OpenAI Stargate Lordstown
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityOpenAI Stargate Lordstown
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
PJM Z2-028 Lordstown Energy Center · Gas | Possibly related generation Speculative Generation request name/developer shares “lordstown” with this facility, in the same county. Not confirmed as serving it. | In service In Service; feasibility: Document Posted; system impact: Document Posted; facilities: Document Posted; ISA/GIA: Document Posted | 800 | 800 | Feb 21, 2014 | In service Aug 15, 2018 | Highland-Sammis 345kV & Highland-Mansfield 345kV TO: ATSI | [4] Sep 27, 2026 |
PJM AB1-017 Lordstown Energy Center · Gas | Possibly related generation Speculative Generation request name/developer shares “lordstown” with this facility, in the same county. Not confirmed as serving it. | In service In Service; feasibility: Document Posted; system impact: Document Posted; facilities: Document Posted; ISA/GIA: Document Posted | 940 | 64 | Jun 18, 2015 | In service Aug 11, 2018 | Highland-Sammis 345 kV & Highland-Mansfield 345 kV TO: ATSI | [4] Sep 27, 2026 |
PJM AF2-044 Lordstown Energy Center · Gas | Possibly related generation Speculative Generation request name/developer shares “lordstown” with this facility, in the same county. Not confirmed as serving it. | In service In Service; feasibility: Document Posted; system impact: Document Posted; facilities: Not Required; ISA/GIA: Document Posted | 940 | 20 | Dec 10, 2019 | In service Oct 20, 2020 | Highland-Sammis and Highland-Mansfield 345 kV TO: ATSI | [4] Sep 27, 2026 |
On-site & dedicated generation
- PJM Z2-028 Lordstown Energy Center (Gas, 800 MW requested)[4]Generation request name/developer shares “lordstown” with this facility, in the same county. Not confirmed as serving it.Natural gasArrangement unknown800 MWSpeculative
- PJM AB1-017 Lordstown Energy Center (Gas, 940 MW requested)[4]Generation request name/developer shares “lordstown” with this facility, in the same county. Not confirmed as serving it.Natural gasArrangement unknown940 MWSpeculative
- PJM AF2-044 Lordstown Energy Center (Gas, 940 MW requested)[4]Generation request name/developer shares “lordstown” with this facility, in the same county. Not confirmed as serving it.Natural gasArrangement unknown940 MWSpeculative
Location & imagery
Mapped outline- Coordinates
- 41.15393, -80.88097
- Address
- County
- Trumbull County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2027-03-01); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
11 EIA-reported plants within 50 km.
- Generation queued in county
6 active generation interconnection requests in Trumbull County: Gas 1,950 MW, Solar 147 MW, Solar + storage 49 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Clean Energy Future-Lordstown, LLC · Clean Energy Future-Lordstown, LLC | Power plant (Natural Gas) | 2.5 km | 858 MW | [6] |
| Clevelandcliffs Warren · Clevelandcliffs Warren | Power plant (Other) | 8.3 km | 12 MW | [6] |
| Niles Rto Btm · American Mun Power-Ohio, Inc | Power plant (Petroleum) | 10.8 km | 11 MW | [6] |
| Niles Power Plant · Niles Power, LLC | Power plant (Petroleum) | 11.3 km | 26 MW | [6] |
| Summit Street Power Plant · Kent State University | Power plant (Natural Gas) | 38.5 km | 12 MW | [6] |
| Hickory Run Energy Station · Hickory Run Energy, LLC | Power plant (Natural Gas) | 41.8 km | 938 MW | [6] |
| New Castle Plant · New Castle Power, LLC | Power plant (Natural Gas) | 49.2 km | 331 MW | [6] |
| Cuyahoga Falls 1 · City of Cuyahoga Falls - (OH) | Power plant (Petroleum) | 49.7 km | 14 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Trumbull 345 kVPJM AJ1-023 | Gas | In study · proposed 2024-12 | 1.01 GW | [4] |
| Trumbull Energy CenterPJM AB1-105 | Gas | Under construction · proposed 2025-08 | 940 MW | [4] |
| Dilworth 69 kV IIIPJM AG2-253 | Solar | In study · proposed 2023-01 | 69 MW | [4] |
| Dilworth 69 kV IIPJM AG2-252 | Solar | In study · proposed 2023-01 | 49 MW | [4] |
| Trumbull138 kVPJM AH2-239 | Solar + storage | In study · proposed 2027-03 | 49 MW | [4] |
| Dilworth 69 kVPJM AG2-251 | Solar | In study · proposed 2023-01 | 29 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startOct 12, 2025[1]
- First operationalMar 1, 2027[1]Projected
- Expected completionMar 1, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-03-01); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | under construction | 300 MW | Mar 1, 2027 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Oct 12, 2025[1]
Land clearing begins in the front of the site (the side facing the Ohio Turnpike), clearing away a parking lot and solar array
- Feb 27, 2026[1]
Still no visible construction, although construction within preexisting facilities
- Jul 30, 2026[1]
Active construction visible on and around the datacenter, with the roofing mostly in place. This is based on satellite imagery. No buildings operational yet.
Projected operational date. OpenAI stated Lordstown and Milam County could scale to 1.5 GW within 18 months of their September 23, 2025 announcement; subtracting Milam County's subsequently disclosed 1.2 GW capacity implies ~300 MW for Lordstown.
All claims (provenance audit)
25| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | OpenAI Stargate Lordstown | [1] | Likely | 2026-07-30 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-10-12 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-02-27 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-07-30 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-30 | Shown |
| Project | Stargate | [1] | Confirmed | 2026-07-30 | Shown |
| Address | 2300 Hallock Young Rd, Warren, OH 44481 | [1] | Likely | 2026-07-30 | Shown |
| Owner | SoftBankOwner: Softbank | [1] | Confirmed | 2026-07-30 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Confirmed | 2026-07-30 | Shown |
| Utility | Ohio Edisonterritory 13998: OHIO EDISON CO (INVESTOR OWNED, FIRSTENERGY CORP) | [2] derived | Likely | 2022 | Shown |
| Planned capacity | 300 MW | [1] estimated | Likely | 2026-07-30 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Generation queued in county | 2.15 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.21 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-07-30 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-07-30 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-10-12 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-02-27 | Superseded / alternative |
| Chip types | Rubin | [1] | Confirmed | 2026-07-30 | Shown |
| Construction start | Oct 12, 2025 | [1] derived | Likely | 2026-07-30 | Shown |
| First operational | Mar 1, 2027 | [1] estimated | Speculative | 2026-07-30 | Shown |
| Expected completion | Mar 1, 2027 | [1] estimated | Speculative | 2026-07-30 | Shown |