QTS Richmond 3
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationFeb 13, 2026
- OperationalFeb 13, 2026
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityQTS Richmond 3
- →substationTechpark Place Substation (230 kV)[5]Proximity onlyUnverifiedNearest mapped substation, 0.72 km away. Proximity does not establish that it serves the site.
- →transmission230 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.58 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
PJM U2-013 Richmond Energy Facility · Gas | Possibly related generation Speculative Generation request name/developer shares “richmond” with this facility, in the same county. Not confirmed as serving it. | In service In Service; feasibility: Document Posted; system impact: Document Posted; facilities: Not Required; ISA/GIA: Document Posted | 8 | 8 | May 16, 2008 | In service Dec 29, 2011 | Northeast 34.5kV TO: Dominion | [6] Sep 27, 2026 |
On-site & dedicated generation
- PJM U2-013 Richmond Energy Facility (Gas, 8 MW requested)[6]Generation request name/developer shares “richmond” with this facility, in the same county. Not confirmed as serving it.Natural gasArrangement unknown8 MWSpeculative
Location & imagery
ApproximateLocation is approximate (approximate); the marker does not identify the exact site.
- Coordinates
- 37.47916, -77.25095
- Address
- County
- Henrico County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-02-13); not necessarily full build-out.
- Estimated annual consumption
202 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Virginia statewide average, July 2026.
- State avg. commercial price
Virginia statewide average, July 2026.
- Generation within 50 km
30 EIA-reported plants within 50 km.
- Generation queued in county
4 active generation interconnection requests in Henrico County: Solar 20 MW, Storage 11 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line · Virginia Electric and Power Company | Transmission line | 0.58 km | 230 kV | [5] |
| Skipjack Solar Center · AES Distributed Energy | Power plant (Solar) | 9.4 km | 175 MW | [8] |
| Darbytown · Virginia Electric & Power Co | Power plant (Natural Gas) | 10.6 km | 340 MW | [8] |
| Chesterfield · Virginia Electric & Power Co | Power plant (Natural Gas) | 15.9 km | 386 MW | [8] |
| Hopewell Cogeneration · Luminant Generation Company LLC | Power plant (Natural Gas) | 21 km | 378 MW | [8] |
| Fort Powhatan Solar · Dominion Renewable Energy | Power plant (Solar) | 28.7 km | 150 MW | [8] |
| Westrock-West Point Mill · WestRock-West Point Mill | Power plant (Biomass) | 39.9 km | 101 MW | [8] |
| Doswell Energy Center · Doswell Ltd Partnership | Power plant (Natural Gas) | 41.7 km | 1.19 GW | [8] |
| Colonial Trail West · Dominion Energy Inc. | Power plant (Solar) | 48.8 km | 142 MW | [8] |
| Techpark Place Substation · Dominion Energy | Substation | 0.72 km | 230 kV | [5] |
| White Oak Substation · Dominion Energy | Substation | 0.84 km | 230 kV | [5] |
| Virginia Electric and Power Company substation · Virginia Electric and Power Company | Substation | 0.96 km | 230 kV | [5] |
| Unnamed substation | Substation | 1.04 km | 230 kV | [5] |
| Elko Substation · Virginia Electric and Power Company | Substation | 1.21 km | 230 kV | [5] |
| Unnamed substation | Substation | 2.33 km | 34.5 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Turner 34.5 kVPJM AG2-193 | Solar | In study · proposed 2023-12 | 20 MW | [6] |
| Darbytown 230 kVPJM AH1-141 | Storage | In study · proposed 2024-12 | 5 MW | [6] |
| Darbytown 230 kV IIPJM AH1-142 | Storage | In study · proposed 2024-12 | 4 MW | [6] |
| Darbytown 230 kV IIIPJM AH1-143 | Storage | In study · proposed 2024-12 | 2 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Compute (H100-equivalents)
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Apr 1, 2024[1]
Land clearing begins.
- Feb 4, 2025[1]
Building 1 shell is mostly complete, with some chillers installed on the roof. Building 2 shell is under construction.
- Nov 19, 2025[1]
The substation is still under construction, based on a Google Earth image, so we don't think any buildings are operational yet.
- Dec 31, 2025[1]
The substation looks complete, but we expect Building 1 still needs commissioning before it is fully operational.
Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the perimeter and no cars in the carpark, but we expect they will be operational within 3 months. Building 4 has complete chillers and backup generators, while Building 5 has chillers but only a few backup generators - roughly the state of Building 1 on 2025-02-04.
Building 2 and 3 are operational, based on the previous entry.
Building 4 and 5 are operational, based on Building 5 being roughly 1 year behind Building 1 in satellite imagery.
All claims (provenance audit)
36| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | QTS Richmond 3 | [1] | Likely | 2026-05-14 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-04-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-02-04 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-11-19 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-12-31 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-13 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-14 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-14 | Shown |
| Address | 3525–3543 Portugee Rd, Sandston, VA 23150 | [1] | Likely | 2026-05-14 | Shown |
| Utility | Dominion EnergyEnergy companies: Dominion Energy | [1] | Confirmed | 2026-05-14 | Shown |
| Current facility power | 202 MW | [1] estimated | Likely | 2026-05-14 | Shown |
| Current facility power | 67 MW | [1] estimated | Likely | 2026-02-13 | Superseded / alternative |
| Current IT capacity | 144 MW | [1] estimated | Likely | 2026-05-14 | Shown |
| Current IT capacity | 48 MW | [1] estimated | Likely | 2026-02-13 | Superseded / alternative |
| Planned capacity | 336 MW | [1] estimated | Likely | 2026-05-14 | Shown |
| Estimated annual consumption | 1,239 GWh/yr | [2] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [4] derived | Likely | — | Shown |
| Nearest mapped substation | Techpark Place Substation (230 kV)way/1265396511 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.7 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 31 MW | [6] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.07¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.68¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.35 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings operational | 3 | [1] estimated | Likely | 2026-05-14 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-04-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-02-04 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-11-19 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-12-31 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-02-13 | Superseded / alternative |
| Capital cost / investment | $5.5B | [1] estimated | Likely | 2026-05-14 | Shown |
| Compute (H100-equivalents) | 174,800 | [1] estimated | Likely | 2026-05-14 | Shown |
| Construction start | Apr 1, 2024 | [1] derived | Likely | 2026-05-14 | Shown |
| First operational | Feb 13, 2026 | [1] derived | Likely | 2026-05-14 | Shown |
| Expected completion | Feb 13, 2027 | [1] estimated | Speculative | 2026-05-14 | Shown |