What changed — Oklahoma

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. Sep 6, 2026
    Google Pryor (North) · OK
    • Current IT capacity: 53 MW → 368 MW
    • Current facility power: 63 MW → 442 MW
    • Buildings operational: 1 → 2
    • Status: Operating + expanding → Operating
    • New capacity online: Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.
    Source: Epoch AI
  2. Nov 18, 2024
    CoreWeave Muskogee OK · OK
    • Construction started: Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center. Core Scientific says the site will provide about 70 MW of critical IT load for CoreWeave's NVIDIA…
    Source: Epoch AI
  3. Jul 19, 2024
    Google Pryor (North) · OK
    • Construction started: Building 1 is operational, based on default roof-to-operational time.
    Source: Epoch AI