Rowan Temple
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No grid, construction or operating record yet backs the 300 MW announced.
- ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
- ⚠ No recorded land acquisition found.
How the time-to-power window was estimated
- Current stage: Announced (furthest stage with documented evidence)[1]
- No public grid record: No interconnection request or utility contract found; adds uncertainty to the upper bound.
- Required: 300 MW
- From “Announced”, large loads have typically taken 2–5 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- AnnouncedSep 11, 2026
Utility filing / announcement
- Sep 11, 2026 · Planned capacity reported: 300 MW[1]
- Land acquired
- Planning / zoning
- Permitting
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under construction
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Utility filing / announcement.
Grid path
- →facilityRowan Temple
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
County-level (approximate)Location is approximate (county-level (approximate)); the marker does not identify the exact site.
- Coordinates
- 31.03737, -97.47867
- County
- Bell County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Developer
“Rowan Digital Infrastructure / Data Center Temple, TX”
- Utility
“Rowan Digital Infrastructure / Data Center Temple, TX” Listed by EEI under this member utility.
No tenants or end users identified in our sources yet.
Power (all fields)
- Planned capacity
“Rowan Digital Infrastructure / Data Center Temple, TX ▪ 300 MW data center project.”
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
16 EIA-reported plants within 50 km.
- Generation queued in county
9 active generation interconnection requests in Bell County: Storage 1,439 MW, Gas 637 MW, Solar 264 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Temple Power Station · Temple Generation Holdings LLC | Power plant (Natural Gas) | 15.5 km | 1.58 GW | [6] |
| Five Wells Solar Center - Hybrid · Five Wells Solar Center, LLC | Power plant (Solar) | 21.4 km | 579 MW | [6] |
| Big Elm Solar · Big Elm Solar, LLC | Power plant (Solar) | 27.5 km | 200 MW | [6] |
| Orion III Solar Project · Ben Milam Solar 3 LLC | Power plant (Solar) | 34.8 km | 250 MW | [6] |
| Phantom Solar · Phantom Solar, LLC | Power plant (Solar) | 35.9 km | 15 MW | [6] |
| Bt Jungmann · BT Jungmann, LLC | Power plant (Solar) | 42.8 km | 40 MW | [6] |
| Orion I Solar Project · Ben Milam Solar 1 LLC | Power plant (Solar) | 45.7 km | 200 MW | [6] |
| North Fork Tx · Engie North America | Power plant (Batteries) | 49.6 km | 100 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Riviera GasERCOT 29INR0206 · BKV-BPP Power | Gas | In study · proposed 2030-06 | 637 MW | [4] |
| Lavita BESSERCOT 26INR0465 · Lavita BESS, LLC | Storage | In study · proposed 2028-07 | 606 MW | [4] |
| Bell County Morgan StorageERCOT 26INR0615 · DM-BCTRM, LLC | Storage | In study · proposed 2029-12 | 256 MW | [4] |
| Bell County Leifester StorageERCOT 26INR0614 · DM-BCRCML, LLC | Storage | In study · proposed 2029-09 | 205 MW | [4] |
| Goldeneye BESSERCOT 25INR0100 · Black Mountain Energy Storage II | Storage | IA signed · proposed 2028-05 | 202 MW | [4] |
| Cosper SolarERCOT 25INR0281 · Gransolar Texas Twenty LLC | Solar | IA signed · proposed 2027-11 | 148 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
- Planned capacity
“Rowan Digital Infrastructure / Data Center Temple, TX ▪ 300 MW data center project.”
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
9| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Developer | Rowan Digital Infrastructure | [1] | Confirmed | 2026-09-11 | Shown |
| Utility | Oncor Electric Delivery | [1] | Confirmed | 2026-09-11 | Shown |
| Planned capacity | 300 MW | [1] | Likely | 2026-09-11 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [2] derived | Likely | — | Shown |
| Balancing authority | ERCO | [3] derived | Likely | — | Shown |
| Generation queued in county | 2.34 GW | [4] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.99 GW | [6] derived | Confirmed | 202502 | Shown |