STACK Infrastructure NVA02

Operating + expandingAI campusCampusManassas, Prince William County, Virginia
60% profile completeness
37 claims from 12 sources
Current facility power
118 MW[1]
Likelyestimated
Planned capacity
487 MW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
$3.2B[1]
Likelyestimated
First operational
Oct 1, 2024[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H2 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Dominion Energy · PJM
Substation: On-site substation

Power reality

Announced
487 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
369 MW[1]
Buildings 2–6 under construction (satellite-tracked phases)
Operational
118 MW[1]
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1]
  • Stated date: Next projected milestone: 2028-01-01 (modeled/speculative)[1]
  • Required: 487 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H2 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredMay 6, 2025
    Government record
    • May 6, 2025 · Land acquisition / deed recorded[9]
    • May 6, 2025 · Deed recorded for parcel 7595-65-9789.00.[9]
    • May 6, 2025 · Deed recorded for parcel 7595-75-3611.[9]
    • May 6, 2025 · Deed recorded for parcel 7595-76-2590.[9]
    • May 6, 2025 · Deed recorded for parcel 7595-54-7478.[9]
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionOct 19, 2019
    Model estimate · Satellite imagery
    • Oct 19, 2019 · Reported status: under construction[1]
    • Oct 19, 2019 · Construction start[1]
    • Oct 19, 2019 · Land clearing begins by Peterson Companies for Stack Infrastructure, which is noted in the [news](https://www.bisnow.com/washington-dc/news/data-center/peterson-cos-partnering-to-b[1]
    • Oct 1, 2024 · Reported status: expanding[1]
  3. EnergizationOct 1, 2024
    Satellite imagery
    • Oct 1, 2024 · Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satel[1]
  4. OperationalOct 1, 2024
    Satellite imagery
    • Oct 1, 2024 · Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satel[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.

Grid path

  1. facility
    STACK Infrastructure NVA02
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    1 substation outline traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Dominion Energy[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    PJM[4]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
38.74436, -77.54020
Address
9590 Hornbaker Rd, Manassas, VA 20109[1]Likely
County
Prince William County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility

Location falls inside this utility's retail service territory.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
118 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
85 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
487 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2028-01-01); not necessarily full build-out.

Estimated annual consumption
724 GWh/yr[3]Speculativeestimated

118 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[4]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Hourglass Substation (230 kV)[5]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
2.1 km[5]Likelyderived
State avg. industrial price
10.07¢/kWh[7]Confirmed

Virginia statewide average, July 2026.

State avg. commercial price
11.68¢/kWh[7]Confirmed

Virginia statewide average, July 2026.

Generation within 50 km
2.83 GW[8]Confirmedderived

35 EIA-reported plants within 50 km.

Generation queued in county
1.35 GW[6]Confirmedderived

16 active generation interconnection requests in Prince William County: Storage 1,350 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Covanta Fairfax Energy · Covanta Fairfax IncPower plant (Biomass)26.5 km98 MW[8]
Remington · Virginia Electric & Power CoPower plant (Natural Gas)30 km604 MW[8]
Marsh Run Generation Facility · Old Dominion Electric CoopPower plant (Natural Gas)31.1 km481 MW[8]
Possum Point · Virginia Electric & Power CoPower plant (Natural Gas)32.3 km645 MW[8]
Potomac Energy Center, LLC · Potomac Energy Center LLCPower plant (Natural Gas)34.9 km766 MW[8]
Covanta Alexandria/Arlington Energy · Covanta Alexandria/ArlingtonPower plant (Biomass)36.2 km29 MW[8]
Ripley · MN8 Energy LLCPower plant (Solar)45 km28 MW[8]
Nih Cogeneration Facility · National Institutes of HealthPower plant (Natural Gas)48 km28 MW[8]
Hourglass SubstationSubstation2.12 km230 kV[5]
Sandlot Substation · Dominion EnergySubstation2.62 km230 kV[5]
Innovation SubstationSubstation2.65 km230 kV[5]
Wellington Delivery PointSubstation2.68 km115 kV[5]
Dominion Delivery Point · Dominion EnergySubstation2.68 km115 kV[5]
City of Manassas - (VA) substation · City of Manassas - (VA)Substation2.71 km13.2 kV[5]
Largest queued generation in this countyFuelQueue statusMWSource
Gainesville-Loudoun 230 kVPJM AI2-231StorageIn study · proposed 2023-10200 MW[6]
Nokesville-Vint Hill 230 kVPJM AG2-113StorageIn study · proposed 2022-08150 MW[6]
Catharpin 230 kVPJM AG2-284StorageIn study · proposed 2023-12150 MW[6]
Liberty 230 kVPJM AG2-304StorageIn study · proposed 2023-12150 MW[6]
Possum Point 230 kVPJM AG2-306StorageIn study · proposed 2023-12150 MW[6]
Possum Point 230kVPJM AH2-034StorageIn study · proposed 2028-12100 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    May 6, 2025[9]
  3. Permitting
    —
  4. Construction start
    Oct 19, 2019[1]
  5. First operational
    Oct 1, 2024[1]
  6. Expected completion
    Jan 1, 2028[1]
    Projected
Planned capacity
487 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2028-01-01); not necessarily full build-out.

Buildings (planned)
6[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
1[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational118 MWOct 1, 2024[1]
Buildings 2–6under construction369 MWJan 1, 2028 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

ParcelRecord ownerAcresZoning / useBuilding sq ftSource
7595-65-9789.00
Prince William County, VA
—14.22——[9]
7595-75-3611
Prince William County, VA
—16.44——[9]
7595-76-2590
Prince William County, VA
—20.77——[9]
7595-54-7478
Prince William County, VA
—49.76——[9]
Site area
101.2 acres[9]Confirmed

Sum of county land area across parcels.

Capital cost / investment
$3.2B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

Size

Parcel / land records
7595-65-9789.00 (Prince William County),7595-75-3611 (Prince William County),7595-76-2590 (Prince William County),7595-54-7478 (Prince William County)[9]Confirmed
Floor area
Not yet sourced

Compute

Chip types
H100[1]Confirmed
Compute (H100-equivalents)
61,100[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Buildings operational
    0Oct 19, 2019[1]→1Oct 1, 2024[1]
  • Status
    Under constructionOct 19, 2019[1]→Operating + expandingOct 1, 2024[1]

Timeline

Construction start: Oct 19, 2019[1]
First operational: Oct 1, 2024[1]
  1. Oct 19, 2019[1]

    Land clearing begins by Peterson Companies for Stack Infrastructure, which is noted in the news and visible on satellite imagery.

  2. Oct 1, 2024118 MW facility power· 1 buildings operational[1]

    Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satellite imagery (a clear image of this can be seen on July 29 via Google Earth).

  3. Feb 14, 2026118 MW facility power· 1 buildings operational[1]

    All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery.

  4. Jan 1, 2028Projected487 MW facility power· 6 buildings operational[1]

    Estimate: All 6 AI data center buildings will be finished in 2028, assuming a groundbreak-to-operational timeline of 18-24 months. One is complete, three are clearly under construction, and the last two data centers are still breaking ground and laying foundations.

  5. May 6, 2025[9]

    Deed recorded for parcel 7595-65-9789.00.

  6. May 6, 2025[9]

    Deed recorded for parcel 7595-75-3611.

  7. May 6, 2025[9]

    Deed recorded for parcel 7595-76-2590.

  8. May 6, 2025[9]

    Deed recorded for parcel 7595-54-7478.

Buildings on this campus

1
  • COPT DC-6Operating · 128,100 sq ft footprint

All claims (provenance audit)

37
FieldValueSourceConfidenceAs ofStatus
NameSTACK Infrastructure NVA02[1] Likely2026-02-14Shown
StatusUnder construction[1] derivedLikely2019-10-19Superseded / alternative
StatusOperating + expanding[1] derivedLikely2024-10-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-02-14Shown
Facility typeAI campus[1] derivedLikely2026-02-14Shown
Address9590 Hornbaker Rd, Manassas, VA 20109[1] Likely2026-02-14Shown
UtilityDominion Energyterritory 19876: VIRGINIA ELECTRIC & POWER CO (INVESTOR OWNED, DOMINION RESOURCE[2] derivedLikely2022Shown
Current facility power118 MW[1] estimatedLikely2026-02-14Shown
Current facility power118 MW[1] estimatedLikely2024-10-01Superseded / alternative
Current IT capacity85 MW[1] estimatedLikely2026-02-14Shown
Current IT capacity85 MW[1] estimatedLikely2024-10-01Superseded / alternative
Planned capacity487 MW[1] estimatedLikely2026-02-14Shown
Estimated annual consumption724 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[4] derivedLikely—Shown
Balancing authorityPJM[2] derivedLikely—Shown
Nearest mapped substationHourglass Substation (230 kV)way/1189694187[5] derivedLikely2026-09-28Shown
Distance to substation2.1 km[5] derivedLikely2026-09-28Shown
Generation queued in county1.35 GW[6] derivedConfirmed2026-09-27Shown
State avg. industrial price10.07¢/kWh[7] Confirmed2026-07Shown
State avg. commercial price11.68¢/kWh[7] Confirmed2026-07Shown
Generation within 50 km2.83 GW[8] derivedConfirmed202502Shown
Buildings (planned)6[1] derivedLikely2026-02-14Shown
Buildings operational1[1] estimatedLikely2026-02-14Shown
Buildings operational0[1] estimatedLikely2019-10-19Superseded / alternative
Buildings operational1[1] estimatedLikely2024-10-01Superseded / alternative
Site area101.2 acres[9] Confirmed2026-09-27Shown
Capital cost / investment$3.2B[1] estimatedLikely2026-02-14Shown
Parcel / land records7595-65-9789.00 (Prince William County)[9] Confirmed2026-09-27Shown
Parcel / land records7595-75-3611 (Prince William County)[9] Confirmed2026-09-27Shown
Parcel / land records7595-76-2590 (Prince William County)[9] Confirmed2026-09-27Shown
Parcel / land records7595-54-7478 (Prince William County)[9] Confirmed2026-09-27Shown
Compute (H100-equivalents)61,100[1] estimatedLikely2026-02-14Shown
Chip typesH100[1] Confirmed2026-02-14Shown
Land acquiredMay 6, 2025[9] derivedConfirmed2026-09-27Shown
Construction startOct 19, 2019[1] derivedLikely2026-02-14Shown
First operationalOct 1, 2024[1] derivedLikely2026-02-14Shown
Expected completionJan 1, 2028[1] estimatedSpeculative2026-02-14Shown