Stream Data Centers DFWA
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityStream Data Centers DFWA
- →substationUnnamed substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.26 km away. Proximity does not establish that it serves the site.
- →transmission138 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.13 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 32.98363, -96.65450
- Address
- County
- Dallas County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Operator
- Utility
Most likely retail provider among 6 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Farmers Electric Coop, INC - (Tx), Trinity Valley Elec Coop INC, Hilco Electric Cooperative, INC., Texas-New Mexico Power CO, Oncor Electric Delivery Company LLC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
36 EIA-reported plants within 50 km.
- Generation queued in county
9 active generation interconnection requests in Dallas County: Storage 817 MW, Other 50 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line · Garland Power & Light | Transmission line | 0.13 km | 138 kV | [1] |
| Lake Hubbard · Luminant Generation Company LLC | Power plant (Natural Gas) | 19.3 km | 915 MW | [6] |
| Ray Olinger · City of Garland - (TX) | Power plant (Natural Gas) | 21 km | 395 MW | [6] |
| Wigeon Whistle Battery Storage Plant · Wigeon Whistle BESS LLC | Power plant (Batteries) | 28.2 km | 120 MW | [6] |
| Forney Energy Center · LaFrontera Holdings LLC | Power plant (Natural Gas) | 29.5 km | 1.77 GW | [6] |
| State Farm Insur Support Center Central · State Farm Mutual Auto Ins Co | Power plant (Petroleum) | 32.1 km | 11 MW | [6] |
| Mountain Creek · Mountain Creek Power, LLC | Power plant (Natural Gas) | 39.1 km | 808 MW | [6] |
| Leon Solar · Cypress Creek Renewables | Power plant (Solar) | 43.4 km | 10 MW | [6] |
| Spencer · City of Garland - (TX) | Power plant (Natural Gas) | 48.3 km | 122 MW | [6] |
| Unnamed substation | Substation | 0.26 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.33 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.88 km | 138 kV | [1] |
| Firewheel Substation · Garland Power & Light | Substation | 1.35 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.5 km | — | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| watermelon 1 energy storageERCOT 27INR0457 · Tempus power management LLC | Storage | In study · proposed 2029-03 | 102 MW | [4] |
| watermelon 2 energy storageERCOT 27INR0458 · Tempus power management LLC | Storage | In study · proposed 2029-03 | 102 MW | [4] |
| watermelon 3 energy storageERCOT 27INR0459 · Tempus power management LLC | Storage | In study · proposed 2029-03 | 102 MW | [4] |
| watermelon 4 energy storageERCOT 27INR0460 · Tempus power management LLC | Storage | In study · proposed 2029-03 | 102 MW | [4] |
| watermelon 5 energy storageERCOT 28INR0255 · Tempus power management LLC | Storage | In study · proposed 2029-03 | 102 MW | [4] |
| watermelon 6 energy storageERCOT 28INR0256 · Tempus power management LLC | Storage | In study · proposed 2029-03 | 102 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
17| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Stream Data Centers DFWAway/1300765126 name=Stream Data Centers DFWA | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Facility type | Colocation | [1] derived | Unverified | 2026-09-27 | Shown |
| Website | https://www.streamdatacenters.com/locations/dallas-data-centers/ | [1] | Likely | 2026-09-27 | Shown |
| Address | 1813 Lookout Drive, Garland, TX 75044 | [1] | Likely | 2026-09-27 | Shown |
| Operator | Stream Data Centersoperator=Stream Data Centers | [1] | Likely | 2026-09-27 | Shown |
| Utility | City of Garland - (Tx)territory 6958: CITY OF GARLAND - (TX) (MUNICIPAL, CITY OF GARLAND - (TX)) | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [3] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1300765155 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 867 MW | [4] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.23 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 281,400 sq ft | [1] derived | Likely | 2026-09-27 | Shown |