Proposed data center — STPL-2022-0040
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No recorded land acquisition found.
How the time-to-power window was estimated
- Current stage: Permitting (furthest stage with documented evidence)[1]
- No public grid record: No interconnection request or utility contract found; adds uncertainty to the upper bound.
- From “Permitting”, large loads have typically taken 1.5–4 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under construction
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Permit / site plan.
Grid path
- →facilityProposed data center — STPL-2022-0040
- →substationPleasant View Substation (230 kV)[4]Proximity onlyUnverifiedNearest mapped substation, 0.59 km away. Proximity does not establish that it serves the site.
- →transmission514 (500 kV)[4]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.64 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
County parcel- Coordinates
- 39.07386, -77.52245
- County
- Loudoun County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Virginia statewide average, July 2026.
- State avg. commercial price
Virginia statewide average, July 2026.
- Generation within 50 km
40 EIA-reported plants within 50 km.
- Generation queued in county
11 active generation interconnection requests in Loudoun County: Storage 940 MW, Solar 100 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 227;274 · Dominion Energy | Transmission line | 0.22 km | 230 kV | [4] |
| 203 · Virginia Electric & Power Company | Transmission line | 0.56 km | 230 kV | [4] |
| 514 · Virginia Electric & Power Company | Transmission line | 0.64 km | 500 kV | [4] |
| 595 · Virginia Electric & Power Company | Transmission line | 0.7 km | 500 kV | [4] |
| 500 kV line · Dominion Energy | Transmission line | 0.7 km | 500 kV | [4] |
| Brambleton - Goose Creek · Virginia Electric & Power Company | Transmission line | 0.81 km | 500 kV | [4] |
| Potomac Energy Center, LLC · Potomac Energy Center LLC | Power plant (Natural Gas) | 2.6 km | 766 MW | [7] |
| Montgomery County Resource Recovery · Covanta Montgomery, Inc. | Power plant (Biomass) | 15.2 km | 54 MW | [7] |
| Dickerson Power · Dickerson Power, LLC | Power plant (Natural Gas) | 15.9 km | 299 MW | [7] |
| Blake Solar Plant · Horus West Virginia 1, LLC | Power plant (Solar) | 34.1 km | 80 MW | [7] |
| Nih Cogeneration Facility · National Institutes of Health | Power plant (Natural Gas) | 37.9 km | 28 MW | [7] |
| Covanta Alexandria/Arlington Energy · Covanta Alexandria/Arlington | Power plant (Biomass) | 45.6 km | 29 MW | [7] |
| Central Utility Plant At White Oak · GSA Metropolitan Service Center | Power plant (Natural Gas) | 46.8 km | 54 MW | [7] |
| Covanta Fairfax Energy · Covanta Fairfax Inc | Power plant (Biomass) | 48.7 km | 98 MW | [7] |
| Pleasant View Substation · Dominion Energy | Substation | 0.59 km | 230 kV | [4] |
| Pleasant View Substation · Dominion Energy | Substation | 0.71 km | 500 kV | [4] |
| Goose Creek Substation · Dominion Energy | Substation | 0.81 km | 500 kV | [4] |
| Cochran Mill Delivery Point | Substation | 1.81 km | 230 kV | [4] |
| Belmont Substation · Virginia Electric and Power Company | Substation | 2.31 km | 230 kV | [4] |
| Stonewater Substation | Substation | 2.44 km | 230 kV | [4] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Loudoun 230 kVPJM AG2-285 | Storage | In study · proposed 2023-12 | 150 MW | [5] |
| Beaumeade 230 kVPJM AG2-287 | Storage | In study · proposed 2023-12 | 150 MW | [5] |
| New Road StoragePJM AE2-019 | Storage | IA signed · proposed 2026-12 | 120 MW | [5] |
| Dulles SolarPJM AF1-147 | Solar | IA signed · proposed 2023-12 | 100 MW | [5] |
| Roundtable 230 kVPJM AG2-307 | Storage | In study · proposed 2023-12 | 100 MW | [5] |
| Shelhorn 230 kVPJM AG2-323 | Storage | In study · proposed 2023-12 | 100 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting2022[1]
- Construction start—
- First operational—
- Expected completion—
- Permitting status
- Permit / case numbers
- Planned floor area
Building area proposed in the site plan.
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Planned floor area
Building area proposed in the site plan.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- 2022[1]
Loudoun County site plan STPL-2022-0040 — Approved: Conditionally, 2,406,563 sq ft proposed.
All claims (provenance audit)
17| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Proposed data center — STPL-2022-0040 | [1] derived | Confirmed | 2026-09-27 | Shown |
| Status | Planned | [1] derived | Confirmed | 2026-09-27 | Shown |
| Utility | Dominion Energyterritory 19876: VIRGINIA ELECTRIC & POWER CO (INVESTOR OWNED, DOMINION RESOURCE | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Pleasant View Substation (230 kV)way/45842846 | [4] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.6 km | [4] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 500 kV | [4] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.04 GW | [5] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.07¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.68¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.56 GW | [7] derived | Confirmed | 202502 | Shown |
| Permitting status | Site plan STPL-2022-0040: Approved: ConditionallyApplication STPL-2022-0040, zoning case ZMAP-2018-0009 | [1] | Confirmed | 2026-09-27 | Shown |
| Permit / case numbers | STPL-2022-0040 | [1] | Confirmed | 2026-09-27 | Shown |
| Permit / case numbers | ZMAP-2018-0009 | [1] | Confirmed | 2026-09-27 | Shown |
| Planned floor area | 2.41M sq ft | [1] | Confirmed | 2026-09-27 | Shown |
| Permit / site plan filed | 2022 | [1] derived | Confirmed | 2026-09-27 | Shown |