Vantage TX1
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationFeb 15, 2026
Satellite imagery
- Feb 15, 2026 · Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the [1]
- OperationalFeb 15, 2026
Satellite imagery
- Feb 15, 2026 · Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the [1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityVantage TX1
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps CPS Energy substation 0.49 km away
- →transmission345 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.92 km away). Not confirmed as the supply path.
- →utilityPedernales Electric Coop, INC[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 29.41612, -98.78986
- Address
- County
- Bexar County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 4 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Guadalupe Valley Elec Coop INC, Karnes Electric Coop INC, Bandera Electric Coop, INC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-08-31); not necessarily full build-out.
- Estimated annual consumption
45 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
20 EIA-reported plants within 50 km.
- Generation queued in county
21 active generation interconnection requests in Bexar County: Storage 4,771 MW, Solar 152 MW, Gas 35 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.46 km | 138 kV | [5] |
| 345 kV line | Transmission line | 0.92 km | 345 kV | [5] |
| Leon Creek · City of San Antonio - (TX) | Power plant (Natural Gas) | 21.9 km | 184 MW | [8] |
| Oci Alamo Solar I Hybrid · OCI Energy LLC | Power plant (Solar) | 37.1 km | 41 MW | [8] |
| Arthur Von Rosenberg · City of San Antonio - (TX) | Power plant (Natural Gas) | 43.1 km | 518 MW | [8] |
| V H Braunig · City of San Antonio - (TX) | Power plant (Natural Gas) | 43.3 km | 1.05 GW | [8] |
| O W Sommers · City of San Antonio - (TX) | Power plant (Natural Gas) | 46.7 km | 830 MW | [8] |
| J K Spruce · City of San Antonio - (TX) | Power plant (Coal) | 47 km | 1.35 GW | [8] |
| Oci Alamo 4, LLC · Consolidated Edison Development Inc. | Power plant (Solar) | 48 km | 40 MW | [8] |
| Ebony Energy Storage · Ebony Energy Storage, LLC | Power plant (Batteries) | 49.6 km | 200 MW | [8] |
| CPS Energy substation · CPS Energy | Substation | 0.49 km | 138 kV | [5] |
| Texas Research Substation · CPS Energy | Substation | 0.53 km | 138 kV | [5] |
| Rafter Substation · CPS Energy | Substation | 1.58 km | 138 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Howard Road BESSERCOT 29INR0173 · Project Fast Flow LLC | Storage | In study · proposed 2028-04 | 618 MW | [6] |
| Orbit Energy StorageERCOT 27INR0082 · GCI Orbit Energy Storage, LLC | Storage | In study · proposed 2027-06 | 502 MW | [6] |
| Bernice Energy StorageERCOT 27INR0294 · Bernice Energy Storage LLC | Storage | In study · proposed 2029-02 | 403 MW | [6] |
| Mission Station Energy Storage IERCOT 28INR0474 · Mission Station LLC | Storage | In study · proposed 2030-05 | 375 MW | [6] |
| Mission Station Energy Storage IIERCOT 28INR0475 · Mission Station LLC | Storage | In study · proposed 2030-05 | 375 MW | [6] |
| Quela BESSERCOT 22INR0423 · BRP Quela BESS LLC | Storage | In study · proposed 2027-12 | 301 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startDec 15, 2023[1]
- First operationalFeb 15, 2026[1]
- Expected completionAug 31, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-08-31); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Sum of 3 building outlines mapped in OpenStreetMap within this campus.
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Dec 15, 2023[1]
Land clearing begins for both Building 1 & Building 2
Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, based on the appearance, we believe it is operational. Reported IT power of 32 MW. Source
Estimated construction completion date of Building 2. Construction Project Filing
Buildings on this campus
4- Vantage San Antonio IOperating
- Vantage TX11Operating · 123,300 sq ft footprint
- Vantage TX12Operating · 123,300 sq ft footprint
- Vantage TX12Operating · 123,300 sq ft footprint
All claims (provenance audit)
29| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Vantage TX1 | [1] | Likely | 2026-02-15 | Shown |
| Status | Under construction | [1] derived | Likely | 2023-12-15 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-15 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-02-15 | Shown |
| Address | 14720 Omicron Dr, San Antonio, TX 78245 | [1] | Likely | 2026-02-15 | Shown |
| Utility | Pedernales Electric Coop, INCterritory 14626: PEDERNALES ELECTRIC COOP, INC (COOPERATIVE, PEDERNALES ELECTRIC | [2] derived | Unverified | 2022 | Shown |
| Current facility power | 45 MW | [1] estimated | Likely | 2026-02-15 | Shown |
| Current IT capacity | 32 MW | [1] estimated | Likely | 2026-02-15 | Shown |
| Planned capacity | 179 MW | [1] estimated | Likely | 2026-02-15 | Shown |
| Estimated annual consumption | 276 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [4] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | CPS Energy substation (138 kV)way/1533313387 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.5 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 4.96 GW | [6] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.3 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-02-15 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-02-15 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2023-12-15 | Superseded / alternative |
| Building footprint | 310,200 sq ftway/1010260674 way/1344369111 way/1533148752 | [5] derived | Likely | 2026-09-27 | Shown |
| Capital cost / investment | $1.2B | [1] estimated | Likely | 2026-02-15 | Shown |
| Compute (H100-equivalents) | 38,700 | [1] estimated | Likely | 2026-02-15 | Shown |
| Chip types | B200 | [1] | Confirmed | 2026-02-15 | Shown |
| Construction start | Dec 15, 2023 | [1] derived | Likely | 2026-02-15 | Shown |
| First operational | Feb 15, 2026 | [1] derived | Likely | 2026-02-15 | Shown |
| Expected completion | Aug 31, 2027 | [1] estimated | Speculative | 2026-02-15 | Shown |