DC
/

Unnamed data center

OperatingUnclassifiedBuildingBell County, Texas
10% profile completeness
12 claims from 6 sources
Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Building footprint
145,300 sq ft[1]
Likelyderived
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Operating (community-mapped, unverified)
Low confidence
Project verification
Unverified
Evidence is limited to community map.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Pedernales Electric Coop, INC · ERCOT
Substation: Knob Creek Switching Station (345 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. Energizationimplied by a later stage
  4. OperationalSep 27, 2026
    Community map
    • Sep 27, 2026 · Reported status: operating[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.

Grid path

  1. facility
    Unnamed data center
  2. substation
    Knob Creek Switching Station (345 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 1.37 km away. Proximity does not establish that it serves the site.
  3. transmission
    345 kV line[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.18 km away). Not confirmed as the supply path.
  4. utility
    Pedernales Electric Coop, INC[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    ERCOT[3]
    Service territoryLikely
    Balancing authority: ERCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

QueueRelationshipStageMW req.MW appr.QueuedExpected in servicePOI / TOSource · as of
ERCOT 23INR0248
Limewood Storage · Limewood Bell Renewables LLC · Storage
Generation at a nearby substation
Unverified
Queue POI “3420 Temple Pecan Creek 138kV” names Temple Switching Station, a substation mapped 2.56 km from the site (OSM). Sharing a POI does not mean this generation serves the facility.
Interconnection agreement executed
SS Completed, FIS Started, IA
50——Dec 29, 20283420 Temple Pecan Creek 138kV[4] Sep 1, 2026
ERCOT 23INR0249
Limewood Solar · Limewood Bell Renewables, LLC · Solar
Generation at a nearby substation
Unverified
Queue POI “3420 Temple Pecan Creek 138kV” names Temple Switching Station, a substation mapped 2.56 km from the site (OSM). Sharing a POI does not mean this generation serves the facility.
In service
SS Completed, FIS Completed, IA
204.6——In service Aug 10, 20263420 Temple Pecan Creek 138kV[4] Sep 1, 2026
ERCOT 26INR0465
Lavita BESS · Lavita BESS, LLC · Storage
Generation at a nearby substation
Unverified
Queue POI “Tap 345kV Temple Pecan Creek (3412) - Temple Switch (3414) 345kV ckt 2” names Temple Switching Station, a substation mapped 2.56 km from the site (OSM). Sharing a POI does not mean this generation serves the facility.
System impact study
SS Completed, FIS Started, No IA
606——Jul 1, 2028Tap 345kV Temple Pecan Creek (3412) - Temple Switch (3414) 345kV ckt 2[4] Sep 1, 2026
ERCOT 29INR0206
Riviera Gas · BKV-BPP Power · Gas
Generation at a nearby substation
Unverified
Queue POI “Tap #3414 Temple Switch - #3780 Tower Switch 345kV DCKT Line” names Temple Switching Station, a substation mapped 2.56 km from the site (OSM). Sharing a POI does not mean this generation serves the facility.
System impact study
SS Completed, FIS Started, No IA
636.9——Jun 14, 2030Tap #3414 Temple Switch - #3780 Tower Switch 345kV DCKT Line[4] Sep 1, 2026

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
31.05748, -97.29841
County
Bell County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility

Most likely retail provider among 5 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Heart of Texas Electric Coop, Bartlett Electric Coop, INC, Oncor Electric Delivery Company LLC, City of Bartlett - (Tx).

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
ERCOT[3]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
ERCO[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Knob Creek Switching Station (345 kV)[1]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
1.4 km[1]Likelyderived
Highest-voltage line nearby
345 kV[1]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
7.07¢/kWh[5]Confirmed

Texas statewide average, July 2026.

State avg. commercial price
8.47¢/kWh[5]Confirmed

Texas statewide average, July 2026.

Generation within 50 km
3.34 GW[6]Confirmedderived

20 EIA-reported plants within 50 km.

Generation queued in county
2.34 GW[4]Confirmedderived

9 active generation interconnection requests in Bell County: Storage 1,439 MW, Gas 637 MW, Solar 264 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
345 kV lineTransmission line0.18 km345 kV[1]
69 kV lineTransmission line0.19 km69 kV[1]
138 kV lineTransmission line0.21 km138 kV[1]
Temple Power Station · Temple Generation Holdings LLCPower plant (Natural Gas)1.8 km1.58 GW[6]
Five Wells Solar Center - Hybrid · Five Wells Solar Center, LLCPower plant (Solar)7.5 km579 MW[6]
Big Elm Solar · Big Elm Solar, LLCPower plant (Solar)12.1 km200 MW[6]
Orion III Solar Project · Ben Milam Solar 3 LLCPower plant (Solar)19.8 km250 MW[6]
Orion I Solar Project · Ben Milam Solar 1 LLCPower plant (Solar)29.1 km200 MW[6]
Orion II Solar Project · Ben Milam Solar 2 LLCPower plant (Solar)34.8 km250 MW[6]
Bpl Crown Solar LLC · BPL Crown Solar LLCPower plant (Solar)38.1 km100 MW[6]
Bpl Sol Solar LLC · BPL Sol Solar LLCPower plant (Solar)38.1 km100 MW[6]
Knob Creek Switching Station · OncorSubstation1.37 km345 kV[1]
Panda Temple 1 Substation · Panda PowerSubstation1.59 km345 kV[1]
Panda Temple 2 Substation · Panda PowerSubstation1.73 km345 kV[1]
Temple Switching Station · OncorSubstation2.56 km345 kV[1]
Largest queued generation in this countyFuelQueue statusMWSource
Riviera GasERCOT 29INR0206 · BKV-BPP Power GasIn study · proposed 2030-06637 MW[4]
Lavita BESSERCOT 26INR0465 · Lavita BESS, LLCStorageIn study · proposed 2028-07606 MW[4]
Bell County Morgan StorageERCOT 26INR0615 · DM-BCTRM, LLCStorageIn study · proposed 2029-12256 MW[4]
Bell County Leifester StorageERCOT 26INR0614 · DM-BCRCML, LLCStorageIn study · proposed 2029-09205 MW[4]
Goldeneye BESSERCOT 25INR0100 · Black Mountain Energy Storage IIStorageIA signed · proposed 2028-05202 MW[4]
Cosper SolarERCOT 25INR0281 · Gransolar Texas Twenty LLCSolarIA signed · proposed 2027-11148 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
145,300 sq ft[1]Likelyderived

Computed from the mapped OSM building outline.

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

All claims (provenance audit)

12
FieldValueSourceConfidenceAs ofStatus
StatusOperating[1] derivedUnverified2026-09-27Shown
UtilityPedernales Electric Coop, INCterritory 14626: PEDERNALES ELECTRIC COOP, INC (COOPERATIVE, PEDERNALES ELECTRIC[2] derivedUnverified2022Shown
ISO / RTOERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.[3] derivedLikely—Shown
Balancing authorityERCO[2] derivedLikely—Shown
Nearest mapped substationKnob Creek Switching Station (345 kV)way/462426907[1] derivedLikely2026-09-28Shown
Distance to substation1.4 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[1] derivedLikely2026-09-28Shown
Generation queued in county2.34 GW[4] derivedConfirmed2026-09-01Shown
State avg. industrial price7.07¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price8.47¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km3.34 GW[6] derivedConfirmed202502Shown
Building footprint145,300 sq ft[1] derivedLikely2026-09-27Shown