What changed — Georgia
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- Jul 10, 2026
- Jun 14, 2026Microsoft Fairwater Atlanta · GA
- Current IT capacity: 321 MW → 636 MW
- Current facility power: 433 MW → 859 MW
- Buildings operational: 2 → 4
- Status: Operating + expanding → Operating
- New capacity online: Building 3 and 4 are operational.
Source: Epoch AI - Feb 20, 2026CoreWeave Dalton 1 & 2 · GA
- Buildings operational: 0 → 1
- Status: Under construction → Operating
- New capacity online: Building 1 is operational, given it was announced completed 4 months ago and looks completed in satellite imagery. All cooling/mechanical rows are installed, with no obvious active building construction visible.
Source: Epoch AI - Oct 14, 2025Microsoft Fairwater Atlanta · GA
- Buildings operational: 0 → 2
- Status: Under construction → Operating + expanding
- New capacity online: Building 1 and 2 are operational. Building 1 looked operational sooner, but the buildings are paired in the Fairwater design. The roof of Building 4 is almost complete, while mechanical equipment is still being instal…
Source: Epoch AI - Feb 20, 2025xAI QTS Atlanta · GA
- Buildings operational: 0 → 1
- Status: Under construction → Operating + expanding
- New capacity online: xAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time. This date is a tentative estimate: Business Insider reported the buildout in February 2025, so the cluster lik…
Source: Epoch AI - Jun 3, 2024CoreWeave Dalton 1 & 2 · GA
- Construction started: According to a few sources, Core Scientific announced that they're rebuilding their existing Dalton 1 (and we're assuming 2) datacenter to run AI using CoreWeave's GPUs, of which contract was first signed on this date…
Source: Epoch AI - Jan 23, 2024xAI QTS Atlanta · GA
- Construction started: X Corp's $700 million investment in AI training hardware for the Atlanta data center is approved by the Development Authority of Fulton County (bond resolution fact sheet).
Source: Epoch AI