Amazon AWS Data Center
Also known as Project Rainier
Part of Anthropic-Amazon New Carlisle
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityAmazon AWS Data Center
- →substationUnnamed substation (345 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.22 km away. Proximity does not establish that it serves the site.
- →transmission345 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.12 km away). Not confirmed as the supply path.
- →utilityIndiana Michigan Power (AEP)[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.66834, -86.47197
- County
- St. Joseph County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Owner
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Indiana statewide average, July 2026.
- State avg. commercial price
Indiana statewide average, July 2026.
- Generation within 50 km
22 EIA-reported plants within 50 km.
- Generation queued in county
14 active generation interconnection requests in St. Joseph County: Solar 790 MW, Gas 786 MW, Solar + storage 588 MW, Storage 542 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 345 kV line | Transmission line | 0.12 km | 345 kV | [1] |
| St Joseph Energy Center · St Joseph Energy Center LLC | Power plant (Natural Gas) | 3.5 km | 715 MW | [6] |
| Honeysuckle Solar Farm · Lightsource Renewable Energy Asset Management, LLC | Power plant (Solar) | 5.7 km | 150 MW | [6] |
| University of Notre Dame · University of Notre Dame | Power plant (Natural Gas) | 20.1 km | 39 MW | [6] |
| Indeck Niles Energy Center · Indeck Niles, LLC | Power plant (Natural Gas) | 29.9 km | 1.08 GW | [6] |
| St. Joseph Solar · Indiana Michigan Power Co | Power plant (Solar) | 31 km | 20 MW | [6] |
| Bremen · Indiana Municipal Power Agency | Power plant (Solar) | 34.3 km | 7 MW | [6] |
| Donald C Cook · Indiana Michigan Power Co | Power plant (Nuclear) | 35 km | 2.18 GW | [6] |
| Michigan City · Northern Indiana Pub Serv Co | Power plant (Coal) | 36.7 km | 455 MW | [6] |
| Unnamed substation | Substation | 0.22 km | 345 kV | [1] |
| Unnamed substation | Substation | 2.35 km | 345 kV | [1] |
| Unnamed substation | Substation | 2.37 km | 345 kV | [1] |
| Unnamed substation | Substation | 2.97 km | 34.5 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Elderberry 345 kVPJM AG2-562 | Gas | In study · proposed 2022-10 | 786 MW | [4] |
| Olive - Dumont 345 kVPJM AH2-112 | Solar + storage | In study · proposed 2026-02 | 250 MW | [4] |
| Northern St. Joseph 138 kVPJM AH2-347 | Storage | In study · proposed 2025-03 | 200 MW | [4] |
| New Carlisle 138 kVPJM AH1-479 | Storage | In study · proposed 2023-09 | 192 MW | [4] |
| Honeysuckle Solar ProjectPJM AF1-158 | Solar + storage | Under construction · proposed 2025-01 | 150 MW | [4] |
| Dumont 345 kVPJM AG2-230 | Solar | In study · proposed 2024-12 | 150 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Site area
Area of the mapped OSM site outline.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
Other buildings on this campus
1- Anthropic-Amazon New CarlisleOperating · 1.47M sq ft footprint
All claims (provenance audit)
16| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Amazon AWS Data Centerway/1303947602 name=Amazon AWS Data Center | [1] | Likely | 2026-09-27 | Shown |
| Also known as | Project Rainieralt_name=Project Rainier | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-09-27 | Shown |
| Owner | Amazon Web Servicesowner=Amazon | [1] | Likely | 2026-09-27 | Shown |
| Utility | Indiana Michigan Power (AEP)territory 9324: INDIANA MICHIGAN POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POW | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (345 kV)way/1463187602 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 2.71 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.16¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.30¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.7 GW | [6] derived | Confirmed | 202502 | Shown |
| Site area | 289.2 acres | [1] derived | Likely | 2026-09-27 | Shown |