What changed — Alabama

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. Jun 18, 2026
    Meta Montgomery · AL
    • Buildings operational: 0 → 2
    • Status: Under construction → Operating + expanding
    • New capacity online: We estimate Buildings 1 and 2 are operational.
    Source: Epoch AI
  2. Jun 2, 2026
    Meta Huntsville · AL
    • Current IT capacity: 78 MW → 146 MW
    • Current facility power: 105 MW → 198 MW
    • Buildings operational: 1 → 2
    • Status: Operating + expanding → Operating
    • New capacity online: We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.
    Source: Epoch AI
  3. Mar 4, 2026
    Meta Huntsville · AL
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: We estimate that Building 1 is operational 30 days after the appearance of color artifacts on the fans.
    Source: Epoch AI
  4. Mar 1, 2025
    Meta Montgomery · AL
    • Construction started: Land clearing begins.
    Source: Epoch AI