VeriSign Incorporated

OperatingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.UnclassifiedBuildingDulles, Loudoun County, Virginia

VeriSign Incorporated is an operating data center in Dulles, Virginia. Current power: 8 MW (estimated). Verification: verified operating. 8 cited sources.

40% profile completeness
22 claims from 8 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Oct 12, 2026
Follow

Get changes to VeriSign Incorporated

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “VeriSign Incorporated.” /facilities/verisign-incorporated-dulles-va. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_verisign_incorporated_dulles_va_2026,
  title = {{VeriSign Incorporated}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/verisign-incorporated-dulles-va}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
8 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likely
Planned capacity
Not yet sourced
Floor area
136,900 sq ft[2]
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by permit / site plan.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Not identified · PJM
Substation: Pacific Substation (230 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
8 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Reported
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. PermittingOct 12, 2026
    Permit / site plan
    • Oct 12, 2026 · Permit / case B10012090100[2]
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. EnergizationOct 12, 2026
    Community map
    • Oct 12, 2026 · Power in use reported: 8 MW[1]
  4. OperationalOct 12, 2026
    Community map · Permit / site plan
    • Oct 12, 2026 · Reported status: operating[1]
    • Oct 12, 2026 · Reported status: operating[2]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Permit / site plan, Community map.

Grid path

  1. facility
    VeriSign Incorporated
  2. substation
    Pacific Substation (230 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 0.51 km away. Proximity does not establish that it serves the site.
  3. transmission
    Pacific Loop (230 kV)[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.19 km away). Not confirmed as the supply path.
  4. utility
    Not identified
    UnknownUnverified
  5. ISO / RTO
    PJM[4]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling

Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source

On-site generation & air permits

Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates

Not yet collected: we haven't found a source for a large-load tariff or commission docket for the serving utility. Know one? Add a source

Location & imagery

Approximate

Location is approximate (approximate); the marker does not identify the exact site.

Coordinates
38.99778, -77.44386
Address
22340 Dresden Street, Dulles, VA 20166[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likely
County
Loudoun County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Not identified

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Property owner of record

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
8 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likely
Estimated annual consumption
49 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated

8 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Pacific Substation (230 kV)[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.5 km[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
230 kV[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.07¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Virginia statewide average, July 2026.

State avg. commercial price
11.68¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Virginia statewide average, July 2026.

Generation within 50 km
1.65 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

64 EIA-reported plants within 50 km.

Generation queued in county
1.04 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived

11 active generation interconnection requests in Loudoun County: Storage 940 MW, Solar 100 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Pacific Loop · Virginia Electric & Power CompanyTransmission line0.19 km230 kV[1]
2137 · Virginia Electric & Power CompanyTransmission line0.54 km230 kV[1]
230 kV lineTransmission line1.07 km230 kV[1]
2152;2170 · Virginia Electric & Power CompanyTransmission line1.49 km230 kV[1]
2152;2165 · Virginia Electric & Power CompanyTransmission line1.53 km230 kV[1]
2203;2214 · Virginia Electric & Power CompanyTransmission line1.56 km230 kV[1]
Potomac Energy Center, LLC · Potomac Energy Center LLCPower plant (Natural Gas)11 km766 MW[8]
Montgomery County Resource Recovery · Covanta Montgomery, Inc.Power plant (Biomass)22.6 km54 MW[8]
Dickerson Power · Dickerson Power, LLCPower plant (Natural Gas)23.6 km299 MW[8]
Nih Cogeneration Facility · National Institutes of HealthPower plant (Natural Gas)30.2 km28 MW[8]
Covanta Alexandria/Arlington Energy · Covanta Alexandria/ArlingtonPower plant (Biomass)34.9 km29 MW[8]
Covanta Fairfax Energy · Covanta Fairfax IncPower plant (Biomass)38 km98 MW[8]
Central Utility Plant At White Oak · GSA Metropolitan Service CenterPower plant (Natural Gas)40.1 km54 MW[8]
Blake Solar Plant · Horus West Virginia 1, LLCPower plant (Solar)44.8 km80 MW[8]
Pacific Substation · Dominion EnergySubstation0.51 km230 kV[1]
Unnamed substationSubstation0.52 km—[1]
Ocean Court SubstationSubstation0.58 km230 kV[1]
Global Plaza Substation · Dominion EnergySubstation0.94 km230 kV[1]
Unnamed substationSubstation0.99 km—[1]
Lockridge Substation · Virginia Electric & Power CompanySubstation1.13 km230 kV[1]
Largest queued generation in this countyFuelQueue statusMWSource
Loudoun 230 kVPJM AG2-285StorageIn study · proposed 2023-12150 MW[6]
Beaumeade 230 kVPJM AG2-287StorageIn study · proposed 2023-12150 MW[6]
New Road StoragePJM AE2-019StorageIA signed · proposed 2026-12120 MW[6]
Dulles SolarPJM AF1-147SolarIA signed · proposed 2023-12100 MW[6]
Roundtable 230 kVPJM AG2-307StorageIn study · proposed 2023-12100 MW[6]
Shelhorn 230 kVPJM AG2-323StorageIn study · proposed 2023-12100 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —
Permit / case numbers
B10012090100[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

ParcelRecord ownerAcresZoning / useBuilding sq ftSource
044174648000
Loudoun County, VA
VERISIGN INC
Project: Broad Run Technology Park
14.45IP · Data Center136,908
built
[2]
Site area
14.5 acres[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

Legal acreage of the parcel(s).

Zoning
IP[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Land use
Data Center[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Annual property tax
Not yet sourced

Size

Floor area
136,900 sq ft[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

Building area on the county's data-center parcel inventory (from building permits).

Parcel / land records
MCPI 044174648000 (Loudoun County)[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

All claims (provenance audit)

22
FieldValueSourceConfidenceAs ofStatus
NameVeriSign Incorporatedrelation/12893102 name=VeriSign Incorporated[1] Likely2026-10-12Shown
StatusOperating[1] derivedUnverified2026-10-12Shown
StatusOperating[2] derivedConfirmed2026-10-12Shown
Address22340 Dresden Street, Dulles, VA 20166[1] Likely2026-10-12Shown
Property owner of recordVerisign INCMCPI 044174648000: VERISIGN INC[2] Confirmed2026-10-12Shown
Current facility power8 MWinput:electricity=8 MW[1] Likely2026-10-12Shown
Estimated annual consumption49 GWh/yr[3] estimatedSpeculative2026-10-12Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[4] derivedLikely—Shown
Balancing authorityPJM[5] derivedLikely—Shown
Nearest mapped substationPacific Substation (230 kV)way/686326407[1] derivedLikely2026-09-28Shown
Distance to substation0.5 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby230 kV[1] derivedLikely2026-09-28Shown
Generation queued in county1.04 GW[6] derivedConfirmed2026-10-12Shown
State avg. industrial price10.07¢/kWh[7] Confirmed2026-07Shown
State avg. commercial price11.68¢/kWh[7] Confirmed2026-07Shown
Generation within 50 km1.65 GW[8] derivedConfirmed202502Shown
Permit / case numbersB10012090100[2] Confirmed2026-10-12Shown
Floor area136,900 sq ft[2] Confirmed2026-10-12Shown
Site area14.5 acres[2] Confirmed2026-10-12Shown
Parcel / land recordsMCPI 044174648000 (Loudoun County)[2] Confirmed2026-10-12Shown
ZoningIP[2] Confirmed2026-10-12Shown
Land useData Center[2] Confirmed2026-10-12Shown