Unnamed data center
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityUnnamed data center
- →substationUnnamed substation (34.5 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.17 km away. Proximity does not establish that it serves the site.
- →transmission138 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.14 km away). Not confirmed as the supply path.
- →utilityMidwest Energy Cooperative[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.99311, -86.09876
- County
- Cass County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Wolverine Power Supply Coop, City of Dowagiac.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Michigan statewide average, July 2026.
- State avg. commercial price
Michigan statewide average, July 2026.
- Generation within 50 km
25 EIA-reported plants within 50 km.
- Generation queued in county
12 active generation interconnection requests in Cass County: Solar 1,439 MW, Solar + storage 220 MW, Storage 150 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.14 km | 138 kV | [1] |
| 69 kV line | Transmission line | 0.58 km | 69 kV | [1] |
| Indeck Niles Energy Center · Indeck Niles, LLC | Power plant (Natural Gas) | 17.8 km | 1.08 GW | [6] |
| St. Joseph Solar · Indiana Michigan Power Co | Power plant (Solar) | 29.1 km | 20 MW | [6] |
| University of Notre Dame · University of Notre Dame | Power plant (Natural Gas) | 33.6 km | 39 MW | [6] |
| Donald C Cook · Indiana Michigan Power Co | Power plant (Nuclear) | 38.6 km | 2.18 GW | [6] |
| New Covert Generating Facility · Consumers Energy Co - (MI) | Power plant (Natural Gas) | 40 km | 1.59 GW | [6] |
| Honeysuckle Solar Farm · Lightsource Renewable Energy Asset Management, LLC | Power plant (Solar) | 42.9 km | 150 MW | [6] |
| St Joseph Energy Center · St Joseph Energy Center LLC | Power plant (Natural Gas) | 45.4 km | 715 MW | [6] |
| Olivepv · Indiana Michigan Power Co | Power plant (Solar) | 46 km | 5 MW | [6] |
| Unnamed substation | Substation | 0.17 km | 34.5 kV | [1] |
| Unnamed substation | Substation | 0.3 km | 34.5 kV | [1] |
| Unnamed substation | Substation | 0.71 km | 34.5 kV | [1] |
| Colby Substation · American Electric Power | Substation | 0.78 km | 138 kV | [1] |
| Poplar St. Substation · City of Dowagiac Eletric Dept. | Substation | 1.75 km | 34.5 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J4102 at WEEDS LAKE - HIPLE 345.0kVMISO J4102 | Solar | In study · proposed 2029-08 | 539 MW | [7] |
| Stinger 138 kVPJM AF2-396 - moved to TC1 | Solar + storage | In study · proposed 2023-12 | 200 MW | [4] |
| Wingstem Solar Energy FarmPJM AE1-170 | Solar | Suspended · proposed 2025-12 | 150 MW | [4] |
| Kenzie Creek-Stone Lake 69 kVPJM AF2-083 | Solar | In study · proposed 2022-10 | 150 MW | [4] |
| Kenzie Creek-Colby 138 kVPJM AH1-309 | Solar | In study · proposed 2023-12 | 150 MW | [4] |
| Granger - Ontwa 138 kVPJM AI1-166 | Storage | In study · proposed 2028-12 | 150 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
12| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Utility | Midwest Energy Cooperativeterritory 12377: MIDWEST ENERGY COOPERATIVE (COOPERATIVE, MIDWEST ENERGY COOPERA | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (34.5 kV)way/1242534297 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.81 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.81¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 16.46¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 5.82 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 598,500 sq ft | [1] derived | Likely | 2026-09-27 | Shown |