemiAnalysis found that the air-cooled chillers serving the second half of the first 50 MW phase were not yet installed, so the phase was not yet operational. SemiAnalysis estimated the full 50 MW would be reached around January to February 2026.
High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational around early 2026 with about 50 MW of IT capacity (70 MW total facility power at a 1.4 PUE), based on DataOne's disclosure of a first 50 MW phase. SemiAnalysis estimated the full 50 MW was reached around January to February 2026 (SemiAnalysis); this April image is our first high-resolution confirmation that the cooling is in place.
Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.
Buildings on this campus
1- DataOne VinelandOperating · 115,800 sq ft footprint
All claims (provenance audit)
33| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Microsoft-Nebius New Jersey | [1] | Likely | 2026-07-12 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-05-31 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-12-15 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-04-15 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-07-12 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-12 | Shown |
| Address | 3963 S Lincoln Ave, Vineland, New Jersey | [1] | Likely | 2026-07-12 | Shown |
| Owner | NebiusOwner: Nebius | [1] | Confirmed | 2026-07-12 | Shown |
| End users | MicrosoftUsers: Microsoft | [1] | Likely | 2026-07-12 | Shown |
| Utility | City of Vineland - (Nj)territory 19856: CITY OF VINELAND - (NJ) (MUNICIPAL, CITY OF VINELAND - (NJ)) | [2] derived | Likely | 2022 | Shown |
| Current facility power | 70 MW | [1] estimated | Likely | 2026-07-12 | Shown |
| Current facility power | 70 MW | [1] estimated | Likely | 2026-04-15 | Superseded / alternative |
| Current IT capacity | 50 MW | [1] estimated | Likely | 2026-07-12 | Shown |
| Current IT capacity | 50 MW | [1] estimated | Likely | 2026-04-15 | Superseded / alternative |
| Estimated annual consumption | 429 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [4] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Lincoln 3/Clayville Substation (138 kV)way/1099917639 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 424 MW | [6] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 15.63¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 19.17¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 5.12 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-07-12 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-07-12 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-05-31 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-12-15 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-04-15 | Superseded / alternative |
| Capital cost / investment | $1.9B | [1] estimated | Likely | 2026-07-12 | Shown |
| Compute (H100-equivalents) | 56,800 | [1] estimated | Likely | 2026-07-12 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-07-12 | Shown |
| Construction start | May 31, 2024 | [1] derived | Likely | 2026-07-12 | Shown |
| First operational | Apr 15, 2026 | [1] derived | Likely | 2026-07-12 | Shown |