Data centers in Clay County, Missouri
Datacenter Source tracks 3 data centers in Clay County, Missouri. Facilities that disclose power add up to 126 MW online and 0 MW in the pipeline — floors, since 33% report a figure. 3 interconnection-queue requests were filed in the county in the last two years.
Follow
Get changes to Clay County, Missouri
Or subscribe in a feed reader: RSS / Atom
Facilities
- Google Kansas City East AI campusOperating126 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Meta Data Center HyperscaleOperating
- Unnamed data center UnclassifiedOperating
Interconnection-queue requests filed here (last two years)
Requests to connect generation or large loads, as the ISO/RTO publishes them. Filing is an application, not a commitment to build.
- Jan 23, 2026 · SPP AFS NJG-2026-001 Storage generation — AFS NJG-2026-001 at Shoal Creek 161kV substation10 MW · None ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.source
- Mar 1, 2025 · SPP GEN-2024-370 Storage generation — GEN-2024-370 at Smithville 161 kV Substation250 MW · DISIS STAGE ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.source
- Oct 30, 2024 · SPP GEN-2024-090 Storage generation — GEN-2024-090 at Smithville 161 kV Substation100 MW · DISIS STAGE ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.source
Local impact
Water, on-site generation and air permits, incentives, regulatory events and large-load tariffs, where a source documents them. Counts are of sourced records, not of the state's totals.
Evaporative (cooling towers): 1 site EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Not yet collected
- Evergy Missouri West: Large Load Power Service (LLPS) rate plan for loads over 75 MW ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Missouri Public Service Commission · Nov 2025 · source
Not yet collected
Recent changes
- Aug 1, 2026 · Google Kansas City East EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 0 → 1
- Aug 1, 2026 · Google Kansas City East EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Status: Under construction → Operating
- Aug 1, 2026 · Google Kansas City East EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. New capacity online: Building 1 operational. Estimated based on present construction progress and typical timelines.
- Jan 1, 2024 · Google Kansas City East EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Construction started: Land clearing has begun for the site