Data centers in Sarpy County, Nebraska
Datacenter Source tracks 14 data centers in Sarpy County, Nebraska. Facilities that disclose power add up to 389 MW online and 0 MW in the pipeline — floors, since 14% report a figure.
Follow
Get changes to Sarpy County, Nebraska
Or subscribe in a feed reader: RSS / Atom
Facilities
- Google Papillion AI campusOperating284 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Meta Sarpy AI campus · SpringfieldOperating105 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Fidelity UnclassifiedOperating
- Google HyperscaleOperating
- Google HyperscaleOperating
- Google HyperscaleOperating
- Google HyperscaleOperating
- Meta Sarpy Data center HyperscaleOperating
- Meta Sarpy Data center HyperscaleOperating
- Meta Sarpy Data center HyperscaleOperating
- Meta Sarpy Data center HyperscaleOperating
- Meta Sarpy Data center HyperscaleOperating
- Travelers Insurance UnclassifiedOperating
- Yahoo UnclassifiedOperating
Interconnection-queue requests filed here (last two years)
Requests to connect generation or large loads, as the ISO/RTO publishes them. Filing is an application, not a commitment to build.
No dated queue filings for this county in the files we ingest (some ISOs don't publish a county or filing date).
Local impact
Water, on-site generation and air permits, incentives, regulatory events and large-load tariffs, where a source documents them. Counts are of sourced records, not of the state's totals.
0.1 M gal/day modeled at 2 sites EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Evaporative (cooling towers): 1 site EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Not yet collected
Not yet collected for this state's utilities.
Not yet collected
Recent changes
- Aug 2, 2026 · Meta Sarpy EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 0 → 1
- Aug 2, 2026 · Meta Sarpy EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Status: Under construction → Operating
- Aug 2, 2026 · Meta Sarpy EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. New capacity online: Building 1 is operational (estimate).
- May 4, 2026 · Google Papillion EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Status: Operating + expanding → Operating
- Aug 3, 2024 · Google Papillion EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current IT capacity: 79 MW → 237 MW
- Aug 3, 2024 · Google Papillion EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Current facility power: 95 MW → 284 MW
- Aug 3, 2024 · Google Papillion EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Buildings operational: 1 → 3
- Aug 3, 2024 · Google Papillion EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. New capacity online: Building 3 looks operational.
- Aug 1, 2024 · Meta Sarpy EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. Construction started: Building 1 grading underway.